1 / 50

Reversing Road Diet – the East 14th Street North Area Reconfiguration Project

Reversing Road Diet – the East 14th Street North Area Reconfiguration Project. MTC Technology Transfer Program Seminar on Road Diets Reh-Lin N. Chen, City of San Leandro March 19, 2008. EAST 14 TH STREET NORTH AREA STUDY. GOALS & OBJECTIVES BACKGROUND DATA ANALYSES ALTERNATIVES

bernad
Download Presentation

Reversing Road Diet – the East 14th Street North Area Reconfiguration Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Reversing Road Diet – the East 14th Street North Area Reconfiguration Project MTC Technology Transfer Program Seminar on Road Diets Reh-Lin N. Chen, City of San Leandro March 19, 2008

  2. EAST 14TH STREET NORTH AREA STUDY • GOALS & OBJECTIVES • BACKGROUND • DATA ANALYSES • ALTERNATIVES • ALTERNATIVES COMPARISON • RECOMMENDATION & APPROVAL • NEXT STEPS • LESSONS LEARED

  3. GOALS & OBJECTIVES • Quantify traffic parameters • Address vehicular issues • Improve Pedestrian safety • Ensure community input • Recommend an optimal configuration

  4. PROCESS • Collect traffic data • Analyze data • Community Outreach and Information • Surveys • Workshops • Formal Hearings • Council Review and Approval

  5. EAST 14TH STREET NORTH AREA STUDY • GOALS & OBJECTIVES • BACKGROUND • DATA ANALYSES • ALTERNATIVES • ALTERNATIVES COMPARISON • RECOMMENDATION & APPROVAL • NEXT STEPS • LESSONS LEARNED

  6. BACKGROUND • Late 1996 – Four lanes to two lanes with tested median • Late 1999 – One lane each direction with a center two-way left-turn lane • Present - Congestion and pedestrian safety concerns persist • 2004 - Consultant developed potential alternatives • Public Surveys

  7. BACKGROUND

  8. BACKGROUND

  9. BACKGROUND • Retained W-Trans for the study • 1st Workshop on September 29, 2004 • Discussed traffic data and problems • Explained alternatives • Received input at the workshop and via a questionnaire

  10. COMMUNITYPRIORITIES • Easier left turns from side streets • Easier pedestrian crossings • Higher speeds • Don’t change

  11. Photo of Existing Traffic Conditions

  12. Photo of Existing Traffic Conditions

  13. Photo of Existing Traffic Conditions

  14. BACKGROUND Follow-up of 1st Workshop • Additional data collection • Revised questionnaire (i.e., Priorities) to neighbors • Neighborhood Traffic Management Group Meeting in February and April 2005 • Prepared a condensed traffic study report

  15. BACKGROUND • Presented to Planning Commission at their November 11, 2005 meeting • Presented to Facilities Committee at their January 25, 2006 meeting

  16. EAST 14TH STREET NORTH AREA STUDY • GOALS & OBJECTIVES • BACKGROUND • DATA ANALYSES • ALTERNATIVES • ALTERNATIVES COMPARISON • RECOMMENDATION & APPROVAL • NEXT STEPS

  17. EXISTINGCONFIGURATION

  18. EXISTING CROSS-SECTION • 17-foot wide center TWLTL • Two 12-foot wide travel lanes • Two 6-foot wide “bicycle/buffer” areas • Two 7-foot wide parking lanes • Total curb-to-curb width = 67 feet

  19. EXISTING CROSS-SECTION

  20. COLLISION SUMMARY

  21. PEDESTRIAN COLLISIONS

  22. EXISTING CONDITIONS SUMMARY • Traffic volumes have increased 17% for ADT and 14% for p.m. peak hours since 1994 • Weekday traffic volumes are typically higher than weekend • 65% of traffic is pass-thru traffic • Collisions have been trendinghigher

  23. EXISTING CONDITIONS SUMMARY • 33% Pedestrian collisions were potentially correctable • Average speed in p.m. peak hour – 17.5 mph (NB) and 19 mph (SB) • Most signalized intersections are LOS C or better, except LOS D at Dutton • Most un-signalized intersections are LOS C or better, except westbound Oakes is LOS D

  24. CHALLENGES • Pedestrian safety concerns • Traffic congestion at East 14th/Dutton • Side-street access at un-signalized intersections is difficult

