1 / 16

Life Cycle Costing

Life Cycle Costing. Learning outcomes. To identify the Life Cycle Cost considerations of mega projects (High speed rail – HS2). HS2 objectives. To connect the city centres of: London, Birmingham, Leeds and Manchester To enhance the economic development. Project details.

betsy
Download Presentation

Life Cycle Costing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Life Cycle Costing

  2. Learning outcomes • To identify the Life Cycle Cost considerations of mega projects (High speed rail – HS2)

  3. HS2 objectives • To connect the city centres of: London, Birmingham, Leeds and Manchester • To enhance the economic development

  4. Project details • The line is in a "Y" configuration to be built in two phases • Construction starts – 2017 • Expected completion – 2033 (Phase 1 – 2027) • Developer – HS2 Ltd (established by the UK Govt) • Capacity - conveying up to 26,000 per hour @ speeds of up to 400 km/hr (250 mph) • Length – 540Km (Phase 1 – 190Km) • Construction cost – £32.7b (2011) however Institute of Economic Affaires noted the cost will be increased up to £80b

  5. Route map (HS2 / Y- network)

  6. Life cycle cost components • Capital construction cost – cost of land purchases, design, materials, construction and allowance for risk • Rolling stock capital costs – the purchase costs of rolling stock (trains) • Operating costs – the operation and maintenance of the railway infrastructure, its trains including train crew and station staff

  7. Infrastructure capital cost • Phase 1 (£16.2b) & Full Y network (£32.7b) – including contingencies • Rates were based on Spon’s Civil Engineering and Highway Works Price Book • Tunnelling / bridge costs were based on Infrastructure UK cost study work

  8. 1. Capital cost components • 250 cost elements were identified • Cost reflects on the route section • Permanent way – rail, sleepers, ballast, walkway, track drainage and high security fencing; • Changes and crossings – based on number of crossings and associated line-speed; • Overhead Line Equipment – overhead line equipment, support structures and power supply; • Train control systems – includes all signalling and communication requirements and control centre; • Stations– civil engineering works, station buildings, station facilities, track, switches, • Earthworks– site clearance, earthworks, soiling, seeding and small structures for the permanent way only • Retaining walls – associated earthworks, concrete, formwork, reinforcement; • Structures– associated earthworks, concrete, formwork, reinforcement, pre-cast units, structural steelwork and finishing works; • Tunnels– excavation, tunnel lining, cross passages (for twin-bore tunnels), shafts, plant and associated control systems. • Highways– include site clearance, fencing, vehicular barriers, drainage, earthworks, pavement, kerbs, footways, signs, lighting and small structures/accommodation bridges;

  9. 1.1 Capital cost • Land cost (Phase 1) - includes property, disturbance and resale values – £966m • Other associated cost – varies with the construction cost

  10. 1.2 Other capital costs • Environmental mitigation (urban areas or areas of known environmental significance 5% of base construction cost, in other areas 3%) • Surveys (ground and topography) - allowance of £150,000 per km • Rail possession / isolation / safety management - 2% of base construction cost for route sections affecting existing railway

  11. Cost estimate (Full network)

  12. Two types of trains will be used to operate HS2 services. • Captive size sets (Euro size) • Classic-compatible sets (British mainline) 1.3 Rolling stock (train) capital costs

  13. 2. Renewals Recognising that the HS2 business case is evaluated over a 60 year period

  14. 3. Operations & maintenance • The calculations were based on HS1 costs. At 2011 prices, an annual figure of £191,000 per km (£103.14m). • Captive set maintenance - £2.97 per kilometre travelled for a 200m captive train • Classic compatible set maintenance - £3.71 per kilometre travelled for a 200m set. £4.82 per kilometre travelled for a 260m • Traction power (electricity grid for the supply of electrified rail networks) cost;

  15. Further information

  16. Questions?

More Related