220 likes | 374 Views
De-Mystifying Customer CUM's and Requirements. Don Thompson EDI Coordinator Continental Strucutral Plastics March 22, 2010. Introduction – Don Thompson. Sr. EDI Consultant – RCM Corporation Implemented MFG/PRO Ecommerce and Gentran. Worked with customer schedules and orders.
E N D
De-Mystifying Customer CUM's and Requirements Don Thompson EDI Coordinator Continental Strucutral Plastics March 22, 2010
Introduction – Don Thompson Sr. EDI Consultant – RCM Corporation Implemented MFG/PRO Ecommerce and Gentran. Worked with customer schedules and orders. EDI Coordinator – Continental Strucutral Plastics Work with shipping departments resolve EDI issues. BS Computer Science – Slippery Rock University
What We’ll Cover Today • What are Cum Based Schedules. • How does MFG/PRO Handle them. • How will my Prior Cum affect MRP. • How will my Cum Shipped affect MRP. • What are Requirement Based Schedules. • How does Merge RSS affect my ship schedules • Questions and answers
830/DELFOR weekly 03/15/2010 1000 03/22/2010 1000 03/29/2010 1000 04/05/2010 1000 04/12/2010 1000 04/19/2010 1000 862/DELJIT Daily 03/22/2010 200 03/23/2010 200 03/24/2010 200 03/25/2010 200 03/26/2010 200 What are Cum Based Schedules • Prior CUM • 03/15/2010 0 • Shipped CUM • 03/15/2010 0
Setting up a Schedule Order as Cumulative based is done in Schedule Order Maint.
The Netting Logic in Schedule Order Maint tells MFG/PRO what logic to use to generate the required ship schedule. 1 - Use Ship schedule only for Req Schedule2 - Use Plan Schedule only for Req Schedule3 - Use Plan & Ship for Req Sched (replace)
Results that Drive MRP Notice how with netting logic set to 3 that the ship data has replaced the plan data.
Now lets see the results when we set the Prior Cum Req to 19,000 and run the selective update.
After running 7.5.6 Notice the 19,000 in the open qty? This is a result of our setting the prior cum to 19,000 but yet our Cum Shipped was 0 so it believes that we are behind 19,000.
Now lets see what happens when we have a higher Cum Shipped then what our prior cum is set to and how that will effect our MRP.
After running 7.5.6 Notice that there is no demand due until the week of 03/29/10. This is because the prior cum is 19,000 but yet our Cum Shipped was 20,000 so it believes that we have over shipped the 1,000 and adjusts the schedule accordingly.
Setting up a Schedule Order as Requirement based(example’s being Kanban, DO, RAN, SEQ, Order Number) is also done in Schedule Order Maint.
When Setting up a Schedule Order as Requirement you will also be askedShip Complete %Merge RSS?Unique DaysExclude Planning Data
Customer Ship Schedule MaintNotice the “RAN” info in the Reference?
Requirement schedules Open Qty’s are not affected by “CUMS”. In the following example our Prior Cum was 0 and our Ship Cum was 0 notice the open Qty’s? In Requirement schedules the qty will remain open until it is shipped or the qty reach’s the shipped complete % set on the Schedule Order.
Requirement schedules Open Qty’s are not affected by “CUMS”. In the following example our Prior Cum was 20,000 and our Ship Cum was 0 notice the open Qty’s still only reflect what is due vs in a CUM based schedule we would be passed due the 20,000.