Welcome to “World Bank Mission” (05 th – 16 th May, 2014). Hydrology Project Phase - II Gujarat – Ground Water ( GWRDC Ltd ) Narmada, Water Resources, Water Supply and Kalpsar Department GANDHINAGAR. Gujarat – Ground Water Status of Financial Progress achieved. (Rs. In ‘000’).
E N D
Welcome to“World Bank Mission”(05th – 16th May, 2014) Hydrology Project Phase - II Gujarat –Ground Water (GWRDC Ltd) Narmada, Water Resources, Water Supply and Kalpsar Department GANDHINAGAR
FINANCIAL PERFORMANCE: GUJARAT – GW Details of Expenditure up to March, 2014 - (Gujarat - GW) (Rs. In Million)
Status of Financial Targets and AchievementGujarat – Ground Water Gujarat SW
Status of Disbursement of Claims (Gujarat – + GW) Details of Claims of Expenditure disbursed up to March - 2014 • Claims of expenditure from January - 2014 to March - 2014 of Rs. 0.727 Million has been submitted to CAAA on 28-03-2014.
Gujarat – Ground Water Major Physical Achievement & Out Come
Upgraded the Piezometer network by Construction of 228 Piezometers , 80 Piezometers in DSS Basin , 16 Piezometers in Porbandar (PDS) district,8 Piezometers and 3 Recharge tube wells in Dharoi RBC(PDS), • Procurement of 26 DWLRs and it’s installation in 26 districts • Procurement of 11 layers of GIS Data set from BISAG, LISS IV data from NRSA. • OSM data of Gujarat state from SOI , ARC GIS software, computer Hard ware and peripherals , Office equipments & Training equipments • The end Users oriented Awareness Raising Seminars at District and Taluka level along with publication of informative brochures and Year book up to year 2013
Organization of study tours for knowledge and experience sharing. • Establishment of DSS cell at Ground Water Division -1,Ahmedabad • Awareness for HIS Data increases day by day • http://gwrdc.gujarat.gov.in/ has been developed with the assistance of National Informatics Centre (NIC). It is also regularly updated and linked with departmental website http://guj-nwrws.gujarat.gov.in/.
Significant change in availability and reliability of Ground water Data led to Ground water development and Management planers more appropriately & economically. • Establishment of Computer based systems , detailed data quality control systems , Coordination with central agencies , specially trained staff by Training programmes is essential to improve accuracy and reliability of data. • Awareness Raising Programmes are very useful to improve interaction between data providers and data users.
DSS(P) tools can be useful to understand Ground water resources issues within a river basin after Fine Tuning of application and with good support from NIH. • The PDS study on Coastal Groundwater Dynamics and Management in the Saurashtra Region has benefited from the involvement of NIH scientists. • The steps have been taken for strengthening of Ground water Monitoring Network by establishing network of 2154 piezometers in entire state , but there is still need for data quality improvement Programme and implementation of Real Time Monitoring Systems.
VERTICAL EXTENTION • II.B. Decision Support System – Planning (DSS-P) • II.C. Purpose Driven Studies (PDS)
II.B. Decision Support System – Planning (DSS-P) • Mahi Basin (Gujarat State Portion ) had been selected as State Pilot Basin. • The components of DSS - Planning are: • Conjunctive surface water & ground water planning. • Ground water management • Seasonal Planning for Ground Water • Artificial Recharge • Drought Management
Status of Modeling activities: • Applications developed using available tools. • The ground water planning application developed in Patadungri, Machhanala, Umaria & Limkheda catchment as a test case to Predict how to manage ground water supply. • Ground water Seasonal planning application is developed in Patadungri catchment as a test case to predict the how much groundwater is available at Pre monsoon based on the groundwater level at post monsoon. • Application on Artificial Recharge is developed in Machhanala catchment. The application is useful to know how groundwater depth would vary with and without the artificial recharge in climatic variation.
