1 / 32

Introduction to EIS/EA

Introduction to EIS/EA. Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation. Classes of Action. Class 1 - Environmental Impact Statement Significant Impacts Class 2 - Categorical Exclusion No S ignificant Impacts

Download Presentation

Introduction to EIS/EA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Introduction to EIS/EA Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  2. Classes of Action • Class 1 - Environmental Impact Statement • Significant Impacts • Class 2 - Categorical Exclusion • No Significant Impacts • Class 3 - Environmental Assessment • ??????? Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  3. Significant - Context and Intensity Context • Effects upon environment, geographic area, setting, socioeconomic profile • What’s there? Intensity • Magnitude, severity • Howbad is it? Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  4. EIS Major Steps • Scoping • Notice of Intent (NOI) • Draft Environmental Impact Statement (DEIS) • Circulation Period • Public Hearing • Final Environmental Impact Statement (FEIS) • Record of Decision (ROD) Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  5. SAFETEA-LU • Section 6002 • Efficient Environmental Reviews for Project Decision-making • New Procedures for EISs • Optional for EAs and CEs Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  6. Lead Agencies • Federal Lead Agency – USDOT (FHWA) • Joint Lead Agency – Project Sponsor Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  7. Role of Lead Agencies • Everything we normally do, plus…. • Identify & Involve Participating Agencies • Develop Coordination Plans • Provide Opportunities for Involvement • Manage the process and resolve issues • Ensure the environmental review process moves forward in a timely manner Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  8. Participating Agency • Any federal or non-federal agency that may have an interest in the project • Must be invited by lead agency Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  9. Declining an Invitation Federal Agencies If a federal agency chooses to decline, the response letter must state they: • Have no jurisdiction or authority with respect to the project • Have no expertise relevant to the project • Do not intend to submit comments If the response does not state their position in these terms, treat them as a participating agency Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  10. Declining an Invitation Non-Federal Agencies • A state, tribal, or local agency must respond affirmatively in order to be designated as a participating agency • If they fail to respond or decline the invitation, regardless of the reasons, they should not be considered a participating agency Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  11. Opportunities for Involvement • Purpose & Need • Range of Alternatives • Evaluation of Alternatives Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  12. EIS Format • Cover Sheet • Summary • Table of Contents • Purpose and Need • Alternatives • Affected Environment • Environmental Consequences • List of Preparers • EIS Distribution • Comments and Coordination • Index • Appendices Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  13. Notice of Intent • Timing – prepare an environmental document or prepare an EIS? • Content • Proposed action • Alternatives • Scoping process Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  14. Summary • Description of Proposed Action • Other Federal Actions in the Area • Reasonable Alternatives Considered • Major Environmental Impacts • Areas of Controversy/Unresolved Issues • Other Federal Actions as a Result • 404 permit, 106 agreement, etc. Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  15. Make it Reader-Friendly • Summarize Data • Tables and Graphics • Pictures • Compare Information • Minimize Text • Technical Information in Appendices Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  16. Purpose and Need • Importance • What if we don’t do anything? • Range of Alternatives • Establishes the yardstick • Basic Elements • Mobility, safety, system linkage, economic development etc. • Use in Decision-Making • Screening, justification, and impacts Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  17. Alternatives • Describe how preliminary alternatives were developed and basis for their elimination • Describe how reasonable alternatives were selected • Compare level of detail • Include discussion of “no build” • Discuss TSM alternative where applicable • Graphics • Presentation Techniques Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  18. Affected Environment • Existing Setting • Social • Economic • Environmental • Environmentally Sensitive Features • Engineering Features • Topography, Facilities, etc. • Photographs and Graphics • Planning process with maps Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  19. Environmental Consequences • Section 4(f) Properties • Historic Sites • Wetlands/Floodplains • Farmlands • 10. Other ????? • Relocations • Noise, Air, Water • Land Use • Economic • Social Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  20. List of Preparers • FHWA, state, consultant or other agency persons who made substantial contribution to the preparation • Qualifications, including education background and/or experience. • Areas of EIS responsibility • FHWA officials responsible for review • If not included above Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  21. Comments and Coordination • Early coordination process including scoping and Participating Agencies • Meetings with groups and/or individuals • Results, not just times, dates, and numbers) • Key issues and pertinent information received from public and government agencies • Every comment deserves a response Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  22. Final EIS Options • Traditional - “New” document • Condensed - Summary of changes • Abbreviated - Re-circulate DEIS Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  23. Condensed FEIS • Reference & summarize DEIS information • Discuss changes • Identify Preferred Alternative & basis • Alternatives not selected & basis • Mitigation & enhancements • Unresolved issues • Comment & coordination • Final 4(f) Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  24. Abbreviated FEIS • Minor changes only • DEIS attachments contain: • Extra sheets • New section with items as shown in condensed version Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  25. FEIS Distribution • File with EPA • Cooperating & Participating Agencies • DEIS Commenters • Requestors • Publish Availability in Local Newspapers • Make Available Locally • Library, City Hall, District Office, etc. Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  26. Record of Decision (ROD) • Decision, including 4(f) Determination • Alternatives Considered & Preferred • Mitigation • Monitoring/Enforcement • Responses to Comments on FEIS • May be submitted concurrent with FEIS Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  27. EA • A document prepared for an action where the significance of the environmental impacts is not clearly established Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  28. EA Major Steps • Early Coordination • Environmental Assessment (EA) • Circulation Period • Finding of No Significant Impact (FONSI) Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  29. EA Content • Concise Public Document • Briefly provide evidence and analysis • Include brief discussion of… • No long descriptions or detailed data… • CEQ suggested page limits - take a guess Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  30. EA Suggested Format • Cover Sheet • Purpose & Need • Alternatives Considered • Impacts/Mitigation • Comments & Coordination • Section 4(f) • Appendices Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  31. Finding of No Significant Impact (FONSI) • Briefly presents why an action does not have a significant impact • Must include or reference the EA Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

  32. EA and FONSI • Does not need circulated • Notice of Availability: • Clearinghouse • 30 Day Comment Period Managing the Environmental & Project Development Process Presented by the Ohio Dept. of Transportation

More Related