1 / 25

PTCS QA and Training

PTCS QA and Training. FY 2007 findings Bruce Manclark, Bob Davis, Jennifer Williamson, Martín Wilson, Ken Eklund. Overview. QA summary Lessons learned from QA BPA PTCS plans for this year PTCS training. QA Overview.

brant
Download Presentation

PTCS QA and Training

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PTCS QA and Training FY 2007 findings Bruce Manclark, Bob Davis, Jennifer Williamson, Martín Wilson, Ken Eklund

  2. Overview • QA summary • Lessons learned from QA • BPA PTCS plans for this year • PTCS training

  3. QA Overview This is the first round of heat pump and duct inspections that has been done (other than STAC detailed monitoring). Elements looked at • Duct leakage • HP controls, airflow, charge While not as comprehensive as STAC, the results of our QA are generally encouraging.

  4. QA Agents Alan VanZuuk • NW ENERGY STAR • Home Builder Bob Davis • Ecotope • STAC Monitoring Bruce Manclark • Delta T • Pasture Golf Bruce Manclark – Pasture Golf Champion of Goldendale WA

  5. PTCS Summary • Total installers – 250 have done at least 1 • Total heat pumps + duct sealing done – 510 • Total duct seals done – 1,500 • Total heat pumps done – 1,300 This flux capacitor is miscalibrated.

  6. QA Summary Duct Sealing • 1,500 Systems done, 55 inspected • 50 passed, 5 failed and had follow up • 23 contractors have done 5 or more Heat Pump (including duct sealing) • 510 Systems done, 43 inspected • 34 passed, 9 failed and had follow up • 54 contractors have done 5 or more The goal is to inspect 10% of all systems

  7. Examples of Failed QA Notes Ducts “QA measured 170 CFM50 both sides to out vs. installer’s 116. House is 1400 ft2. The system is too leaky to meet 10% criteria. “ “QA measured 101 cfm50 leakage to outside, a 3 cfm50 reduction from the original test. The target is 56 cfm50.The original duct sealing form submitted by the contractor stated 63 cfm50. “

  8. Examples of Failed QA Notes Heat Pumps “QA measured 305 CFM per ton. QA recommends the technician increase the airflow to at least 350 CFM per ton.” “Controls: Outdoor sensor for ODT installed too close to hot vapor line; sensor reads warmer than actual temperature. Strip heat stays off even when it would be appreciated by the occupants.”

  9. QA – Some issues we saw • One brand of heat pumps generally needs to have the outdoor unit size tap set ½ ton larger than the actual system size to get the desired airflow • Control of strip heat • With training and improved thermostats, this has gotten easier to do right • Utilities now check them often, so they are more consistently correct • Sizing, while not addressed in detail, could be

  10. Failed Heat Pumps All heat pump QA Portion of test failed 79%passed

  11. QA – What We Learned We’re still in the early phase of this project; with more QA, we will have a clearer picture of performance. • Installs are generally pretty good • Many fails are on the new parts of the commissioning (controls, TrueFlow, etc.) • QA works. It adds value and improves program credibility with installers Increased utility personnel capability. (i.e., they can go into Honeywell 8000 thermostat and see the outdoor lockout setting)

  12. QA – Remaining Challenges • New technologies (9.0 HSPF, 15 SEER, everything has Vista) can be troublesome • Even with QA, we don’t measure energy savings over time, just a snapshot of performance • Coordination of QA visits is tougher than we thought

  13. STAC – In Comparison STAC monitoring showed generally good performance, at least after problems were identified and fixed.  Some findings that deserve attention: • Dual stage compressors – some are lemons • Energy usage for the defrost cycle flies below ARI's radar (but field adjustments can limit the damage)

  14. ENERGY STAR • We don’t inspect ENERGY STAR jobs (but we do inspect new construction heat pumps) • 6 were inspected in Bend and Vancouver • 1 failed (the compressor wouldn’t start)

  15. CheckMe! • 12 CheckMe! heat pumps were inspected • 2 failed • 1 outdoor sensor installed near a warm liquid line • 1 had low airflow

  16. Utilities • Some utilities come to inspections, and the help is always appreciated • Having a local active utility is a big factor in getting good QA results • Utilities seem to generally be appreciative of QA

  17. QA in FY2008 We have a projected 3,000 systems in FY2008, which means we will do 300 QA inspections. • We would like to refine the sampling to focus QA where it is most needed • Lower inspection rate for contractors with demonstrated capability • Get to far flung reaches of the territory • We will increase our pool of knowledge

  18. Training Overview High demand for training caused us to evaluate how to increase capacity to certify new technicians. As a result, “The Goldendale Summit” was convened, with the following result:

  19. Master Technician The “Master Technician” path will allow specific qualified technicians or utility staff to train technicians in their territory This will be people like Bryan Boe, Zach Erdmann, Mattias Jarvegren (Clallam PUD), Darryl Knabe (Mountain View Heating), etc.

  20. Training This new way to deliver training will complement, not replace current classroom based training. It will be a good way to increase response to demand for training new technicians Thanks to Ken Eklund for writing updated PTCS Provider Standards

  21. Master Technician Qualifications Minimum 2 years full time experience (or equivalent) AND Minimum 30 systems tested or commissioned OR An individual may be certified as a PTCS Trainer by an existing Trainer based on direct observation of the individual’s classroom and field instruction.

  22. Trainer’s Latitude • New trainers can certify in their vicinity or company • They are responsible for producing technicians who can meet PTCS specs (and may lose their trainer status) • Trainers are responsible for notifying Ecos when they believe a technician is ready to be tested • Ecos is evaluating using online testing

  23. Certification Path Master technician provides on the job training and hands on field work. • Follows current curriculum • Sets the pace and structure for each tech • Integrates with the firms needs • Has a vested interest in doing a good job, because certification can be revoked

  24. Classroom Training The BPA is moving to a 50% cost sharing requirement for training in 2008. • 1 Day Heat Pump Training - $2,000 • 3 Day Duct Sealing Training - $3,400

  25. FIN

More Related