Status of Modeling activities Contd. • The Application on conjunctive use of surface and Ground water developed for Patadungri catchment to test the performance of the utilization of groundwater and canals in dry, average, and wet years and to predict how this affects the groundwater in the long run. • The interfaces provided by the DSS-P consultants, to populate results for following applications, are being evaluated for their suitability: • Conjunctive use • Artificial Recharge
II. C. Purpose Driven Studies Two Purpose Driven Studies have been taken up . • 1) Coastal Ground water dynamics and Management in the Saurashtra Region, in collaboration with NIH : To simulate transport of saltwater in coastal aquifer system numerically & study impact of existing aquifer management practices on gw regime • 2) Ground Water Management in Water Logged Area of Dharoi project command (RBC) project and Strategy to maintain Harmony on water levels of perched aquifer with deep Aquifer: To study the Geohydrology of perched and deeper aquifer systems & the possibility of recharge tube wells for inter-aquifer transmission of water
PDS-1 Coastal Ground water dynamics and Management in the Saurashtra Region, in collaboration with NIH Study Area , Coastal Saurashtra, Gujarat • GW occurs 1.25 m to 26 m bgl. • Depth of wells ranges from 4.8 to 40 m. • Main productive aquifer is Milliolitic Limestone which is highly overexploited for domestic & irrigation purpose. • Groundwater usage has affected the water table which in turn has disturbed the dynamics of coastal aquifer system. • GW Salinity • from sea in the coastal aquifer system due to lowering of water table. • through creeks during high tides. • deterioration of gw quality occurs due to increasing salinity • Activities carried out • Ground water level and quality Monitoring on 16 nos of newly constructed piezometers and Monitoring stations suggested by NIH. • Geophysical survey at 50 locations. • Aquifer Parameter Test at 12 locations
PDS-2 Ground Water Management in Water Logged Area of Dharoi project command (RBC) Pakistan Rajsthan PDS Area • Problems/Issues that prompted to take up the PDS • Due to presence of shallow clay layer & application of surface water by Dharoi canal distributaries for irrigation, the water levels in this area rise to problematic level. • Adverse effects noticed • The soil texture ruptured and enrichment of Soil Salinity • Diminishes the Agricultural products. • Leaching of water in deep cart tracks and nalas, de-active the sewerage pits. • Effect on environment & socio economy. Arabian Sea
Based on the Preliminary Investigation in 72 villages, the ground water level trend of monitoring stations located in perched aquifer/unconfined aquifer in the close vicinity of canal passing through the area, detailed investigation carried out in 32 villages. • Total 22 no of Ground Water monitoring networks are fixed to study its behavior in the area. • 13 pumping tests conducted to study the aquifer parameters. • Collected water level and soil analysis data from soil survey department to identify the area affected by soil salinity. • The change in land use pattern studied with help of Remote sensing data of 1998 & 2010. • Constructed 3 Nos. of Recharge Tube Wells 90 mts. Depth and 8 Nos. of Piezometers ( 4 Nos. of Shallow Piezometers -20 mts. Depth and 4 Nos. of Deep Piezometers - 90 mts.) • The data has been analyzed using Visual Modflow software and the results have been obtained regarding the extent of water logging in different seasons, the groundwater movement, and the inflow and out flow, the mass and zonal balance for different aquifers and seasons. • The consultancy work has been entrusted to CEPT university. • The Final Draft Report is on completion stage by CEPT University and will be submitted to TAMC/PCS within two days for approval.
Constructed 3 Nos. of Recharge Tube Wells 90 mts. Depth and • 8 Nos. of Piezometers ( 4 Nos. of Shallow Piezometers -20 mts. Depth and 4 Nos. of Deep Piezometers - 90 mts.) In Malekpur Village ,Taluka – Vadnagar ,District Mahesana
Continuation of Awareness Programme from State Fund • Ground Water Resources Estimation, • Aquifer Mapping Study • Planning of new exploratory tubewell programme implemented in Tribal Areas of Gujarat. • Artificial GW Recharge locations findings and Defining Area improved through Recharge structures. • Defining Saline areas for ground water Assessment