An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. General Co-ordination ScheduleUpdate on 16een October 2007 K. Foraz TS-IC-PL

  2. Changes wks.37-41 K. Foraz TS-IC-PL

  3. Maintenance works and helium • Maintenance works – defined • Helium delivery • Discussed within AT • Schedule compatible with foreseen contracts (2008) for helium delivery K. Foraz TS-IC-PL

  4. K. Foraz TS-IC-PL 1/2/2020 Upated General schedule – wk 42 Mar. Mar. 10 10 11 11 12 12 12 13 13 23 34 45 56 67 78 81 Apr. Apr. 14 14 15 15 16 16 17 17 May May 18 18 19 19 20 20 21 21 Jun. Jun. 22 22 23 23 24 24 25 25 26 26 Jul. Jul. 27 27 28 28 29 29 30 30 Aug. Aug. 31 31 32 32 33 33 34 34 Sep. Sep. 35 35 36 36 2007 2007 37 37 38 38 39 39 Oct. Oct. 40 40 41 41 Consolidation 42 42 43 43 Nov. Nov. 44 44 45 45 46 46 47 47 48 48 49 49 Dec. Dec. 50 50 51 51 52 52 . Jan. Jan. 01 01 02 02 03 03 04 04 05 05 Feb. Feb. 06 06 07 07 08 08 09 09 Mar. Mar. 10 10 11 11 12 12 13 13 Apr. Apr. 14 14 15 15 16 16 17 17 18 18 May May 19 19 20 20 21 21 22 22 Jun. Jun. 23 23 Machine Checkout 24 24 25 25 26 26 Jul. Jul. 27 27 Beam Commissioning to 7 TeV 28 28 29 29 30 30 31 31 2008 2008 Aug. Aug. 32 32 33 33 34 34 35 35 Sep. Sep. 36 36 37 37 General schedule Baseline rev. 4.0 38 38 39 39 Oct. Oct. 40 40 41 41 42 42 Interconnection of the continuous cryostat Global pressure test &Consolidation Warm up 43 43 Global pressure test &Consolidation 44 44 Nov. Nov. 45 45 46 46 47 47 Leak tests of the last sub-sectors 48 48 Flushing Powering Tests Powering Tests Dec. Dec. 49 49 50 50 51 51 Inner Triplets repairs & interconnections 52 52 . Cool-down Cool-down CV maintenance

  5. Table of milestone– 08 October 2007