Case History : Florin County Water District, Sacramento, California. This project was driven by a need to replace a WWII-vintage, tar coated, steel water line . In total, the project will use 400 feet of 8-inch and 1200 feet of 6-inch DR18, C900 pipe.
E N D
Case History:Florin County Water District, Sacramento, California • This project was driven by a need to replace a WWII-vintage, tar coated, steel water line • In total, the project will use 400 feet of 8-inch and 1200 feet of 6-inch DR18, C900 pipe.
Case History:Florin County Water District, Sacramento, California • Assembling the Bulldog joint is the same as assembling a conventional PVC gasketed joint. In this project, a pry bar was used to lever together the joints. • Note, it is recommended that a wooden block be placed between the bar and the pipe’s bell.
Case History:Florin County Water District, Sacramento, California • Florin pressure tests the pipe installed that day at the end of the day. • Bulldog Restraint System offered a simple means of providing joint restraint to facilitate this daily pressure test.