Tom Procter Manager of Contracts and School Organisation, Children, Schools & Families Dept.

LB Merton primary school expansion programme Singlegate Primary School - proposed expansion Chair: Paul Ballatt, Head of Commissioning, Strategy and Performance, Children, Schools & Families Dept. Tom Procter Manager of Contracts and School Organisation, Children, Schools & Families Dept.

bonita
Download Presentation

Tom Procter Manager of Contracts and School Organisation, Children, Schools & Families Dept.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LB Merton primary school expansion programmeSinglegate Primary School- proposed expansion Chair: Paul Ballatt, Head of Commissioning, Strategy and Performance, Children, Schools & Families Dept.

  2. Tom Procter Manager of Contracts and School Organisation, Children, Schools & Families Dept.

  3. Summary • Demographic background • Background to expansion proposal and new proposal to expand Singlegate from 1 to 3FE • Legal process • Building plans

  4. Birth rate increase = additional primary school places

  5. Agreed reception class expansions21 FE to date - 630 extra reception places in 5 years)

  6. Background Autumn 2010 and Autumn 2011 consultations • Singlegate to become 2FE. Phase 1 provides 2 classrooms that will convert to hall and kitchen. Phase 2 due to commence August 2012

  7. Previous expansion plans Phase 2 for Sep ‘13 Phase 1 for Sep ‘12

  8. Previous expansion plans Phase 2 for Sep ‘13 Phase 1 for Sep ‘12 Phase 2 Phase 1

  9. Shared area landscaped (still in new plan)

  10. Spring to August 2012 • Council entered negotiations to purchase Jamia building. • Phase 2 plan postponed then cancelled • Building purchase completed late August 2012

  11. Singlegate and Jamia buildings

  12. New proposal Singlegate provides 2 reception classes again in September 2013 Through Jamia building Consultation on permanent expansion from September 2014 to 3FE/pre-planning application • Education:> Consider > Publish a statutory notice > Decision > Statutory duty to implement, subject to planning permission • Planning: > Consider and develop > Planning application process > Decision by Planning Committee

  13. New proposal • Existing Singlegate school building – lower school and main halls • Jamia School building – upper School. Major adaptation work but no/minor extension • Shared area for the park