Forskningsnettet (FSKnet) optical network upgrade Status for the infrastructure upgrade process April 2008. Nordunet Conference 2008 in Espoo 11th April 2008 Deputy Director Martin Bech, UNI•C martin.bech@uni-c.dk
September 2005 letter to the Ministry: We have seen the future – and it needs more bandwidth!
April 2007: We got the money – but that’s just where the work starts…
What do we need in Denmark? • Our own optical infrastructure • 10Gbps production network • λ-connections for research projects (nationally and internationally) • λ-connections for separate parts of one institution • Hopefully user-controlled λ-network provisioning (in a few years)
AAU DTU AU Ørestad SDU SDU-1 SDU-2 AU-1 AU-2 AAU-1 AAU-2 Wavelengths for the production service DTU UNI-C Ørestad
Is there any research in Denmark requiring λ-networking at all?
The User Community • University reform in 2006/07 reducing 25 institutions to 10 • But this left ”all” Universities with buildings in ”all” cities • Other research institutions than Universities • Potentially 120 addresses • More than 100.000 prople have Forskningsnettet as their daily Internet supplier
First step:Call for tender for WAN connections Framework contracts with multiple vendors for: • Dark Fibre for the National Ring infrastructure • Dark Fibre for Access Connections • Transmission capacity (100Mbps, 1Gbps, 10Gbps, 40Gbps, …) The actual procurement is done in a ”mini-competition” among suppliers qualified in the framework contracts
31st August 2007: Tenders for framework contracts for WAN connections
2nd step:Mini-competition for the National Ring • Among the 3 suppliers on the framework contracts (GC, Telia, Nianet) • Evaluation criteria favoring the shortest possible distance • Contract entered with Global Connect A/S in December 2007
The acquired fibre ring • 1154km length • 8 OADM sites • 11 ILA sites • Distance between any part of two fibre sections/spans: >5m • Attenuation <0.2dB/km @1550nm • PMD < 0.2 ps/√km (currently a problem) • Delivery not yet completed! • Nevertheless, the fibre ring measurements are a preprequsite for the equipment tender
3rd step:Pre-qualification for DWDM equipment suppliers • Announced 8th February 2008 • ≥40 x 10Gbps platform • EoI due 11th March 2008
Suppliers selected for the closed call for tender for DWDM equipment • Nortel • Alcatel-Lucent • Ciena • NokiaSiemens • Conscia (Cisco) Selected on the basis of references, technical abilities, R&D efforts and financial capacity- but not on actual prices
4th step: RFQ and Tender • 1200 km without regeneration • Expandable and upgradable platform • Option for a Metro solution • Great help from local people as well asJanne Kanner from Funet,Afrodite Sevasti, GRNET and theTERENA community in general • Issued 28th March 2008 • Deadline 8th May 2008
5th step: Negotiation process • In May and June 2008 • Reducing the number of suppliers from 5 to 2 and ultimately to 1 • Contract signing envisaged on 7th July 2008
6th step: Delivery and commissioning • Delivery starts with some documentation in July and ends with • Acceptance test is to be passed on 15th October 2008 • Commissioning test to be passed in November 2008.
7th step: Launch Event • At the Forskningsnet conference in Kolding on the 11th November 2008 • You are all invited!
8th step: Operation and enjoyment • Bringing Lambdas into Denmark • Participating in user-controlled Lambda provisioning initiatives • Operations in cooperation with NORDUnet/NUNOC (hopefully)
Lessons learned (so far) • Twisting EU tendering rules to allow for a negotiation process becomes increasingly difficult • You have to do a fair bit of marketing towards the vendors • PMD values below 0.2 ps/√km are not trivial in the real world.