1 / 59

Erosion and Sediment Control General Permit (ESCGP-1)

This document provides an overview of the Erosion and Sediment Control General Permit (ESCGP-1), including background information, permit options, and the application process. It also outlines the requirements for earth disturbance activities associated with oil and gas development.

bweber
Download Presentation

Erosion and Sediment Control General Permit (ESCGP-1)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Erosion and Sediment Control General Permit (ESCGP-1) Christopher Tersine, Environmental Engineer Division of Resource Management & Well Development Department of Environmental Protection Rachel Carson State Office Building 400 Market Street | Harrisburg, PA 17101 Phone: 717.772.2199 | Fax: 717.772.2291 www.depweb.state.pa.us

  2. Erosion and Sediment Control General Permit (ESCGP-1) • ESCGP-1 Background • ESCGP-1 Options • ESCGP-1 NOI and Checklist

  3. ESCGP-1 Authority • TheClean Streams Law (35 P. S. §§ 691.1--691.1001), • The Oil and Gas Act (58 P. S. §§ 601.101--601.605 • Sections 1905-A, 1917-A and 1920-A of The Administrative Code of 1929 (71 P. S. §§ 510-5, 510-17 and 510-20)

  4. ESCGP-1 Background • The ESCGP-1 follows the Department’s plan for regulating erosion and sediment control and stormwater management at oil and gas exploration. Continue Enforcement of Chapter 102 • Production • Processing Treatment operations or transmission facilities (oil and gas activities)

  5. ESCGP-1 Requirements • All earth disturbance activities associated with oil and gas development that totals earth disturbance equals or exceeds 5 acres at one time or over the life of the project • (Greater 5000 square feet = E/S plan) • Including substantially connected earth disturbance • (Ex. Centralized impoundment, associated access roads, all well sites serviced by that impoundment, pipelines and other support activities) • Earth disturbance cannot be piecemealed • to avoid obtaining a permit

  6. ESCGP-1 General Requirements - Earth disturbance activities cannot begin until you receive the permit authorization. - Always use the most up-to-date NOI authorization package available.

  7. ESCGP-1 Permitting Guidelines • All projects at the very least project includes construction of the well site and access roads. • All associated utility lines or support facilities that are substantially (functionally) connected to the well site or access road and constructed prior to achieving permanent restoration of the well site and access road must be included as part of the project.

  8. Multiple Wells Sites ESCGP-1 Requirements • If multiple well sites are constructed with a common access road the project includes: -The well sites • -Access road • -Pipelines • -Any associated utility lines • -Support facilities for each of the well sites that are substantially connected to any of the well sites or access roads and are constructed prior to achieving permanent restoration and permanent stabilization of the well site

  9. ESCGP-1 • Two Options: • Standard ESCGP-1 • Expedited ESCGP-1

  10. Administrative Review (Checklist) Expedited ESCGP-1 Submit an ESCGP -1 Notice of Intent (NOI) at least 14 business days prior to any earth disturbance A sealed by a Licensed Professional (Engineer, Geologist,, Surveyor) • Approval notice –written authorization within 14 business days (Fax, Email, followed up with hard copy. (Dept.) • Expedited Approach is not mandatory • Earth disturbance activities cannot begin until you receive the permit authorization • PA Bulletin Final Action Notice (Dept.)

  11. Standard ESCGP-1 NOI Application -Submit a standard ESCGP-1 NOI application at least 60 days prior to earth disturbance - NOI Review & Approval issued - PA Bulletin Final Action Notice

  12. Where do you apply for an ESCGP-1? Applications: • Requests for coverage should be submitted to the regional DEP Oil and Gas Program Office. • DEP regional O&G program offices will process all Oil & Gas related erosion, sediment and stormwater permit applications except those related to transmission lines and facilities (inter and intra state pipelines).

  13. ESCGP-1’s for Transmission Lines and Associated Facilities • Delegated Conservation Districts will process these permits • (Chapter 102 permit review responsibilities) • Non- Delegated Counties – DEP Regional Office • Watershed Management Program • There is no Expedited process for these permits Definition of Transmission Line:

  14. Transmission Line Definition: Transmission lines (inter and intra state) include compressor stations, gas processing facilities and all other pipelines and facilities downstream of the production and gathering line system

  15. Delegated Responsibilities • Delegated conservation districts will be responsible for inspection and complaint response for all transmission facility earth disturbances. For non-delegated counties the appropriate regional DEP Watershed Management program shall have program responsibility

  16. Non-Delegated Counties • Oil and Gas Exploration, Production, Processing • and Treatment Projects • Bureau of Oil & Gas Management • Regional Office (SWRO, NWRO or NCRO) Transmission Line Projects Appropriate Bureau of Watershed Management DEP Regional Office

  17. The ESCGP-1 Notice of Intent (NOI) Application Get it right the first time if you don’t waste time and risk the chance of have in it returned and lose your$$$$$!

