1 / 10

ALMA Update: October 2004-October 2005

ALMA Update: October 2004-October 2005. Bob Dickman ALMA Staff Associate Division of Astronomical Sciences. Events Reviewed. Antenna procurement Rebaselining Cost Review Near Future. Rebaselining. Fall 2004: Rebaselining begins

benjamin
Download Presentation

ALMA Update: October 2004-October 2005

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ALMA Update: October 2004-October 2005 Bob Dickman ALMA Staff Associate Division of Astronomical Sciences

  2. Events Reviewed • Antenna procurement • Rebaselining • Cost Review • Near Future

  3. Rebaselining • Fall 2004: Rebaselining begins • March 2002 project baseline antedates formal project agreements and Japanese participation • September 2005: “Final” re-baseline cost estimate (JAO) • Assumptions • Common antenna type, ESO maintains procurement schedule, and 50-element array starting point • Increase in cost: • Antennas • Other areas • List of possible changes/descopes/scrubs • NSF working hard to buttress overruns: descopes, considering deferrable work, additional partnerships • November 2005 goal: New Project Baseline (Scope, Cost and Schedule) in place

  4. Rebaselining: Cost Escalation Sources • Antennas • Delay for coordinated procurement • Commodity price increases: oil, steel, nickel • Site • Booming Chilean economy • Dollar/peso exchange rates • Management • Joint ALMA Office, including Project Management & Control System (PMCS) • Costs of partnership • Systems Engineering and Integration • Complexity of project • Other (e.g., missing scope, etc.)

  5. Cost Review • Lehman-style cost review • Review requested by ALMA Board • Report will be passed on to NSF and ESO Council • 4 days: October 13-16, 2005 • Detailed assessment of • Cost • Schedule • Management • Initial assessment of integrating Japan Enhanced ALMA; early operations; operations • Panel: • Chair: Steve Beckwith • Vice-Chair: Thijs de Graauw • 20-member panel • 7 members each nominated by NA and ESO • 4 members nominated by Japan • 2 members nominated by Chile • Report timed to fit needs of ALMA Board, NSF

  6. Antenna Procurement: I • Parallel procurement required by different legal regimes and practices of partners • Each partner provides half the total number of antennas • Highly coordinated, based on purchase of two prototypes • Goal is manufacture of a single design • Start: December 2003. Bumps in the road: • Prototype performance: • Late questions about (mainly) one prototype arose Summer-Fall 2004 • Extended testing program given to JAO; settled in early 2005 (both prototypes are excellent) • Coordinated procurement broke down in June 2005 with the interruption of the ESO procurement

  7. Antenna Procurement: II • In June 2005, ALMA Board urged NSF/AUI/NRAO to proceed with a unilateral NA procurement • This approach was supported by ESO Council • NRAO signed antenna contract July 11, 2005 • Significantly higher costs than even 1 year earlier: • Commodity cost increases • Assume all NRE (recoverable) • Loss of quantity discount (recoverable)

  8. Antenna Procurement: III • ESO making rapid progress on procurement • NSF action has accelerated process • On schedule to complete by end of October • ESO Council endorsed a 50-element array • Both prototype designs still in the running in Europe

  9. Immediate Future: Milestones • ALMA Cost review: October 13-16 • ALMA Board acts on ESO antenna choice: November 1 • NSF-USG decision process to select and authorize new baseline: • October 2005 - March 2006 • New Baseline put in place

  10. Challenges • Operations Costs • U.S. Cost increase  Non-Defense discretionary budgetary climate

More Related