An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COMMODITY REVIEW MECHANICAL PARTS PAUL SHELDON

  2. Mechanical Components (P. Sheldon) SCORE CARD FY 06

  3. Mechanical Components (P. Sheldon) • STRONG PRESENCE OF SUPPLIERS IN E. EUROPE • FY06 ACTION: ‘WESTERNIZE BUSINESS HABITS OF MAIN EE BASE’ • REVERSE AUCTIONS • PRICES: • CLOSER FOLLOW UP of price vs raw materials • PRODUCTIVITY: especially machined parts (R. Bédard) • ACTION IN MACHINING S/CONTRACTING: as opposed to machined parts inc material • ROTC • LEAN: but most suppliers of Olomouc are already lean… • DPO • IMPACT OF ASIA SUPPLIERS MAINLY IN Q3 & Q4 • Volume deliveries of machined castings & stamped parts. • Difficulty in tracking savings automatically

  4. REVERSE AUCTIONS • REVERSE AUCTIONS • €467k Plastic components (feb 05): €42k savings (RO/F) DONE. €32k (RO: tooling AR done) + €17k (F: transfer in progress) • €113k machined Bronze casting (oct 05): €10k savings (F). Unsuccessful. • €120k Aluminium (dec 05): €20k (HO: 1st tool transfer of 4 done) • €150k. Machining (Jan 06): €5k (CZ) DONE. €20k (CZ) Almost done (first samples delivered, refused. New samples end June) • €202k Bar machining: €12k (F) done, approved. €19k in progress (1st approval refused). 2 other lots didn’t work. • €615k Cast iron (Feb 06): €156k (RO & CZ) in progess, AR done. • €150k Cast iron (Avril 06): €35k (HO & CZ) in progess, AR done. • €220k Cast iron (May 06): €60k (RO, BG, HO, CZ): decision to be made. • €150k Cast iron (June 06): released • €120k Machined parts (July 06): to be done

  5. PRICING • ACTIONS ENGAGED IN Q1 / Q2 on existing base • Scrape back some of high price hikes of FY05 in Q1 & Q2 • TES (€71k), Trie Château (€27k), Koopron (€25k), PBS (€8k) • Productivity in machining • ZLKL: 3% to 5% on targeted parts • PRICE TENSION SINCE JAN 06: Low profile / defensive position adopted in Q3 & Q4 • Energy costs up 8% to 27% depending on the country • Raw material prices go up again • Many EE mechanical companies back in a ‘production economy’: • At full capacity, they ‘clean up’ their portfolios • Big price rises asked for on small volume (5% to 20%)

  6. KEY OBJECTIVE FY 06: CASH FLOW • DPO improvement: • Targetting of suppliers between 0 & 45 days • High sales • Targetting criteria (tailor to the situation): • Group or family company? • Take account of customer portfolio of the suppliers (esp direct competitors of LS) • Do not create fragile situation at good suppliers’ (eg. family companies) • Talk it over with them & listen: cash flow isn’t managed the same way in small companies • Target suppliers with increasing sales (esp with LS) • Agree to go ther step by step: • Don’t add extension of DPO to big price reduction requests • Get E. European suppliers used to participating in our ROTC improvement effort

  7. TOP 6 SUPPLIERS, E. EUROPE, MECHANICAL

  8. DONE IN FY 06: CASH FLOWACTION ENGAGED ON €15700k of SALES

  9. LEAN : ACTIONS FY 06-07

  10. IMPACT OF ASIA • Big savings from FY05 auctions in stampings & cast –iron • Only kicks in in Q3 & Q4 • Stamping savings clearly identified in inflation tracking • Castings not so easy: raw + machined in Europe, but supplied finished (mchined) from Asia • Manual tracking necessary • Example of Alternator division (castings) • Manual tracking necessary • Top 6 castings in sales value = €3000k raw + €1600k machining = €4600k • €700k savings in FY06 unidentified automatically (Asia) • €320k savings identified automatically, piece / piece rough castings (LCC / VLCC EE) • New castings introduced in mid FY05 (global alternator design) • €150k savings in FY06 (Q3 & Q4): VLCC EE (Uk, BG, RO)

