An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Implementing EV in ITA Three Step ApproachJohn ChapmanTouchstone Ltdjohn.chapman@touchstone.co.uk

  2. EV in IT • Implementing Earned Value Management requires a change of working practice. Not only do Project managers need educating in EV but • Project accounting has to be setup to track the • financial values • Project delivery methods have to take into account • how to ‘Earn the Value’ i.e. how do we evidence • that we have completed the deliverable by type of • work • Tools implemented to track items such as Schedule • Variance against baseline plan

  3. A way of approaching • Instead of trying to achieve all these at once a proposal is to split this into three levels representing three levels of maturity • Level 01: Focus on the financial values • Level 02 : Implement changes to the delivery • method so the BCWP can be calculated (i.e. how are • you going to earn the value by the type of work) • Level 03: Track schedule variance, SPI, TCPI and • so forth

  4. Level 01: The Financials • Work out how you are going to calculate 8 elements: • ACWP • BAC • CV • CWBS (do your PMs produce a WBS?) • EAC • ETC • PMB

  5. Level 01: Planning • From a planning perspective you need: • Planned time (for each WBS element) • Actual time (by WBS) • Remaining effort (so you can calculate ETC) • Baseline (to calculate the spend over a period of time) • Planning package (so you know what to do when) • Work Package (to get individuals to do their work)

  6. Level 01: Planning • From a planning perspective you need: • Planned time (for each WBS element) • Actual time (by WBS) • Remaining effort (so you can calculate ETC) • Baseline (to calculate the spend over a period of time) • Planning package (so you know what to do when) • Work Package (to get individuals to do their work)

  7. Level 02: Earning the value • This takes more work as for each activity you need to define how you are going to ‘Earn the value’ • Is it going to be • 50 – 50 • Budget Milestone • 100 – 0 • etc • etc

  8. Level 02: Earning the value • For example on an IT Project • Training is 0-100 : either you are trained or not trained! • Design could be by budgeted milestone • 25% on completion of a design workshop • 50% on issuing a design document • 25% on design signoff

  9. Level 02: The financials • There are 6 elements to this: • BCWP (Earned) • BCWS (Planned) • Cost Variance % • CPI • Management Reserve • Undistributed budget

  10. Level 02: Planning • From a planning perspective you need: • Duration Variance • % Complete • how are you going to identify the physical % complete? • What skills do your team need to say whether they are 50% or 60% complete? • How will this be proved?

  11. Level 03: The financials • At level 03 we are calculating values compared to time and productivity • SV • SV % • SPI • TCPI

  12. Level 03: The financials • The TCPI ‘provides a projection of the anticipated performance required to achieve either the BAC or the EAC’1 • The TCPI might tells us what we need to do – but how are we going to achieve improvements in Productivity? • 1. http://en.wikipedia.org/wiki/Earned_value_management

  13. Summary • Level 01: is about calculating the financial values • Level 02: is about confirming the method of ‘earning the value’ • Level 03: is about understanding the schedule and changes to the schedule