40 likes | 64 Views
This project aims to address issues such as water supply, tree cutting, expediting the establishment of a 33 KV sub-station, external sewerage system, and widening the external road network at AIIMS Raipur. The local electricity department has declined to sanction the electrical load at 11kV but may relax to provide connection at 11 KV in consultation with the commission. Flexibility in voltage levels according to system availability is crucial.
E N D
AIIMS-RAIPUR Project Consultant HSCC
Issues local electricity department has declined to sanction the electrical load in 11kV. However they may relax to provide connection on 11 KV instead of 33 KV as there is provision in State Electricity supply code. “Provided that depending on system availability or condition, the licensee at its discretion, may release supply at any other voltage in consultation with the commission. Particularly in case of Railways, the maximum and minimum limits of contract demand on the various voltage levels indicated in the above table may be relaxed by the licensee on mutual agreement depending on the actual requirement and feasibility. “
Issues • Water supply up to Hospital • Tree Cutting still pending • Establishment of 33 KV Sub-station to be expedited • External sewerage system to be expedited • External Road net work to be widened.