  11. MECHANICAL PARTS ANALYSIS BY COMPONENT FAMILY

  12. LS Family & DRI Code

  13. MECHANICAL Parts

  14. MECHANICAL Parts

  15. MECHANICAL Parts : LCC FY 06

  16. MACHINED Parts

  17. MACHINED Parts

  18. MACHINED Parts : LCC FY 06

  19. PUS FY 06 / FY 07 • TARGET INFLATION FY 07 : -2 % • MARKET TREND: risks & opportunities • Steel prices fluctuate less, but remain high • Castings index similar • New machines cost same price in LCCs as in West • Energy prices continue to rise much faster than inflation: moderate prce hike requests of FY06 (+0 to 2%) could be higher in FY07 • LS in market trend toward purchasing more added value (eg. Machined castings) • China attractive for high volumes • A few EE companies invest in more modern machinery, but the majority have too much (old) capacity • EE & China have different supply bases: • China is organised between mechanical / foundries & machining companies • EE is not

  20. PUS FY 06 / FY 07 • STRATEGY & ACTION PLAN • Share our markets between EE & China via separate auctions if possible • Keep an eye on $/€ rates • Enlarge strategy to subcon machining (same supplier base) • Reduce number of suppliers by consolidation • Wisconsin CZ (€400k), UNEKO (€300k) & ISH (€250k) not strategic: consolidate in existing & VLCC base • Continue toward more added value in purchase • Casting suppliers pre-informed of machining requirement • Enlarge machining base / partnerships with foundries to create market for future auctions • Replace Tafonco (major price rise in FY06)

  21. KPI / PUS

  22. CASTING GREY IRON

  23. CASTING RAW MAT’L INDEX

  24. CASTING GREY IRON

  25. CASTING GREY IRON : LCC FY 06

  26. PMO FY 06 / FY 07 • TARGET INFLATION FY 07 : -3 % • MARKET TREND: risks & opportunities • CZ still pretty saturated: several foundries closed in 05 & 06 • Casting material prices remain high (autumn/winter 04 level) • No raw material shortage today, but we remain vigilant • CZ, SK, RO: currency revaluation 8% to 10% in 2005. • ‘Unhealthy’ EE suppliers have cash problems • W. Europe staggered price rises in 05 & 06: 3-5% in 05, 1-5% in 06 • EE imposed almost full impact in 05, moderation in 06 • 0% - 3% inflation from Asia

  27. PMO FY 06 / FY 07 • STRATEGY & ACTION PLAN • New supplier base in VLCC (Romania, Bulgaria, Ukraine) • Capacity suppliers in Central Europe (Croatia) to help CZ short term • Auctions of high volume parts : • Do not mix EE & China in auctions: EE not mature / competitive. Strategic share of markets. • Always include tooling in auctions: 25% - 50% savings possible • Take care with Asia in FY07: direct RFQ with newly developed suppliers gives same prices in FY06 for (machined) castings as in FY05 • Not sure to get this containment on open market / auctions (+10% to 15% mat’l price rise since then) • Auction potential limited in FY07: • Top 5 parts all auctioned / double auctioned in last 18 months • 24 month contracts preferred • Reduce number of suppliers in W Europe: target 2 or 3 strategic foundries • Be opportunistic when raw material costs drop • Be close to CZ / Olomouc = big volume buys of LS • Seek partners capable of machining (even if not yet ready) • Problems with low volume parts: pruning by EE foundries

