EA Renovation – Decabling campaign (EN-EL): Preparation

This update provides information on the status of cable identifications and the planning of the decabling campaign for the East Hall under construction. It highlights the progress made so far and the focus on the end-of-the-year work. It also mentions the coordination meeting and the areas covered by the campaign. Various numbers of cables needed for different areas are mentioned along with actions needed.

capetillo
Download Presentation

EA Renovation – Decabling campaign (EN-EL): Preparation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EA Renovation – Decabling campaign (EN-EL): Preparation East Hall under construction - 1962 E. Harrouch

  2. Index • Status of identifications • Planning of the decabling campaign • Focus on the end of the year work EAR Coordination meeting

  3. What has been done so far? • Cable identification during YETS 2017-2018 by all the groups (Detail available on SharePoint : Procedure, scope…), • Transmission of a general DEC to EN-EL-FC on the 15/03/2018 (Ticket) in time but not complete! Area covered by the decabling campaign CLOUD will be decabled depending on their need for operation No decabling campaign foreseen for the IRRAD/CHARM Facility EAR Coordination meeting

  4. Some numbers 22 cables needed for CLOUD RUN Will not be removed • BE-BI : 200 cables • BE-ICS : 40cables • BE-CO : 6 cables • IT-CS : 82 cables • HSE-RP : 4 Cables • EN-EL: 1138 cables • EN-CV : 60 cables Require more investigation Sure to be removed at the beginning of LS2 Action needed : Link to the files EAR Coordination meeting

  5. Planning of the decabling campaign First decabling phase EAR Coordination meeting

  6. Planning of the decabling campaign Second decabling phase EAR Coordination meeting

  7. Identification & Déconnexion des câbles • Require the complete labelling and disconnection of cables in b.157 and b.251 (Except the cables in b.352(PS), the primary area and (Of course) required for CLOUD RUN in 2019) EAR Coordination meeting Exemple : EBCR – Racks vacuum, collimateurs, BE-BI, BE-OP

  8. Identification & Déconnexion des câbles • Quand : Lundi 03/12 -> Jeudi 06/12 • Durée: 4 jours; • Qui: • Tout les groupes; • Quoi: Déconnecter tous les câbles candidats à la campagne de décablage EN-EL. • Conditions préalables: • Connaissance (et respect) de la procédure de décablage (EDMS 1889546); • Identification des câbles à enlever (Tenir à jour les listing); • Détection Incendie -> IS37, mise en arrêt définitif. Clim. Détectionincendie Prises AUL Eclairage + secours Racks Equipt. faisceaux

  9. Etape de consignation Automate (EBC26*EH) • Quand : Vendredi 07/12 • Durée: 1 jours; • Qui: • Tout les groupes; • Quoi: 3 type de consignation • Consignation des convertisseurs de puissance (B.263/B.251) par TE-EPC, • Consignation des réseaux électriques par EN-EL, • Consignation des racks par tous les groupes (Réglette, Canalis …) • Conditions préalables: • Respect de la procédure (En cours de rédaction!), • Listing des convertisseurs à consigner (A établir), • Listing des départ électrique à consigner(A établir), • Listing des racks à consigner(A établir). EOD26*EH Coffretalim. EBCR (EBD26*EH) B.251

  10. VIC > Début du décablage • Quand : Lundi 10 décembre 2018; • Durée: 3 semaines; • Qui: EN-EL + Tous les groupes; • Quoi: Réception de toutes les fiches de consignation; • Conditions préalables: • Equipements consignés, déconnecté & scotché (procédure);

  11. Summary • Complete identification before the beginning of the worksite (Mainly EN-EL, IT-CS, EN-CV, BE-BI), • (Until the beginning of November) Complete the lock-out procedure : • Provide the responsible of lock-outs (All Groups), • Issue the list of equipment to be locked-out (All Groups + EN-EA, EN-EL-OP, TE-EPC), • Circulate the lock-out procedure (Erwan), • Mon 03-12 -Thu 06-12 : Labelling + disconnection of all cables, • Fri 07-12 : Complete Lock-out (TE-EPC,EN-EL, All groups), • Mon 10-12 : VIC (EN-EL will collect all the fiche de consignations) + beginning of works, EAR Coordination meeting

  12. Thanks for your attention ! EAR Coordination meeting