  18. The Total Project Area Entire area of activity, development or sale including, the area of an earth disturbance activity, the area planned for an earth disturbance activity and other areas which are not subject to an earth disturbance activity. Enter the size of the area in acres to the nearest tenth of an acre. (this could be the leased area)

  19. Disturbed Area - Total Disturbed Area is that portion of the total project area where earth disturbance activities are planned to occur over the life of the project. - For phased projects, this refers to the disturbed area of the initial project phase plus the planned disturbed areas of subsequent project phases. - Enter the size of the area in acres to the nearest tenth of an acre.

  20. Provide the name by which this proposed earth disturbance activity or project is, or will be, known. Check all boxes that best describe the general type of activity. In the description, provide details such as number of wells to be drilled. Does the include everything? How about compressor stations, pipelines, borrow pits etc.?

  21. Provide the latitude and longitude coordinates for the approximate center of the project area or facility Locate the project area on an 8 ½" x 11" photocopy of the U.S.G.S. topo map area. If the project is to be phased, provide an estimate of the timetable for the major phases. For each major phase, provide a description of the activity undertaken during the phase, total area of the phase, the disturbed area of the phase and the start and end dates for each phase of the activity. 7.List the existing and previous land use. If the stormwater discharge contains a pollutant other than sediment, list the pollutant, the source of the pollutant and concentration. Provide a plan for removal of the pollutant.

  22. Phased ESCGP-1 Permits • Applicants continue to have the option to utilize a “phased permit” approach. • Use the DEP Policy on Phased NPDES Stormwater Discharges Associated with Construction Activity Permits, Chapter 102 Erosion and Sediment Control Permits and Chapter 105 Waterway Restoration Permits, DEP No. 363‑2134-013. This policy is available on e-Library.

  23. Phased Projects • Operator may wish to develop the project over time or in phases. If an operator plans to develop the entire or part of the lease or mineral estate over time, but the well spacing or location cannot be determined until some wells are drilled, an ESCGP-1 may be obtained for the entire area with approval of the first increment or phase. • Part of policy of the Department to ensure projects requiring DEP permits are reviewed as complete projects and meet all public health, safety and environmental requirements. Including any part or a phased project.

  24. Phased Projects • For coverage by ESCGP-1 for phased projects an applicant must submit the following: • For the entire project area • A completed notice of intent (NOI) for ESCGP-1 • An application must be accompanies by a check with the appropriate permit application fee. The application should be calculated based on the total disturbed acreage of the entire project. • Municipal notifications to all county(ies) and municipality(ies) and proof of receipt. • Complete PNDI form and search receipt(s) for all phases of the project site. • An erosion and sediment control plan (E & S Plan) and Site Restoration Plan containing the following information: • The existing topographic features for the project site and immediate surrounding area. • The types, depth, slope, locations and limitations of the soils. • A narrative description and plan drawings showing the locations and the characteristics of the earth disturbance activity including past, present and proposed land uses and a description of the planned physical alterations, earth disturbances and other construction activities, as well as a general description and location of anticipated BMPs, including BMPs for special protection waters.

  25. Phased Projects • For coverage by ESCGP-1 for phased projects an applicant must submit the following: • The location of all surface waters, which may receive runoff within or from the project site and their classification pursuant to Chapter 93. • Procedures to ensure the proper handling, storage, control, disposal and recycling of wastes or other materials that have potential to cause pollution. • A narrative description and a map (USGS topographic quadrangle or equivalent) of the project area that identifies the location and characteristics of sensitive areas or areas of environmental concern for the project site. • Sensitive areas or areas of environmental concern include but are not limited to: wetlands, • special protection waters, • historic or cultural resource areas and areas where threatened • endangered special or critical habitat may be present

  26. Phased Projects • For the initial phase (and each subsequent phase) of the project: • A detailed description identifying the specific BMPs that will be used, plan details, drawings, specifications and a sequence of BMP installation • The amount of projected runoff and supporting calculations for each BMP. • E&S plan drawings identifying the location and boundaries of the phase, the locations of BMPs that will be used, construction details, specifications and a legend. Typical sketches may be used but must provide sufficient detail to illustrate critical dimensions and construction requirements. • Maintenance program including the inspection of BMPs on a weekly basis and after each measurable rainfall event and the type of maintenance required for each BMP to ensure effectiveness. • A site restoration plan that meets the following requirements of 25 Pa Code §102.8, subsections (b), (c), (e), (f), (h), (i), (l) and when applicable (m) • Phased Projects and Conceptual Future Activities can not be used to circumvent the five acre threshold of earth disturbance.

