The Sigmaplan:policy-integration and stakeholder management 1/07/2014 ir. Maarten Jans commissioned by ir. Wim Dauwe Waterways and Sea Canal (W&Z) Sea Scheldt Department
NWRM – workshop 1.07.2014Agenda Waterways & Sea Canal the Sigmaplan Introduction Policy-integration and preparation Safety, Nature and Economic growth for Flanders Stakeholder management Participation and public support
NWRM – workshop 1.07.2014Agenda Waterways & Sea Canal the Sigmaplan Introduction Policy-integrationandpreparation Safety, Nature andEconomicgrowthforFlanders Stakeholder management Participationand public support
Waterways & Sea Canal Flemish Government agency (Belgium) • Stimulate multifunctional use of the waterways • Ensure safety and manage flood risk (Sigmaplan) • Manage living on and around the waterway • Stimulate recreation, tourism and nature experiences • Enhance the link between water & city
NWRM – workshop 1.07.2014Agenda Waterways & Sea Canal the Sigmaplan Introduction Policy-integrationandpreparation Safety, Nature andEconomicgrowthforFlanders Stakeholder management Participationand public support
the Sigmaplan Why?
the Sigmaplan Why? Baasrode Wintam Wintam Antwerpen
the Sigmaplan What? • Sigmaplan 1976 • Higherandstrongerdikes: 512 km • 13 Flood Control Areas • TidalBarrier
the Sigmaplan What? • Sigmaplan 1976 • Higherandstrongerdikes: 512 km • 13 Flood Control Areas • TidalBarrier
the Sigmaplan What? • Sigmaplan 1976 • Higherandstrongerdikes: 512 km • 13 Flood Control Areas • TidalBarrier
the Sigmaplan What? • Sigmaplan 1976 • Higherandstrongerdikes: 512 km • 13 Flood Control Areas • TidalBarrier
NWRM – workshop 1.07.2014Agenda Waterways & Sea Canal the Sigmaplan Introduction Policy-integrationandpreparation Safety, Nature andEconomicgrowthforFlanders Stakeholder management Participationand public support
Policy integration and preparation Safety, Nature and Economic growth for Flanders • Updated Sigmaplan dd. 2005, necessity: • Endangered Aquatic and marine fauna and flora (natura 2000 – habitat directive) • Reassessment of flood risk (climate change – spatial planning) • Economic value of the river Scheldt
Policy integration and preparation Safety, Nature and Economic growth for Flanders project areas of the Sigma Plan • 1976 (start) – 2005 (actualisation) – 2030 (completion) • 500+ kilometers riverdykes • 5,000 hectares flood control andnatureareas
NWRM – workshop 1.07.2014Agenda Waterways & Sea Canal the Sigmaplan Introduction Policy-integrationandpreparation Safety, Nature andEconomicgrowthforFlanders Stakeholder management Participationand public support
Multiple goals, several win-win’s, many stakeholders Optimizing Safety: waterway managers, localresidents, … Developingnaturalquality: environmentalorganisations, … Economy: port companies, farmers, boatmen… Recreation : cyclists, hikers, canoeists, pleasurecraft operators Overal: resident, localmunicipalities (politicians) Difficultchoicesneedtobe madeRoom for the river = lessspaceforhumans needtoexpropriate or purchasesoils anddevelopcompensationmeasures Stakeholder managementStakeholders
Stakeholder managementDifferent levels • Program level • Planning Phase • Implementation Phase • Project level • Planning Phase • Construction Phase
Stakeholder managementDifferent levels • Program level • Planning Phase • Implementation Phase • Project level • Planning Phase • Construction Phase
comprehensive studies Stakeholder managementplanning phase DAMAGE AND VICTIME MODEL Damage (€) per return period for 2000 and 2100 for everymunicipality HYDROLOGICAL MODEL Flooding simulations per return period for 2000 and 2100 SELECTION OF MEASURES COSTS-BENEFITS MODEL Floodingrisks, profitability, pay-back time ADDITIONAL EFFECTS Agriculture, View of neighbours, Nature CALCULATING COSTS MODEL Estimation investmentcosts and maintenance costs
Intensive consultationbefore en duringdecision making governmentdepartments civil society organisations Agricultural Nature (recreation) Politicians … Last phase: via environmental assessment report Localmunicipalities, residents Resulted in optimalisations of the plan + support on program level (= macro) Stakeholder managementplanning phase
Stakeholder managementDifferent levels • Program level • Planning Phase • Implementation Phase • Project level • Planning Phase • Construction Phase
Stakeholder managementDifferent levels • Program level • Planning Phase • Implementation Phase • Project level • Planning Phase • Construction Phase
Stakeholder managementProgram Level - ImplementaionPhase Sounding Board Committee (social feedback) SteeringCommittee (strategicchoices - policy feedback)
Stakeholder managementProgram Level - ImplementaionPhase Thematical committees Sounding Board Committee (social feedback) SteeringCommittee (strategicchoices - policy feedback) Nature - landscape Supportingagricultural policy Technical infrastructure recreation safety
Stakeholder managementDifferent levels • Program level • Planning Phase • Implementation Phase • Project level • Planning Phase • Construction Phase
Stakeholder managementProject Level – Planning Phase FRAMEWORK( SIGMA PLAN 2005 ) Project target: 850 ha wetlandssearch area : 1,300 ha timing : start constructionby 2015 Project development process STAKEHOLDERS regionalandlocalauthorities sectoral interest groups 30,000 directlyinvolvedresidents TECHNICAL STUDIES Agriculture Impact Assessement Surfaceandground water model Ecological niche model PROCEDURES Environmental Impact AssesmentRegionalSpationImplementation PlanApplyingfor permits RESULT land use plan safety – ecologyecological management plan recreationandtourism plan CONSTRUCTION Starting 2015 andonwards
Stakeholder managementProject Level – Planning & ImplementationPhase Communication Management: Project Committee (localauthorities, incl. politicians) … Nature - landscape Supportingagricultural policy recreation Thematical committees
Stakeholder managementDifferent levels • Program level • Planning Phase • Implementation Phase • Project level • Planning Phase • Construction Phase
Firm basis extensivemultidisciplinary system studies legal policy decision Uniform process lay-out preparation consultation formal procedures realisation Main goal Safety & Nature in Scheldt estuary robustandself-sustainingecosystem Withminimalsocial impact & maximalsocial support Conclusionkeyelements
The Sigmaplan:policy-integration and stakeholder management 1/07/2014 ir. Maarten Jans commissioned by ir. Wim Dauwe Waterways and Sea Canal (W&Z) Sea Scheldt Department
Policy integration and preparationmore sustainable approach Deeperinsight in the estuary’smanyfunctions Integral water management Respect the variousfunctions of the water system; Avoidnegativeconsequencesfor the environment; Seekaddedvalueandsynergies ROOM FOR THE RIVER APPROACH Movingdykeslandward (de-poldering) More complex ‘controlledreducestides’ (GGG) New riverareas (new alignment of the embankment)
Policy integration and preparation Safety, Nature and Economic growth for Flanders • PAST • Decisionsbased on high water levels; • Basic rule: water canbesuppressed; • taller, strongerdykes • flood control areas • 2005 • Decisionsbased on potentialdamage (costs –benefits); • ‘Floods are also part of the Scheldt’; • Safety vision: Betterprotectionbygiving the river more room tobreathe