Ideas about Tests and Sequencing 3rd March 2001 C .N .P .Gee Rutherford Appleton Laboratory
Testing Overview • There are many different tests, separate but overlapping. We need to start making a complete list. • When to do which test depends on when the hardware arrives. • Comments on Module vs. System tests. • Connectivity - are modules correctly and reliably linked • Algorithms - Analogue and Digital • Timing stability and margins • Cross-talk and low-rate error checks (Soak Tests) • Rate Limits • Alternate Operating Modes and Fault Detection/Recovery • System Stability and Behaviour.
Comments on Module vs System Tests • We will test: • individual modules as they are built; • then small groups of modules, leading to full PPr sub-system, full CP sub-system, and full JE sub-system • building up to the complete slice and perhaps ROIB and/or ROS. • Even with fully-tested modules, we need the capability to repeat module tests at will for groups of modules and complete slice. • The data-related TESTS and the TEST VECTORS need to be structured to fit together into a hierarchy. “Integrated test suite”. • We don’t know how to do this yet, but it could save a lot of time and effort.
Connectivity • This section verifies that all cables and links join correctly: • Generate bit patterns (e.g. a ramp) at the input to each backplane or cable link, check that correct data is received. • Rough timing needs to be done at the same time. • Links should be driven one at a time, so that swapped cables are quickly found. • Generate VME commands to each module in turn and verify (by eye) that the correct module is selected. • Check that individually addressed TTC commands are received where expected • Repeat for DCS commands.
Algorithms - Analogue • We rely on correct analogue processing. Test: • Analogue connectivity (separate problem from digital system). • Small, medium and large pulses (Saturation); • Range of pulse widths; • Ability to capture pulse regardless of analogue timing; • Automatic procedure to calibrate timing and BCID coefficients; • Automatic procedure for LUT set-up; • Proper operation of BCID; • Ability to handle out-of-spec pulse shapes. • Conformity of readout with applied analogue input (resolution).
Algorithms - Digital • Already tested by module engineers. • Testing adder trees (PPr towers, CPM hits, JEM energy and hits, CMMs) is easy, as described for CMM. • Testing adder trees with thresholds is more boring - you can’t see the sum, only the output from the thresholding stage. • Need to scan threshold value to determine adder content. • Must be done separately for each comparator where several are in parallel. • Test vectors must be able to specify required threshold settings.
Timing Margins and Stability • Measure the width of timing windows (by changing TTCrx delays on modules). Are they all similar and close to predictions? • LVDS data from PPr into CPMs and JEMs; • CPM/JEM backplane data into CMMs; • CMM - CMM and CMM - CTP cable links • Input links to RODs. • How sensitive are timings to temperature or crate supplies? • How closely aligned do PPrs, CPMs, JEMs, CMMs need to be? • Using external TTC clock, what are the upper/lower system frequencies?
Cross-talk and Soak Tests • Cross-talk is hopefully small, so combine with soak tests. • Excite signal lines singly, and look on physically adjacent lines for non-zero data. Long and Tedious!! • Short and Long Backplane links; • Connectors; • Cable links; • Between adjacent modules (e.g. through power supplies); • Digital - Analogue pickup. • Include some long tests to match previous LVDS link tests. • Include physics analogue data.
Rate Limits • Check that all parts of the trigger run up to the specified limits: • Able to sustain 100kHz L1A with no readout data loss; • Able to handle multiple close L1As (8 in 40 bunches, then pause); • Apply and check readout back-pressure operation; • Run RODs at data limits for different numbers of slices or compression options; • Check large number of non-zero channels (as in calibration run).
Alternate Operating Modes and Fault Detection • Can we run with BCID off for individual channels? • Can we simulate all error sources for checking? • Can we really run with links with errors or loss of link? • Are all error sources detected and counted so that they can be isolated. Can all be disabled? • How long does it take to start from cold, start a new run, etc.
System Stability and Behaviour • It must be possible to reconfigure the system easily (e.g. change cables). • Can the system (trigger plus supporting computers and software) run for long periods (e.g. weekends) reliably? • Is system start-up/shutdown and run start/stop repeatable? • Is there a routine timing set-up procedure, including setting up wrt the LHC bunch 0? • How does it behave if there are bad channels?