  28. PMO

  29. CASTING ALUMINIUM

  30. CASTING ALUMINIUM

  31. ALUMINIUM LME

  32. CASTING ALUMINIUM : LCC FY 06

  33. PMA FY 06 / FY 07 • TARGET INFLATION FY 07 : -2 % (w/o aluminium variation) • MARKET TREND: risks & opportunities • Fast & furious Aluminium price increase early 2006. Dec 05 to March 06 +40%. Impact: • Pressure: + 20% (raw 50%) • LP gravity: + 12% (raw 30%) • sand: + 8% (raw 20%) • Expect severe carry over in FY07 (lagged price rises on past 3 months) • So far, impact Q3/Q2 = 7%

  34. PMA FY 06 / FY 07 STRATEGY & ACTION PLAN Replace Diace by LCC supplier • Auction dec 05: first tooling transferred Increase coquilla volume in Romania Find new sources in LCC/VLCC in 3 types of aluminium castings: Romania, Bulgaria, Turkey Auctions if enough volume (but LS not so attractive) Investigate Dourlet: hard to put in auction - single, critical customer - value analysis - engineering / purchasing approach

  35. KPI / PMA

  36. PLASTICS

  37. PLASTICS

  38. PLASTICS : LCC FY 06

  39. PLA FY 06 / FY 07 • TARGET INFLATION FY 07 : -5% • MARKET TREND: risks & opportunities • Increase in materials linked to petroleum: +5% to +10% • Price tension on finished components +2% to + 6% • LS had reasonable price increase with Schulman in Jan 06 (8% on ABS = +1.7% total from Schulman) • Several W European component mfrs have moved to EE • CZ, SK, RO: revaluation of currency 8% to 10% 05/06 • No problem finding capacity on plastics market • Price reductions possible if ready to change suppliers

  40. PLA FY 06 / FY 07 • STRATEGY & ACTION PLAN • Develop 1 or 2 sources in E Europe • SK, RO, HO….. • Several sources identified • Build on good savings following FY05 auction: new sources in Romania • Reduce number of suppliers in LS factories • Plan new auctions if volume permits: good markets for auctions • Use auctions for tooling: 35% to 50% savings in March 05 • Continue working group to find available raw materails for RM auctions • Big problem in FY06: captive market too large (ULs)

  41. KPI / PLA B

  42. STAMPING PARTS

  43. STAMPING PARTS

  44. STAMPING PARTS : LCC FY 06

  45. PDE FY 06 / FY 07 • TARGET INFLATION FY 07 : -5% • MARKET TREND: risks & opportunities • Price of steel remains high • Temporary shortage in 05 but OK in 06 / 07 • Cold rolled (+40%) & hot rolled (+50%) in 05/04: same level today • % Raw material in finished product now at much higher levels • W. European companies coming back into the game on volume markets: • Well equipped: productivity • Sometimes competitive vs EE (eg. New account TCIN)

  46. PDE FY 06 / FY 07 • STRATEGY & ACTION PLAN • Continue to contain price rise requests in EE: suppliers passed on 70% of raw increase in 05 • Use Asian pressure from previous auctions • Price savings • Helps in containment elsewhere • Think twice before doing new auctions in Asia • Big material inflation since 05 auctions… • Find new suppliers in VLCC for high volume: RO, BG, UK? • Logistic costs an issue • Target newly approved LCC suppliers for medium volume: eg. Hundec Hungary • prices –20% to –40% depending on factories (DEI, IMI, GP) • Subsidiary of French company: already has logistic circuit to France • €200k account in FY07 / 08?

  47. KPI / PDE FY 05 FY 06 FY 07 Spend in K€ 3,010 K€ 4,461 K€ 4,237 K€ Net Material Inflation 4.2% -1.0% -5.0% LCCS (%) 51.0% 60.0% e-Sourcing K€ (M) Bid 660 K€ 0 K€ 250 K€ average Results -40.0% -20.0% Direct Material DPO Total Averge Days 73 Days 72 Days 72 Days K€ less than 30 days 1,361 K€ 13 K€ 100 K€

  48. MECHANICAL Parts (inc FY07 plan)