An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Pacific Aviation Directors Workshop“Aviation Safety & Sustainability in the Pacific – Environment, Energy and Economic Viability”International Conference CenterMajuro Atoll, RMIMay 4 – 6, 2009 Majuro Airport Presentation Presented by: Jack S. Chong-Gum

  2. Presentation Outline • Majuro AIP Projects Overview: • Apron Rehabilitation • ARFF/SAWRS Building • Airport Master Plan • Airport Road Realignment/RSA Improvement • Proposed Airport Improvement Projects

  3. No Taxiway shoulders Obstructions penetrating the FAR 77 transitional surfaces Poor apron drainage Poor security fencing Apron congestion Substandard illumination No control/ protection against jet blast Generation of FOD One Fuel Hydrant Limited paint markings Apron Rehabilitation Project

  4. Apron Congestion • Add photo of apron congestion here

  5. Three jet capable gates

  6. Asphalt overlay and concrete hardstands

  7. Minimise obstruction

  8. Apron floodlighting

  9. Majuro Atoll Lagoon Improving apron drainage Three jet capable gates Pacific Ocean

  10. Additional fuel hydrants

  11. Blast/Security fence Backup power supply Signage and paint markings

  12. Photo of current apron look

  13. ARFF/SAWRS Building Project • Bid opening May 7, 2007 • Contract awarded on December 19, 2007 • NTP issued on March 3, 2009 • Contract completion date is November 3, 2009 • Overall completion approx. 45%

  14. N

  15. Airport Master Plan • SOW entails traditional AMP elements, plus: • Airport Certification Manual • Wildlife Hazard Assessment and Management Plan • Pavement Maintenance Management Plan • Airport Maintenance Plan for facilities and equipment • Updated Airport Layout Plan • Updated Obstruction Charts • Financial feasibility analysis • NPIAS Criteria Study for outer island airports • Planning contract under review/execution process

  16. Public Road • Picnic Area: • Public Safety • Jet Blast Poor Security Fence No RSA Airport Road Realignment / RSA Improvement Project

  17. Proposed Airport Projects • Additional Runway Safety Area Improvements

  18. Proposed Airport Projects • Security Perimeter Fencing Upgrade

  19. Proposed Airport Projects • Aircraft Water Rescue Implementation Plan • Signage and Wind Cone Upgrade • 0.5 million-gallon Capacity Tank for Fire Suppression and Potable Water Storage • Relocation of NDB/DME facility and antennae towers • Shoreline Protection Upgrade • Runway Extension • New Terminal Building / Terminal Building Improvement