220 likes | 416 Views
Chapter 13. ٠ Contract Types ٠ Supplier Management. Three key decisions in procurement:. Supplier Selection Price Contract Type The type of contract chosen is important because contracts by their nature: -Allocate risk -Influence supplier performance.
E N D
Chapter 13 ٠Contract Types ٠ Supplier Management
Three key decisions in procurement: • Supplier Selection • Price • Contract Type The type of contract chosen is important because contracts by their nature: -Allocate risk -Influence supplier performance
Three General Categoriesof Contracts • Fixed Price Contracts • Cost Reimbursable Contracts • Incentive Contracts to incentivize • - Cost control • - Technical achievement • - Schedule • - Other
The concept of Risk • Risk is uncertainty • Suppliers are risk averse • Types of risk: - Technical risk - Cost risk - Schedule slippage • Extremes in contract risk: FFP CPPC increasing risk to buyer increasing risk to supplier
Contract Types by Risk Level to the buyer-firm • FFP • FP/Escalation • FP/Redetermination • FPI Example: TC = $1000 T = 100 TP = $1100 CP = $1300 Share Ratios = 50/5070/30
Contract Types by Risk Level to the buyer-firm • CPIF Just like a FPI but - No ceiling - Minimum and Maximum Profit amounts • Time and Materials Contracts • CPFF • CPPC
Two other Contract Types • Award Fee contracts • Letter Contracts Award Fee is tied into another type of contract; e.g., CPIF + Award Fee
CPIF Contract Price 100/0 TP 70/30 Buyer/Contractor Share Ratios 50/50 100/0 Cost TC R. I. E.
For next class period . . . • Submit your individual case analysis of Selection of a Pressure Vessel Manufacturer
The Issue of Long-term Contracts • Spot contracts (transactional) • Short-term contracts (transactional) • Evergreen Clauses (partnership) • Long-term contracts need to reflect and guide a relationship(partnership or alliance) Issues include: initial price, mechanisms for price adjustments, expectations, confidentiality agreement, special clauses on incentives, etc.
Downsides to long-term contracts from the buyer-firm’s perspective • Supplier complacency • Selecting the wrong supplier
Supplier Management • Post-Award Activities “Once a contract has been negotiated and signed, the real work begins.” “It is the buyer’s responsibility to ensure that all of the terms and conditions of the agreement are fulfilled.”
Supplier Management • Starts with Pre-Award Conference • All terms and conditions • Specifications • Milestones • Delivery schedule • Review buyer responsibilities • Performance evaluation and feedback: Access, reports, conferences
Supplier Management • Continues with either Routine or Special activities 1. Routine (Administrative actions for follow-up) 2. Special (Employ formal performance tracking) • Gantt Charts • CPM • Earned-Value Accounting • Site Visits and Weighted-Point Evaluations • Recurring Reports (Cost, Schedule, Technical) • Program Assessment Reviews (PARs) • On-site Monitors (Buyer-firm co-location)
Earned Value (EV) Accounting Background: The Spend Plan Concept $ Plan Actual TNow Time
Earned Value Concept BCWS BCWP ACWP $1000 $800 Schedule Variance equals BCWP – BCWS = -$200 BCWS BCWP ACWP $1000 $800 $860 Cost Variance equals ACWP – BCWP = $60 In this example, the contractor has an unfavorable schedule variance (behind schedule) and an unfavorable cost variance (over budget)
Earned Value Concept BCWS BCWP ACWP $1000 $800 Schedule Variance equals BCWP – BCWS = -$200 BCWS BCWP ACWP $1000 $800 $860 Cost Variance equals ACWP – BCWP = $60 The “spend plan” analysis however has everything looking great. Budget to date is $1000 and expenditures to date are only $860!
Example Problem Bendix Corporation’s performance on Contract AF-8260 16 Weeks into the Contract: ACWP = $220,440 BCWP = $216,000 BCWS = $214,440 Total Budget at Completion (TBC) = $660,000 Evaluate Bendix Corporation’s performance by computing the cost variance and the schedule variance to date.
Example Problem Evaluate Bendix Corporation’s performance on Contract AF-8260 16 Weeks into the Contract: ACWP = $220,440 BCWP = $216,000 BCWS = $214,440 Total Budget at Completion (TBC) = $660,000 SV = BCWP – BCWS = +1,560CV = ACWP – BCWP = +4,440 Cost Performance Index (CPI) = ACWP/BCWP = 1.02056 Estimate at Completion (EAC) = CPI x TBC = $673,567
Motivation in Supplier Management • Punishment • Bill backs • Award Fee denial • Downgrade a supplier • Remove supplier from approved list • Rewards • Incentive fee • Formal recognition • Follow-on business • Elevate level of relationship
Relationship Management • Supplier Surveys • Are our buyers knowledgeable? • Are we ETDBW? • Do we “team” with you? • Do we pay on time? • Are our buyers and technical people available to you? • Do we engage in any questionable or poor business practices? • Are we a preferred customer? • Supplier Roundtables Review company’s procurement program with key suppliers as a way to manage and improve relationships