1 / 21

30 Min Culvert Design

30 Min Culvert Design. Jered Carpenter Region 3 Roadway Design. Design Steps. Step 1) Gather hydrological & site specific data Step 2) Assume culvert size Step 3) Find headwater depth for trial size Step 4) Try another size Step 5) Compute outlet velocity

blake
Download Presentation

30 Min Culvert Design

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 30 Min Culvert Design Jered Carpenter Region 3 Roadway Design

  2. Design Steps • Step 1) Gather hydrological & site specific data • Step 2) Assume culvert size • Step 3) Find headwater depth for trial size • Step 4) Try another size • Step 5) Compute outlet velocity • Step 6) Determine Invert Protection • Step 7) Document selection

  3. Del Rio Example

  4. Pictures of Existing Culvert

  5. Step 1) Gather Hydrological Data Q = cia = (.35*52*.82) = 14.9 cfs Zone 6 IDF Curve Culvert Location

  6. Step 1 Cont.) Site Specific Data • Invert In El. = 564.9’ • Invert Out El. = 564.5’ • Pipe Length = 75’ • Slope = -0.5%

  7. Step 1 Cont.) Site Specific Data • Calculate Tail Water, TW • 2.5’ btm, class 50 rip-rap lined FBD with 2:1 side slopes @ outlet • Manning’s Equation for discharge Q = (1.486/n)*A*R2/3S1/2 • Using a spreadsheet & setting Q as a function of depth, I get the following results when d=1.7 ft: 15.0 cfs = (1.486/0.07)*10.03ft2*0.99ft2/30.051/2 • TW = 1.7’

  8. Key #15186 – Del Rio “DR” 92+15 Jered Carpenter 11 Feb 08 1 of 1 Rational 52 Ac -0.5% Trapezoid 564.9 75 564.5 50 14.9 1.7 100 16.4 1.8

  9. Step 2) Assume Culvert Size Start With 18” Circular CMP

  10. Step 3) Find HW Depth For Trial Size • Assume inlet control • From Nomograph, HW/D = 3 • HW depth w/ inlet control approx. 569.4 ft., which is too high • I’ll try a 24” pipe

  11. Step 3) Find HW Depth For Trial Size • Assume inlet control • From Nomograph, HW/D = 1.2 • HW depth w/ inlet control approx. 566.7 ft., which is OK. • The 24” pipe looks good so far

  12. Key #15186 – Del Rio “DR” 92+15 Jered Carpenter 11 Feb 08 1 of 1 Rational 52 Ac -0.5% Trapezoid 564.9 75 564.5 50 14.9 1.7 100 16.4 1.8 CMP-Circ.-18”-Mitered 4.2 569.4 14.9 3.0 CMP-Circ.-24”-Mitered 14.9 1.2 2.4 567.3

  13. Step 3 Continued Check for outlet control • Need to calculate H, total outlet control head loss • Outlet control nomographs can be used if outlet crown is submerged. (TW>Top of Pipe @ Outlet) • TW @1.7’ < D @ 2’ , so I will not use the nomograph

  14. Step 3 Continued • Alternatively, H can be calculated by following the steps on the culvert design sheet • Calculate critical depth, dc • Critical depth = 1.4’ (from graph located in Chapter 8, appendix B)

  15. Step 3 Continued • Following Steps 4 thru 5 on the culvert design sheet: • (dc+D)/2 = (1.4’+2’)/2 = 1.7’ • ho = TW or (dc+D)/2 , whichever is greater TW @ 1.7’ = (dc+D)/2 @ 1.7’ ,use 1.7’

  16. Key #15186 – Del Rio “DR” 92+15 Jered Carpenter 11 Feb 08 1 of 1 Rational 52 Ac -0.5% Trapezoid 564.9 75 564.5 50 14.9 1.7 100 16.4 1.8 CMP-Circ.-18”-Mitered 4.2 569.4 14.9 3.0 CMP-Circ.-24”-Mitered 14.9 1.2 2.4 567.3 1.7 1.4 1.7 1.7

  17. Step 3 Continued • Calculate Energy losses, H for the culvert From the culvert design sheet: • H = (1+ke+(29*n2*L/R1.33))*(V2/2g) Ke = .7 (from table 9-3, mitered to slope) n = .024 (from table 8-A-2) L = 75’ Use values of V and R under full flow (d=2’) R = 0.5’ V = 4.74 ft/s (Average Velocity) • H = 1.52

  18. Step 3) Continued • Inlet Control HW Elevation = 567.3’ • Outlet Control HW Elevation = 567.9’ • The pipe flowing under outlet control.

  19. Step 4) Try Another Size • 24” pipe is acceptable. • Remainder of the Culvert design sheet is completed.

  20. Step 5) Compute Outlet Velocity • Previously calculated value. Determine if channel protection is required following the guidance in Chapter 11 of the hydraulics manual. Step 6) Determine Invert Protection • Follow guidance in Chapter 5 of the hydraulics manual to determine if & what type of invert protection is required.

  21. Step 7) Document Selection Key #15186 – Del Rio “DR” 92+15 Jered Carpenter 11 Feb 08 1 of 1 Rational 52 Ac -0.5% Trapezoid 564.9 75 564.5 50 14.9 1.7 100 16.4 1.8 CMP-Circ.-18”-Mitered 4.2 569.4 14.9 3.0 CMP-Circ.-24”-Mitered 14.9 1.2 2.4 567.3 1.7 1.4 1.7 1.7 1.7 1.7 567.9 567.9 4.74 Outlet Control Trap. Channel: W=2.5’ 2:1 side slopes N= .07 (class 50 rip rap) S=0.5% Dc=1.7’ 24” Circ. Metal 0.024 Mitered

More Related