1 / 7

DCS Network

DCS Network. Close-out. DCS Network. DCS Network covers: Ports in SG2 for Gas systems (26) Few ports in ACR (DCS dedicated equipment) (4) Majority of ACR is DAQ network Ports in CR1-CR4, for DCS equipment (~120) Mainly CR3 (PCs) and CR4 (detector equipment)

brand
Download Presentation

DCS Network

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DCS Network Close-out

  2. DCS Network • DCS Network covers: • Ports in SG2 for Gas systems (26) • Few ports in ACR (DCS dedicated equipment) (4) • Majority of ACR is DAQ network • Ports in CR1-CR4, for DCS equipment (~120) • Mainly CR3 (PCs) and CR4 (detector equipment) • [CR1: DAQ network, CR2: HLT network] • Ports on CR5 (plug) for gas, safety and detector equipment (18) • Ports in UX (250 ports + 40 ‘uplinks’) • “ALICE” Switches in UX • to connect detector FE such as DCS boards, RCU etc. • Connection into the detector up to detector FE Installed and maintainedby IT/CS Installed andmaintainedby ALICE ALICE Technical Board

  3. DCS Network - GPN • GPN (General Purpose Network) is currently only available in: SXL2, CR1-4, ACR and offices above ACR • The GPN will be installed/extended in the same installation campaign in those places where there is no GPN (or insufficient) available. Mainly • Gas building SG2 (10) • CR5 (plug) (4) • UX (50) • Outside barracks ALICE Technical Board

  4. 1 10 4 1 2 1 3 1 2 5 10 10 10 5 1 4 4 4 1 4 1 4 2 2 1 2 1 Laserhut 1 5 4 6 2 2 2 2 Cooling 3 2 3 1 4 10 3 2 3 1 5 6 4 2 4 4 4 4 2 1 10 1 1 1 5 10 10 10 6 1 • DCS network in UX -- [power supplies, VME crates etc.] • For fixed installed equipment • Based on: rack layout, DCDB, individual requests • 248 ports, only in racks • Connected to switches, installed and maintained by IT/CS • In ‘starpoints’ located in CR5 (plug) and US25 N ALICE Technical Board

  5. 9 6 6 9 1 10 4 1 2 1 3 1 2 5 10 10 10 5 1 4 4 4 1 4 1 4 2 2 1 2 1 Laserhut 1 5 4 6 2 2 2 2 Cooling 3 2 3 1 4 10 3 2 3 1 5 6 4 2 4 4 4 4 2 1 10 1 1 1 5 10 10 10 6 1 • DCS network in UX -- [power supplies, VME crates etc.] • 248 ports, only in racks • DCS network in UX -- [“ALICE” switches for DCS boards, RCU] • Baseline: 1 Gbit uplink per group of switches (15) • Additional request from TRD: 1 uplink per switch (+26) • Total of 41 uplinks N ALICE Technical Board

  6. 9 6 6 9 1 10 4 1 2 1 3 1 2 5 10 10 10 5 1 4 4 4 1 4 1 4 2 2 1 2 1 Laserhut 1 5 4 6 2 2 2 2 Cooling 3 2 3 1 4 10 3 2 3 1 5 6 4 2 4 4 4 4 2 1 10 1 1 1 5 10 10 10 6 1 • DCS network in UX -- [power supplies, VME crates etc.] • 248 ports, only in racks • DCS network in UX -- [“ALICE” switches for DCS boards, RCU] • 41 Gbit uplinks • GPN network -- [e.g. for commissioning/debugging] • Wireless (enough to cover whole cavern) • ~50 ports ‘strategically distributed across rack areas’ • Exact locations being defined now N ALICE Technical Board

  7. Summary • All “IT/CS installed” network (DCS & GPN) has been ordered • Installation will start end of the month, through April • For “ALICE installed” part: • Switches were tested by TRD, wait green light for ordering • Cables into detector are in cable DB and length checked • Minor modifications might still be possible while installing • More important changes will need an additional installation campaign • With its costs and uncertain delays ALICE Technical Board

More Related