Status Report WP 4 26/27 February 2008
WP4.2 Common action plan • Establish tool box with common evaluation procedures & standards for • projects (joint call) • infrastructures • Common action: joint call
WP4.2 Tool box • Second iteration of procedures for the joint call (Deliverable D17 “White book”) • first iteration -> February 2007 workshop • 2nd WP4.2 workshop jointly with WP4.3 in The Hague 18 Sep. 2007 (organised by NWO) • discussion of call procedures, administrative structure, procedures for ranking list and funding proposal
Funding agencies FA 1 FA 2 FA n-1 FA n ……… Programme Board Joint Secretariat Evaluation Panel Administrative structure of Joint call
Administrative structure of Joint call • three bodies: • Programme Board: • representatives of FAs • supervises call • establishes funding recommendation • Joint Secretariat: handles call • Evaluation Panel: evaluates proposals
Common action plan: joint call national processing phase Formal national funding decision Start of funding Funding proposal Joint Call announcement Applicants‘ reply pre-announce. Referee reports Ranking Application deadline 1.10.08 1.02. 2008 1.11.08 15.04.08 1.01.09 1.07.08 1.08.08 8.01.2008 15.07.08 ASTRONET level National level
Selected theme • “Common tools for future large sub-mm facilities” • The projects should aim at activities linked to the future large sub-mm facilities in the areas: • Data evaluation infrastructure including data analysis and post processing tools • Numerical simulation and theoretical modelling • Provision of atomic, molecular and other physical parameters in a coherent way linked to the infrastructures, and via the development of dedicated database structures. • Theme aims at ALMA and HERSCHEL* *if supported by national FAs
Call participants • January 2008: • final decision by joint call partners • NWO, CNRS-INSU, BMBF/PT-DESY, VR, FWF, MEC • signed Implementation Agreement
Approved financial contributions (for 3 years) • CNRS-INSU: 500,000 € • BMBF: 900,000 € • MEC: 500,0001 € • NWO: 500,000 € • VR: 450,000 € • FWF: 300,000 € 1reduced on 2 Feb 2008 from originally committed 900M€
WP4.3 • Start 1 July 2007, Task leader NWO • Task: implementation of joint call