120 likes | 134 Views
FPLE raises concerns over inadequacy of upgrades in McCamey area, impacting energy generation. Review findings, propose alternatives, and address timing and implementation challenges. Explore implications for the existing plan and potential mitigation strategies.
E N D
Why are we here? FPLE is seriously concerned that the upgrades being constructed in the McCamey area are not adequate.
Concerns • McCamey Area Plan, as it is currently being implemented, will not meet the existing requirements of 755 MW, much less the 900 MW announced by ERCOT • Findings need to be verified • Generation patterns may result in lower limits • Additional mitigation alternative considerations • Timing • Implementation by ERCOT
Assumptions • Rio Pecos capacitors in-service • RAPs in the 69 kV system • Big Lake – McCamey 138 @ 149/170/170 • Operations case at 52000 MW load (80%), McCamey area load 144 MW • Outages required for upgrade construction not modeled
AssumptionsRAPs • Shef-Iran 69 kV • Atlt-Humt 69 kV • Odnth-Pegtp 69 kV • Illn-Oznr 69 kV • FtL-Iln 69 kV
Why is there a difference? • Dispatch outside McCamey was not taken into account when the plan was originally developed • If generating units in the Odessa area are dispatched, a portion of the generation flows through McCamey
Potential Mitigation Alternatives • Accelerate Ft. Lancaster to Friend Ranch 138 kV by an additional 6 months • Install Breakers at North McCamey • Add Tension Monitors in Crucial lines • Implement SPS • Start building 345 kV line • Other
Maximizing Line Capacity • Limiting lines and tension monitors • Rio Pecos to Crane 138 kV • North McCamey to Big Lake 138 kV • SPS until the 345 kV is completed
McCamey Area Transmission Upgrades 50 MVAR 50 MVAR 25 MVAR 25 MVAR 50 MVAR 25 MVAR 25 MVAR 50 MVAR