1 / 26

ELC 347 project management

ELC 347 project management. Week 11. Agenda. Integrative Project 3rd part Graded 4 th part due next week Outline of deliverables (posted in WebCT) Quiz 2 is Due Today we will discuss Project Scheduling: Lagging, Crashing and Activity Networks.

cameo
Download Presentation

ELC 347 project management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ELC 347 project management Week 11

  2. Agenda • Integrative Project • 3rd part Graded • 4th part due next week • Outline of deliverables (posted in WebCT) • Quiz 2 is Due • Today we will discuss Project Scheduling: Lagging, Crashing and Activity Networks

  3. Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 © 2007 Pearson Education

  4. Lags in Precedence Relationships The logical relationship between the start and finish of one activity and the start and finish of another activity. Four logical relationships between tasks • Finish to Start • Finish to Finish • Start to Start • Start to Finish

  5. 0 A 6 Spec Design 6 6 B 11 Design Check 5 15 C 22 Blueprinting 7 Lag 4 Finish to Start Lag • Most common type of sequencing • Shown on the line joining the modes • Added during forward pass • Subtracted during backward pass This lag is not the same as activity slack

  6. 15 D 21 Wiring 6 21 C 22 Inspection 1 10 A 16 Plumbing 6 16 B 21 HVAC 5 Finish to Finish Lag Two activities share a similar completion point • The mechanical inspection cannot happen until wiring, plumbing, and HVAC installation are complete

  7. 30 D 36 Wiring 6 Lag 3 36 C 37 Inspection 1 33 B 36 HVAC 5 31 A 33 Plumbing 6 Start to Start Lag • Logic must be maintained by both forward and backward pass

  8. Lag 3 Start to Finish Lag • Least common type of lag relationship • Successor’s finish dependent on predecessor’s start 30 D 36 Wiring 6 33 C 34 Inspection 1 28 B 33 HVAC 5 22 A 28 Plumbing 6 fssf.mpp

  9. Gantt Charts • Establish a time-phased network • Can be used as a tracking tool Benefits of Gantt charts • Easy to create and comprehend • Identify the schedule baseline network • Allow for updating and control • Identify resource needs

  10. Create a Gantt chart based on the activities listed in the table. gantt.mpp

  11. Gantt Chart With Resources in MS Project

  12. Crashing Projects Accelerating a project by committing more resources than initially planned Principal methods for crashing • Improving existing resources’ productivity • Changing work methods • Increasing the quantity of resources

  13. Managerial Considerations • Determine activity fixed and variable costs • The crash point is the fully expedited activity • Optimize time-cost tradeoffs • Shorten activities on the critical path • Cease crashing when • the target completion time is reached • the crash cost exceeds the penalty cost

  14. What is the lowest cost to complete this project in 53 weeks? Times are in weeks and costs in dollars. crash.mpp, crash.xls

  15. Activity on Arrow Networks • Activities represented by arrows • Widely used in construction • Event nodes easy to flag • Forward and backward pass logic similar to AON • Two activities may not begin and end at common nodes • Dummy activities may be required

  16. Wrong Wrong

  17. AOA Network

  18. Forward Pass

  19. Backwards pass

  20. Use AOA to sketch the network that represents the project as described in the table. • Calculate early and late start and finish times for all activities.

  21. Controversies in the Use of Networks • Networks can be too complex • Poor network construction creates problems • Networks may be used inappropriately • When employing subcontractors • The master network must be available to them • All sub-networks must use common methods • Positive bias exists in PERT networks

More Related