1 / 11

James Webb Space Telescope Update

James Webb Space Telescope Update. Eric P. Smith Deputy Director, JWST Program NASA Science Mission Directorate. 2010 Programmatic Events. TAT: Test Assessment Team ICRP: Independent Comprehensive Review Panel. NASA TAT Responses. ICRP Recommendations (1). Baseline Funding

betty
Download Presentation

James Webb Space Telescope Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. James Webb Space Telescope Update Eric P. Smith Deputy Director, JWST Program NASA Science Mission Directorate

  2. 2010 Programmatic Events TAT: Test Assessment Team ICRP: Independent Comprehensive Review Panel AAS 217th Meeting

  3. NASA TAT Responses AAS 217th Meeting

  4. ICRP Recommendations (1) • Baseline Funding • NASA did not establish an adequate cost and schedule baseline at JWST’s Confirmation Review milestone, and recommended four specific steps be taken to establish a realistic baseline. AAS 217th Meeting

  5. ICRP Recommendations (2) • Independent Analysis Capability • NASA Headquarters should have a robust independent cost and program analysis capability, and recommended a stronger role for the Office of Independent Program and Cost Evaluation (IPCE). AAS 217th Meeting

  6. ICRP Recommendations (3) • Program and Project Management • Recommended that JWST be elevated to a new organizational entity at Headquarters • Implementation phase of JWST project requires a different management approach than the Formulation phase AAS 217th Meeting

  7. HQ Management Changes WAS IS AAS 217th Meeting

  8. GSFC Management Changes WAS IS AAS 217th Meeting

  9. ICRP Recommendations (4) • Additional Items • NASA program/project governance policy • Program, Project, Industry communication • Potential Risk in Integration and Test • ICRP Endorsed findings of the TAT • System Engineering • Establish a plan that provides the required level of experience and involves appropriate prime contractor personnel before changing system engineering accountability • Project Scientist and Science Team • Recommend this role be strengthened AAS 217th Meeting

  10. Steps to A Launch Date AAS 217th Meeting

  11. End AAS 217th Meeting

More Related