An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. July 15, 2013 All Experimenters’Meeting Photo by Greg Vogel

  2. Shutdown 2012 - 2013 Machine Status: • Proton Source Commissioning and Studies • RFQ Injector Line (RIL) • Linac • Booster • Main Injector • Tunnel work on Saturday • Power Supply studies on weekends TeV & Muon Rings – Partially available for tours with approval and appropriate training

  3. MSS Bypass Project

  4. MSS Bypass Project – Impact Areas • Project Completion Date • July 16th (Adding on additional PS3 work) • Main Ring Road Closure and Power Outages • Main Ring Road reduction at A1 (Restriction lifted on 7/16/13) • Power off to A1, A2, & A3 (Last power outage will be 7/15/13) • PS3 Power Outage • July 17th from 0800 – 1630 • Work in manhole to prepare for further work about 1.5 weeks away.

  5. Kautz Road SubStation • Status • MI backfed from Master SubStation • Using Feeder 45 for MI conventional power which is normally T85 on KRS • We ordered 6+ new surge arrestors (4.7k each) from Hubbell and wait for delivery in ~1 week • Schedule a ~1 day KRS outage (not really an outage, we can’t run power supplies) to replace all surge arrestors on transformers T85 & T87 • There will be a 20 minute outage to remove the backfeed after the surge arrestors are installed

  6. MI Startup Activities (~1 Week) • Turn on power supplies and establish ramps • Establish 8 Gevbeam • Match MI8 line lattice with IPM • Tune abort line @8 Gev • Establish 120 Gevbeam • Smooth orbits up the ramp • Tune abort line @ 120 Gev • High field Orbit smoothing (quad moves)  • Requires tunnel access (2x8 hrs) • Calibrate tune table • MI8 line lattice matching • Dedicated beam study • Extraction line tune up (NuMI) • Tune up for operation • Deliver low intensity beam to NuMI beam line for target scans • Estimated to take an additional week after MI is tuned up for operations

  7. Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.html