  25. EAST 14TH STREET NORTH AREA STUDY • GOALS & OBJECTIVES • BACKGROUND • DATA ANALYSES • ALTERNATIVES • ALTERNATIVES COMPARISON • RECOMMENDATION & APPROVAL • NEXT STEPS • LESSONS LEARNED

  26. ALTERNATIVES • Alternative 1 – Existing Conditions • Alternative 2 – Four-lane Configuration • Alternative 3 – Modified 3-Lane Configuration with Pedestrian Safety Features • Alternative 4 – Two Northbound Lanes and One Southbound Lane

  27. ALTERNATIVE 1 – EXISTING CONDITION

  28. ALTERNATIVE 1 - EXISTING CROSS-SECTION

  29. ALTERNATIVE 2 – 4-LANE CONFIGURATION

  30. ALTERNATIVE 2 - CROSS-SECTIONS

  31. ALTERNATIVE 2 - CROSS-SECTIONS

  32. ALTERNATIVE 3 – MODIFIED 3-LANES WITH PEDESTRIAN SAFETY FEATURES

  33. ALTERNATIVE 3 - CROSS-SECTION

  34. ALTERNATIVE 4 – TWO NORTHBOUND LANES AND ONE SOUTHBOUND LANE

  35. ALTERNATIVE 4 – CROSS-SECTION

  36. ALTERNATIVE 4 – CROSS-SECTION

  37. EAST 14TH STREET NORTH AREA STUDY • GOALS & OBJECTIVES • BACKGROUND • DATA ANALYSES • ALTERNATIVES • ALTERNATIVES COMPARISON • RECOMMENDATION & APPROVAL • NEXT STEPS • LESSON LEARNED

  38. TRAVEL TIME AND LOS COMPARISON

  39. QUEUING AT DUTTON AVENUE P.M. PEAK HOUR

  40. SUMMARY ALTERNATIVES COMPARISON

  41. COMMUNITYPRIORITIES • Easier left turns from side streets • Easier pedestrian crossings • Higher speeds • Don’t change

  42. EAST 14TH STREET NORTH AREA STUDY • GOALS & OBJECTIVES • BACKGROUND • DATA ANALYSES • ALTERNATIVES • ALTERNATIVES COMPARISON • RECOMMENDATION & APPROVAL • NEXT STEPS • LESSONS LEARNED

  43. ALTERNATIVE 4 – MODIFIED WITH PEDESTRIAN SAFETY FEATURES • 11-foot wide center TWLTL • Three 11-foot wide travel lanes (2 NB & 1 SB) • Two 4.5-foot wide “bicycle/buffer” areas • Two 7-foot wide parking lanes • Pedestrian Safety Features at selected un-signalized intersections

  44. RECOMMENDATION & APPROVAL • Staff requested that Planning Commission recommend Modified Alternative 4 to Council for implementation • Planning Commission split vote between Alternatives 2 and Modified Alternative 4 with one abstention on November 11, 2005

  45. RECOMMENDATION & APPROVAL • Facilities Committee reviewed the project and favored Modified Alternative 4 on January 25, 2006 • Staff recommends Modified Alternative 4 with pedestrian safety features • City Council adopted Resolution approving Modified Alternative #4 as new configuration, May 1, 2006

  46. MODIFIED ALTERNATIVE 4 – TWO NORTHBOUND LANES AND ONE SOUTHBOUND LANE

  47. EAST 14TH STREET NORTH AREA STUDY • GOALS & OBJECTIVES • BACKGROUND • DATA ANALYSES • ALTERNATIVES • ALTERNATIVES COMPARISON • RECOMMENDATION & APPROVAL • NEXT STEPS • LESSONS LEARNED

  48. NEXT STEPS • Collaboration with Caltrans and other agencies • Design • Implementation through 2007-2008 Capital Improvement Program (CIP)

  49. EAST 14TH STREET NORTH AREA STUDY • GOALS & OBJECTIVES • BACKGROUND • DATA ANALYSES • ALTERNATIVES • ALTERNATIVES COMPARISON • RECOMMENDATION & APPROVAL • NEXT STEPS • LESSONS LEARNED

  50. LESSONS LEARNED • Community inputs are as crucial as the traffic data • Road diets may not work for all especially when collisions and congestion/bottleneck worsen traffic conditions

More Related