1 / 28

A2 Operations Management

A2 Operations Management. Critical Path Analysis. How long will it take?.

britain
Download Presentation

A2 Operations Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. A2 Operations Management Critical Path Analysis

  2. How long will it take? • Walls have decided to launch a new Magnum ice cream. Machine delivery will take 9 weeks, installation takes 5 weeks, staff recruitment 4 weeks and training a further week. Suppliers need 2 weeks lead time and the trial production run will take 2 weeks. • How long until the new magnums will be in the retailers fridges? • Answers? • 22 weeks? • Longer? • Shorter?

  3. Prepare a grid.

  4. Answer

  5. Critical Path Analysis • The process of planning the sequence of activities in a project in order to discover the most efficient and quickest way of completing it. • Widely used in industries such as construction where it is possible to operate a range of activities in parallel • By mapping out the network of different activities firms can see which activities can be run at the same time • It also allows firms to see which activities can not be delayed without holding up the overall project

  6. Critical Path Analysis involves constructing a network diagram. • A node denotes the start and finish of an activity. It is split into 3 sections • An arrow represents an activity which is labelled and put above the arrow. Each activity has a duration which is put underneath the arrow. Earliest start time (EST) that an activity can commence and depends on the completion of the previous activity Number of the node. Provides a unique identity 1 Latest finishing time (LFT) of the previous activity without delaying the next activity A 5 days

  7. This diagram represents a project with four activities - A,B,C and D. D can not start until C has been completed. B C A D 1 2 3 4

  8. Student activity • Draw a network using the following information: A,B and C begin together. D follows A, E follows B, F follows C and E.

  9. Answer A D B E F C

  10. Constructing a critical path network • Prerequisite - the activity that must be completed before our selected activity can occur. E.g. digging foundations for a house before building the walls

  11. Constructing a critical path network • Step 1: Draw a node to represent the start of the network. All networks must start and end with a node. Do not draw a node at the end of an activity line immediately, ensure it is right first. A node represents the point at which a new activity can begin. • Step 2: Identify activities with no prerequisites. Draw lines from left to right from node 1. • Step 3: Label activity lines with description and duration • Step 4: Move onto the first activity with a prerequisite. Place a node at the end of the line and draw the next activity which is reliant on the previous activity being completed. • Step 5: Repeat steps 3 and 4 until complete. Then calculate the ESTs and LFTs. Then the critical path can be established.

  12. Constructing the Critical Path Analysis • Earliest starting time (EST) - Move forward through the nodes and always pick the largest of the options. Work right choosing the highest option for each node. • Latest finishing time (LFT) - move back from the final node and always pick the smallest of the options. Work left choosing the lowest option for each node.

  13. The Critical Path • The sequence of activities that cannot be delayed without delaying the overall completion of the project. • It is represented by activities that have identical LFTs and ESTs and it is the longest path between nodes.

  14. Student activity - Complete the critical path analysis for the following project. Identify the critical path.

  15. A 5 B B D C 7 9 0 3 2 3 4 1 7 9 0 3 2 3 3 4 D C 2 4 Answer The critical path is B, C, D

  16. Tips • Always ask your self the question: What activity can I do next? • A node is like a full stop. It must go at the end of an activity, it does not represent an activity

  17. Critical path analysis - Lesson 2 - Recap • Critical path analysis is a way of showing how a lengthy and complex project (e.g. a building project, marketing campaign) can be completed in the shortest possible time. • It shows which of the activities are ‘critical’ - this means that if these activities are delayed, then the project will not be able to be completed on time.

  18. Student Activity - Produce a critical path for the following project. Identify the critical path.

  19. Node 1 always start with anESTof zero and should have anLFTof zero Answer • Step 1 - Draw the activities and nodes in the correct order • Step 2 calculate the ESTs and LFTs • EST - Earliest the next activity can begin • LFT - latest finishing time that the previous activity can finish without delaying the next activity LFT = work backwards subtracting the activity from the previous LFT if there is an option choose the smallest value EST= Previous EST plus activity length (between node 1 and 2: 0 + 6 = 6) EST F A B 0 G 6 14 19 21 1 2 4 5 6 0 6 7 6 15 4 2 19 21 C D 5 3 LFT E 3 11 If you have a choice between two different EST values as at node 4 choose the biggest 11 8

  20. Step 3 - Label the Critical Path • The critical path is the sequence of activities that cannot be delayed without delaying the overall project completion. • It is represented by the activities with identical ESTs and LFTs and the longest path between the nodes • The critical path for the previous example would be: • Critical path A,C,E,G • On the diagram the critical path activities will be symbolised with two lines through the activity line

  21. Float Times • Float time - the amount of time that non-critical activities within a project can be delayed without affecting the deadline for completion of the whole project. • Total float for an activity- the amount of time an activity can be delayed without delaying the whole project • Total Float for an activity= LFT -EST - duration of the activity • E.g. Activity D = 15 - 11 - 3 = 1 day • Therefore the activity may be delayed by 1 day without affecting the whole project

  22. Critical Path Analysis • Produce a critical path network for the following Marketing campaign. Calculate the EST, LFT, critical path and total float for each activity A

  23. 0 3 2 1 0 3 B D 8 3 21 10 5 3 13 21 Calculating float times Float for the activity = LFT – EST - Duration Float for this activity = 3 – 3 - 0 = 0 Float for this activity = 21 – 10 - 8 = 3

  24. Float times for Marketing strategy activity • A = 4 - 0 - 4 = 0 • B = 13 – 4 – 6 = 3 • C = 11 – 7 – 4 = 0 • D = 21 – 13 – 8 = 0 • E = 21 – 11 – 10 = 0 • F = 30 – 21 – 9 = 0 • G = 35 – 30 – 5 = 0

  25. Student Activity • Complete the exam question 2 a) for January 2005 Unit 4 exam paper

  26. Answer January 2005 Question 2a)

  27. Problems of using CPA • Can encourage rigidity • If every activity is strictly time-tabled a delay in a critical activity may result in a greater overall delay • CPA focuses on speed of completion rather than quality • CPA relies on estimated completion times • Complex projects may be difficult to produce • Sub-contractors are outside of the firms control and may not stick to deadlines • Supplies may be delayed

  28. Business Implications of Critical Path Analysis • Read and highlight the information on the business implications of using CPA • Complete questions 1 and 2 on the information sheet • For both critical path questions calculate all ESTs, LFTs, the critical path and the float time of each activity

More Related