Project: IEEE P802.15 Working Group for Wireless Personal Area Networks (WPANs) Submission Title: July c losing report for ULP Date Submitted: July 2012 Source: : Shahriar Emami, Samsung E-Mail: [ Shahriar.e@samsung.com] Re: Abstract: Purpose: Closing report

blue
Download Presentation

Project: IEEE P802.15 Working Group for Wireless Personal Area Networks (WPANs)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project: IEEE P802.15 Working Group for Wireless Personal Area Networks (WPANs) Submission Title: July closing report for ULP Date Submitted: July 2012 Source::Shahriar Emami, Samsung E-Mail: [Shahriar.e@samsung.com] Re: Abstract: Purpose:Closing report Notice: This document has been prepared to assist the IEEE P802.15. It is offered as a basis for discussion and is not binding on the contributing individual(s) or organization(s). The material in this document is subject to change in form and content after further study. The contributor(s) reserve(s) the right to add, amend or withdraw material contained herein. Release: The contributor acknowledges and accepts that this contribution becomes the property of IEEE and may be made publicly available by P802.15. Shahriar Emami, Samsung

  2. July Closing Report for ULP SG (1/6) • Number of meetings slots: 4 • Total Number of contributions: 5 • Participation: Tuesday (23)- Wednesday (10) Shahriar Emami, Samsung

  3. July Closing Report for ULP SG (2/6) • Meeting Activities: - Hear presentations - Work on PAR and 5C Shahriar Emami, Samsung

  4. July Closing Report for ULP SG (3/6) • Contributions: Document #15-12-381-01 Document #15-12-389-00 Document #15-12-393-00 Document #15-12-383-00 Document #15-12-384-00 Shahriar Emami, Samsung

  5. July Closing Report for ULP SG (4/6) • Accomplishments - Heard all 5 presentations - Prepared PAR and 5C drafts Shahriar Emami, Samsung

  6. July Closing Report for ULP SG (5/6) • Conference Calls - August 9, 2012 7 pm-8 pm PST - August 23, 2012 7 pm-8 pm PST Shahriar Emami, Samsung

  7. July Closing Report for ULP SG (6/6) • Plan for September Meeting - Finalize PAR and 5C Shahriar Emami, Samsung