An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 现代服务业指挥部重点项目12月份进 度 市效能办、市现服办 2013年12月

  2. 现代服务业在建项目 • 1、财富中心 • 2、万豪建材大市场二期 • 3、汇金商业广场 • 4、华安证券 • 5、冷链物流 • 6、巴黎公馆 • 7、盛唐现代城 • 8、天瑞国际酒店

  3. 11月份进度 12月份进度 1.财 富 中 心 主体项目竣工 2幢主楼地上部分外墙漆过半,2幢裙楼内、外装结束,拆除围墙、 整理外围场地

  4. 11月份进度 12月份进度 2.万豪建材大市场二期 21层在建 23层在建

  5. 11月份进度 12月份进度 3. 汇 金 商 业 广 场 11号楼已封顶;10号楼7层,9号楼8层,12、13、14号楼3层。 2号楼已建至3层,超计划么进度。 完成12、13、14号楼2层,11号楼8层,10号楼6层,9号楼7层在建。

  6. 11月份进度 12月份进度 4.华 安 证 券 已完成选址,现正在进行装修 装修工程完成,正在申请消防验收。

  7. 11月份进度 12月份进度 5.冷 链 物 流 项 目 围墙拉建己进场施工,正在做骨架搭建,土地平整调整为交承建方总包,线杆迁移正在推进。 完成公司注册,协商地块内线杆迁移方案,平整土地

  8. 11月份进度 12月份进度 6.巴 黎 公 馆 施工许可证已办理,完成整体基础,地下室一层钢筋绑扎完成70%。 施工图审、许可证正在办理,基础建设。

  9. 11月份进度 12月份进度 7.盛 唐 现 代 城 施工许可证已办理,完成地下室整体基础,完成7号楼一层建设(超月计划进度)。 施工许可证正在办理,7号楼地下室完成。

  10. 11月份进度 12月份进度 8.天 瑞 国 际 酒 店 完成第三层梁板柱砼浇筑 完成第五层梁板柱砼浇筑,六层钢筋绑扎。