Cost Estimate Management, Cost Trends and Long Range Estimates for Turnpike Enterprise / FICE Estimates Training. Dale Stanley FDOT Estimating Systems Support Manager (850) 414-4197 SC 994-4197 dale.stanley@dot.state.fl.us. Topics. Part 1: Cost Estimate Management Cost Trends
E N D
Cost Estimate Management, Cost Trends andLong Range Estimatesfor Turnpike Enterprise / FICEEstimates Training Dale Stanley FDOT Estimating Systems Support Manager (850) 414-4197 SC 994-4197 dale.stanley@dot.state.fl.us
Topics • Part 1: • Cost Estimate Management • Cost Trends • Communication • Part 2: • Estimating Systems • LRE Update
Part 1 Cost Estimate Management and Cost Trends
Cost EstimateManagement • Means controlling scope of work and design parameters to stay within the construction cost budget • Cost Estimates Task Team:“TheProject Scope of Work should be well defined early in project development. Significant scope changes should be approved by upper management.”
Cost EstimateManagement • There may be times when changes are necessary, but cost managementinvolves knowing the cost impact of these changes. • We can’t expect to add work to a project without increasing the cost!
Cost EstimateManagement • Cost Estimates Task Team:“Estimates should NEVER be artificially constrainedto stay within budget.”
UpdatingBudget Estimates • In many cases, cost estimates are not updated frequently enough to reflect the latest scope of work until Phase III plans, when the pay items and quantities are available. • Cost Estimates Task Team: “Estimates should be updated at every project phase and at least every six months, whether or not final quantities are available.”
UpdatingBudget Estimates • Performance and Quality measures are based on the estimates at: • Initial entry into the Work Program • Scope development • Phase 2, 30% Plans stage • Official Estimate Estimates MUST be updated at each of these milestones !!
Communication • Cost Estimate Task Team:“The Districts should foster a culture that requires a close working relationship between project consultants, project managers and estimators to ensure the project features are accurately reflected in the estimate.”
Consequences of Bad Estimates • What happens if we underestimate? • Projects may have to be moved out. • Related activities (R/W, Utilities) will be affected. • What happens if we overestimate? • Production limits are not achieved. • Public lack of confidence – we could have done more with the money we had.
44.0% 38.5% 75.0% Recent Cost Trends(Annual Averages) • Asphalt • Jan-Dec 2003 $53.93/ton • Jan-Dec 2005 $77.66/ton • Concrete (Structural) • Jan-Dec 2003 $549.82/CY • Jan-Dec 2005 $761.71/CY • Steel (Reinforcing) • Jan-Dec 2003 $.52/LB • Jan-Dec 2005 $0.91/LB Figures based on Weighted Averages
$85.38 $51.60 +20.1% Rising Asphalt Costsby Quarter
$1,045.14 $490.02 +64.2% Rising Concrete Costsby Quarter
$1.28 $0.53 +48.8% Rising Steel Costsby Quarter
Causes forMajor Cost Increases • Construction market saturation: • “Hot” Market, both public and private sector • Labor and equipment shortages, due to hurricane recovery efforts • Material shortages • Fuel cost increases • Project requirements: • Hours of operation • Night work • Delayed start
Part 2 Estimating Systems and LRE Update
Estimating Systems • Long Range Estimates (LRE) • Budget, 5-Year Work Program • Conceptual, prior to 60% Plans • FDOT developed – “First in the Nation” • TRNS*PORT • Quantities based on complete Design • Department’s Official Estimate • AASHTO owned – developed by Infotech
Pay Item Definitions & Prices Budget $$ Project Data Pay Item Definitions LAS TRNS*PORT CES Project Data Pay Items, Quantities & Unit Prices Systems Interaction
Price Update Process • Update occurs each month • Uses 1 year of bid history • Uses all bidders • New prices will appear on newly created projects • Existing projects must be “refreshed” for new prices • Blocked projects and locked pay item prices are not affected by price refresh.
Price Refresh Utilitiesavailable to LRE Coordinators • Refresh Project Prices - allows individual, unblocked projects to be refreshed • Mass Refresh of Project Prices – allows all unblocked projects within a District to be refreshed • Mass Refresh of Selected Pay Items – allows selected pay item prices to be refreshed on all unblocked projects within a District.
Lock Price Featuresavailable to LRE Coordinators • Reset and/or Lock default county prices on individual pay items • Lock individual pay item prices within a project
This price should be reset Reset / Lock Default Prices Feature
Consultant Designers and Pricing • Pricing LRE projects is usually done by the District Estimates Office, but each District has its own policy regarding pricing requirements. • Make sure you know what your District requires!
Interchange Models • Default models will be available for several basic interchange designs (i.e., Compressed Diamond, Rural Diamond, Partial Cloverleaf, Semi-Directional, etc.) • Model Selection will be from the sequence selection screen:
Interchange Model Selection DRAFT Subject to Change
Also In-Work: • Change spec year to 2004 • New Utility to copy a sequence from within the project • New Field – “Quantities Complete in Trns*Port”
Intranet Internet • Next on the priority list - expected release in May • No more VPN!! • You will be notified when the permanent web address is known
Modifications Tracking • Tab on the Main Version view will list: • Date and time of change • Userid • Type of change (code, drills down to details) • Net change in primary version cost
Architectural Component • Provide site work details – Earthwork, Drainage, Electrical, Concrete, Hardscape, Utilities, Paving, Signing, Safety, Landscaping • Choose building type from selection list – Administration, Rest Area, Weigh Station, Toll Plaza, Utility, Parking, ITS • Provide Building details – SF, costs for concrete, masonry, metals, wood & plastics, doors & windows, finishes, etc., and cost-per SF will be calculated
Other Pending Enhancements • ITS as a subcomponent of Signalization • Revise bridge types to match Trns*Port • Updated pay items and fields for grassing, finished soil layer, rumble strips, etc. • Many other minor enhancements
Use the Feedback button!! Our goal is to make the LRE system as easy and effective as possible for you!
Training • Conducted in Districts, upon request • One full-day session • You must have an active userID • PDH credits are now available • Contact your District LRE Coordinator for information on upcoming classes.
District EstimatesCoordinators • D1 – Steve Walls • D2 – W.C. Cobb • D3 – Jess Bruner • D4 – Gene Lipscomb • D5 – Jonathan Linforth / Ed Kestory • D6 – Ruben Rivero • D7 – Jason Spilak • TP – Don Brackins • CO – Dale Stanley / Tyrone Ware