1 / 7

Earned Value

Earned Value. $$$. Measure of Project Performance Overall for All Activities Measured at Particular Point in Times. Earned Value. EV = (% Completed Work) (Planned Cost) E.G. EV = .75 x 100 = 75 EV Also Known as: Budgeted Cost of Work Performed to Date (BCWP). Computing Earned Value.

cain
Download Presentation

Earned Value

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Earned Value $$$

  2. Measure of Project Performance Overall for All Activities Measured at Particular Point in Times Earned Value

  3. EV = (% Completed Work) (Planned Cost) E.G. EV = .75 x 100 = 75 EV Also Known as: Budgeted Cost of Work Performed to Date (BCWP) Computing Earned Value

  4. Cost Variance (CV) = EV (BCWP) – Actual Cost of Work Performed (ACWP) E.G. CV = 75 – 100 = -25 (Over Budget) Schedule Variance (SV) = EV(BCWP) - Budget Cost of Work Scheduled (BCWS) E.G. SV = 75 – 125 = -50 (Costs behind Schedule) Time Variance (TV) = Scheduled Time Work Performed (STWP) – Actual Time Work Performed (ATWP) E.G. TV = 20 – 25 = -5 (Behind Schedule) Using Earned Value

  5. EV = (% Completed) (Planned Cost) EV = (Actual Progress/Scheduled Progress) (100) CR = (Actual Progress/Scheduled Progress) (Budget Cost/Actual Cost) CR = (EV/100) (100/Actual Cost) CR = EV/Actual Cost Example: Problem 3.8

  6. Day A:EV A:Cost A: CR 1 90 95 .947 2 92 98 .939 3 94 101 .931 4 98 106 .925 5 104 116 .897 6 112 126 .889 CR for A: Over 6 Days

  7. Day B:EV B:Cost B: CR 1 90 95 .947 2 88 94 .936 3 95 102 .931 4 101 109 .927 5 89 99 .899 6 105 118 .890 CR for B: Over 6 Days

More Related