  27. Next named stream downstream There may be more than one Enter the Name of the Corporation, Partnership, Agency or Individual and all other required information.

  28. Permittees and Co-permittees • All operators that are not permittees must be included as co-permittees on the ESCGP-1 authorization. Operators include: • Any entity that has oversight responsibility of earth disturbance activity on a project site or a portion of the project site that has the ability to make modifications to the E&S plan restoration plan or site specifications • Or day-to-day operational control over earth disturbance activity on a project site or a portion of the project site to ensure compliance with the E&S plan or restoration plan

  29. Required for additional individuals, partners or operators to be co-permittee. Enter the Name of the Corporation, Partnership, Agency or Individual. Provide the name of the site at the specific physical location. Do not use abbreviations, acronyms, etc. Provide the physical address of the location where the permitted activities will occur. No PO Box Numbers will be accepted for site location information. Provide the city (or municipality), state, and the ZIP+4. When providing written directions, do not use PO Box address data. Include landmarks and approximate distances from the nearest highway. Indicate the county(ies) and municipality(ies) in which the site is located.

  30. The attached PCSM Plan must be a separate, distinct and complete plan. There could be cases where none of these are checked then E-3 must be filled out

  31. Attach three (3) copies of the PCSM Plan that includes a written narrative, identification and location of BMPs, plan drawings of BMPs, operation and maintenance procedures and supporting calculations and measurements

  32. Supporting calculations and measurements are not required if ALL the earth disturbance area within the project boundary is permanently revegetated or otherwise stabilized with pervious materials, the approximate original contours are maintained Post Construction Stormwater BMPs are used that use natural measures to eliminate pollution, do not require extensive construction efforts, promote pollutant reduction, and are capable of controlling the net increase in the volume and rate of stormwater runoff from a 2‑year/24 hour storm event and infiltrates the net increase of the post construction runoff

  33. If the proposed post construction stormwater BMPs will not infiltrate all the net increase in stormwater runoff volume, please explain how you plan to manage the increased stormwater runoff volume Please check the appropriate box and list the existing BMPs that will be used or expanded.

  34. The amount of impervious area on the project site as determined by the dominant land condition or land use for the five (5) years preceding the planned project. The amount of impervious area on the project site after the completion of the project. Remember dirt and gravel roads can be impervious Subtract pre from post

  35. The amount of stormwater that would runoff the project site during the design storm event as determined by the dominant land condition The amount of stormwater that would runoff from the project site after construction if the planned stormwater BMPs were not installed. Subtract pre from post

  36. The amount of stormwater that will run off from the project site after the planned stormwater BMPs are installed. Subtract post-construction volume with BMPs from pre-construction volume

  37. Show the stormwater runoff discharge rate for the design frequency storm event as determined by the dominant land condition Show the stormwater runoff discharge rate for the storm event after the planned stormwater BMPs are installed. Subtract pre from post

  38. Please check all the boxes that apply to the plan. If there is no check box for a planned BMP, check the box for “other” and list the BMP.

  39. Provide the information requested in accordance with 25 Pa Code Chapter 93.4(a), Chapter 102.4(b)(6), the Oil and Gas Operator’s Manual and the Oil and Gas Stormwater Policy 550-2100-008 if the earth disturbance activity is in a Special Protection Watershed.

  40. Provide the information requested. Use additional pages if necessary. The person responsible for preparing the Erosion and Sediment Control Plan and Post Construction Stormwater Management Plan must complete this section.

  41. Notice of Intent (NOI) ESCGP-1 Checklist NOTICE OF INTENT (NOI) ADMINISTRATIVE COMPLETENESS CHECKLISTEROSION AND SEDIMENT CONTROL GENERAL PERMIT FOR EARTH DISTURBANCE ASSOCIATED (ESCGP-1) WITH OIL AND GAS EXPLORATION, PRODUCTION, PROCESSING, OR TREATMENT OPERATIONS OR TRANSMISSION FACILITIES

  42. ESCGP-1 Checklist

  43. Is it in the narrative or on the drawings a D or N should be used What specific page is the item located

More Related