Steering Committee Meeting Statewide Financial Management System Update

Steering Committee Meeting Statewide Financial Management System Update. November 14, 2008. Today’s Topics. Project status – Kent Change Control Log – Peggy Project risks – Gary Labor distribution analysis – Gary. The 1 st Six Months of the Project. Mid-April. mid-March. Oct 6 th.

bstites
Download Presentation

Steering Committee Meeting Statewide Financial Management System Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Steering Committee MeetingStatewide Financial Management System Update November 14, 2008

  2. Today’s Topics • Project status – Kent • Change Control Log – Peggy • Project risks – Gary • Labor distribution analysis – Gary

  3. The 1st Six Months of the Project Mid-April mid-March Oct 6th mid-January mid- November mid-October Begin FMS Team Training Begin Conference Room Pilots Project Kick-off Build-out of Data Center Including SHARP II Interface Standards Complete and Published to Agencies Analysis Complete for COA, KDOT, SRS and Treasurer Systems

  4. Project Activities • Conference Room Pilots (CRPs) • Identifies gaps between Kansas’ desired future business processes and requirements against the processes directly supported by PeopleSoft • Analyzes identified gaps and defines the Reports, Interfaces, Conversions, Extensions, and Workflows inventory • Identifies process changes needed to mitigate gaps • Uses an Oracle-hosted environment with PeopleSoft software pre-configured for prototyping • Using PC sharing technology for agency participation for agency personnel in remote locations

  5. Project Activities (cont.) • Project team training courses - Completed • General Ledger • A/P & Purchasing • A/R Billing • Query • Asset Management • Numerous technical courses for tech team • Upcoming courses • e-Procurement • Project Costing • Contracts

  6. Project Activities (cont.) • Chart of Accounts design • Inter-agency team lead by Annette • Drafted chart of accounts in review by team • Presented to ASTRA last week • Areas of potential change • Organizational structure – Agency (3) - Division (2) in STARS to Department ID (10) • Transaction codes – no longer used • Index codes – no longer used • Agency use (13) in STARS to Chartfield #1 (10) • Object codes (4) in STARS to Account (6) • Elimination of Index will be significant impact to numerous agencies and will require

  7. STARS vs. FMS Chart of Accounts

  8. Project Activities (cont.) • Configuring GL business units • Foundation decision – cannot easily be reversed • Complex decisions with numerous trade-offs (configuration, maintenance, impact on agencies) • Detailed analysis of alternatives and pros and cons for each alternative • Consulting with other States (OH), STA and Oracle • Data center hardware • Ordered servers (DEV, TST) from Sun in late-October • Will arrive next week

  9. Change Control Log • Regular agenda item beginning this month • Changes to the Statement of Work • Added a deliverable for SHARP integration Design (mistakenly combined w/ the SHARP Analysis deliverable); split funding equally among the two deliverables • Refined schedule and SOW by moving the dates for five deliverables1-2 months later; no overall schedule impacts • Eliminated e-Grants analysis ($58K); polled agencies during grants business process mapping sessions and did not validate that this was needed by a critical mass of agencies

  10. Project Risks • Risk management workshop held with Accenture on 11/12 • Identified over 30 project risks • Ranked and prioritized risks (probability and impact) • Assigned risks to teams • Teams will develop risk mitigation for priority risks • Prioritized risks will be reported on weekly and monthly basis

  11. Status of Labor Distribution Analysis • Four of 14 agencies left to visit (KBI, Aging, KDHE, Corrections) • Agencies who want central labor distribution solution fall into two camps: • Agencies that would like to retain their existing system and interface to SHARP (some do now some do not) • Agencies that either do not have a time capture system or would like to retire their existing one • Evaluating possibility of implementing PS Time and Labor electronic timesheet with optional self-service capabilities • Oracle will provide a demo of Time and Labor 11/18 @ 1pm • Invitees include: A&R, DPS, DISC, Agriculture, Highway Patrol, Labor • Central labor distribution analysis briefing and decision in January

  12. Questions and Answers For additional information on the project, please see the project website: http://www.da.ks.gov/ar/fms/ ?

  13. Back-up • Changes to Object codes/Accounts: • 6-digit object code with the 1st character a GL account, characters 2-5 the current object code and a 6th character for expansion – impacts many agency systems • Eliminate BPC specific Codes (xxx8) • Eliminate the agency specific designations, for example, 4070 Road and Highway Machinery and Equipment (Agencies 276, 710) • Eliminate codes based on dollar amounts (non-inventory and inventory) • Eliminate codes no longer used • Add codes to further define “other” categories, such as 2790