Filling Pond Control Minimizing Water loss on Scipio River. (Comparison between PI Controller and Fractional Order Controllers). By Nicolas MONEGIER DU SORBIER. Outline. 1.Introduction 2.System Specifications 3.System Modeling and Parameters Calculation
E N D
Filling Pond Control Minimizing Water loss on Scipio River (Comparison between PI Controller and Fractional Order Controllers) By Nicolas MONEGIER DU SORBIER
Outline • 1.Introduction • 2.System Specifications • 3.System Modeling and Parameters Calculation • 4.System Control & Simulations (PI, Piα,PIIα) • 5.Comparison : PI vs Piα vsPIIα Controllers • 6.Conclusion
1. Introduction • The aim of this project was to control the filling of each pond of the Scipio Open Channel in the right time, minimizing the water loss at the end of the canal. • The most difficult was that only a positive action was available on the system. • Many controllers were tested in this project to find the best one.
2. System Specification Sensors and actuators can be used just one time each hour. Gate height, Diversion water level and Pond water Level are available for each Pond. Gate height, Water level and Outflow are available for the Reservoir.
Diversion Flow Calculation • For each diversion gate, the flow was calculated using the derivative of the pond volume variations. • Thus, the points related to the gate height, the diversion pond height and the flow were plotted. • Seeing these plots, so many points had very low flows for many values of gate heights and diversion pond heights. That is why a Look-up Table, based on 5 values of diversion pond heights and 5 values of gate heights, was made for the model. • So for each cell of the Look-up Table, the average was taken in the neighborhood of the point.
Time Delay Calculation • To Calculate the Time Delay between the reservoir and each diversion, the Rootcanal software was used: http://www.neng.usu.edu/bie/faculty/merkley/BIE6300.htm • Through Google Earth the topographic datas of the Scipio channel were obtained to model it on this software (elevations, distances) • Thus, 3 Look-Up Tables were made to calculate the delay relative to the Reservoir outflow for each part of the canal. • So each part of the canal was represented by a delay : y (t)= u (t-τ)
Delay Modeling For each part of the canal, Delays were modeled like this : But for parts between diversions and Ponds, Delays were modeled by constant delays. Johnnie’s Pond Delay=0.2 hours, Tom’s Pond Delay=0.2 hours City’s Pond Delay=0.1 hours and Cemetary’s Pond Delay=0.5 hours
Pond Volume Calculation Where q (t) is the flow and C the initial Pond Volume
Reservoir (PI) For PI Global error=156830 m 3 and Water loss = 8158 m3
Reservoir in Use (PI) For PI Global error=168450 m 3 and Water loss =7868 m3
Reservoir (PIα) For α = 0.3 Global error=156950 m 3 and Water loss = 8066 m3 For α = 0.6 Global error=157320 m 3 and Water loss = 8026 m3 For α = 0.8 Global error=164330 m 3 and Water loss = 7447 m3
Reservoir in Use (PIα) For α = 0.3 Global error=161750 m 3 and Water loss = 7912 m3 For α = 0.6 Global error=163620 m 3 and Water loss = 7176 m3 For α = 0.8 Global error=168010 m 3 and Water loss = 7745 m3
Reservoir (PIIα) For α = 0.3 Global error=155680 m 3 and Water loss = 7369 m3 For α = 0.7 Global error=158170 m 3 and Water loss = 8118 m3