RENEWABLE ENERGY – FROM POLICY TO REALITY Ł u b i a n k a P o l a n d 1 5 M a y 2 0 1 2 RuralCommunitieseffortstowardsRenewable Energy Jerzy Zająkała Mayor of the Łubianka Community Presidentof theEuropean Alliance Group
Characteristics of The Commune of Łubianka Kujawsko-Pomorskie Voivodeship Toruń County • Number of inhabitants - 6524 • Area - 8464 ha • Villages - 14 • Distance from Toruń – 7 km • Distance from Bydgoszcz – 22 km • Distance from Warsaw – 200 km • Distance from Brussels – 1200 km „RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012
Monuments „RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012
„RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012
„RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012
10.02.2009 – signing Ceremonyof ,theCovenant of Mayors in the European Parliament in Brussels Themaingoal of theinitiativeis to reduce CO2 emissionbeyondthe 20% by 2020 through: • an improvementinthe energy effectiveness by the 20% atleast • increasing the output of the energy from renewable sources beyond 20% • 31.03.2010 – adoption of The Sustainable Energy Action Plan by the Community Council „RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012
The Sustainable Energy Action Plan The list of thepotentialvariants of possibilities
Accepted undertakings for the realisation • exchange of coal boilers to gas boilers (347 pieces) – 867.500 € • exchange of coal boilers to biomass boilers (339 pieces) – 847.500 € • thermomodernisation of residential buildings (in 336 buildings) – 2.940.000 € • solar collectors (in 485 buildings) – 1.818.750 € • photo-voltaic cells to the production of the energy (in 28 buildings) – 280.000 € • energy managing (15.000 €/y x 10 years) – 150.000 € • total expenditure – 6.903.750 € „RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012
Thephases of thesolarprojectpreparation • 15.06.2010 - submission of an application for funding the project partially from theRegional Operational Program • 9.11.2010 – resolution of The Board of Directors of the Kujawsko-Pomorskie Region about granting the subsidy • 30.12.2010 – conclusion of theagreementwith The Marshall of the Kujawsko-Pomorskie Region • the grant – 1.577.925 € (75% of thetotalinvestment value) • thetotalvalue - 2.103.900 € • from 10 March 2011 to 26 August 2011 – tender procedure • 6.09.2011r. – conclusion of theagreement with the contractor of the investment „RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012
Theoutcome of the project „RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012
Theoutcome of the project • 680– number of thesolar collectors installed on private buildings • 15– number of thesolar collectors installed on public buildings Technology • vacuum collector • heating water (250 – 500 l) • aiding heating of the building • useful power of collectors (30 pipes) - 2.373 W „RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012
EnergyManagement Creatingtwonewpositions: • thepositionresponsible for optimisation of the electric energy using • thepositionresponsible for applyingrenewable energy sources Ourgoal - 44,6 % „RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012
Thankyou for yourattention „RuralCommunitieseffortstowardsRenewable Energy” - Łubianka, Poland, 15 May 2012