APPLYING RISK MANAGEMENT STRATEGIES PRUDENTLY Paper No 192 Presented At 2011 ICHS Conference September 13, 2001 By Michael Pero, P.E. – Director of Risk Management Hydrogen Safety, LLC & Douglas Rode, P.E. – Managing Director Hydrogen Safety, LLC
Agenda • The Total Cost of Risk • Commercialization Barriers • Risk Management Strategies • Conclusions
The Total Cost of Risk Technologies Environmental Markets Total Cost Of Risk Regulatory O & M Financial/Insurability Community • Design/Constriction/Testing
Project / Operation Risks RiskTimeline OPERATION TEST (OEM) CONSTRUCTION CONCEPT Financial Closure I/O CO - Warranty Decom- mission Design Higher Costs Delays Sourcing EPC Wrap Site Remediation Dynamic Test Reliability Test Repair/Redesign LDs Reputation Margins Tech Obsolescence. Environmental Competitiveness O&M Environmental Community Rel. Contracts Development Fuel Permitting Project Funds Purchase Agmts. Debt Service Cash Flow
Commercialization Barriers • Project Agreements with the Participants: • Adequacy of risk sharing between all participants • Limits of technical and commercial support by project owners and equipment suppliers • Track record for participants for success projects and ones that failed • Technology Design: • Too many innovations in one project - scale-up of size • Combined with integration complexity, unusual equipment designs, untested global sourcing • Lack of comfort level or familiarity with process, technology, long-term maintenance costs, external costs
Commercialization Barriers • Operating Risks: • Under-estimated up front capital costs and life-cycle costs • Margin or Uncertainty Risk (the fear of ‘Murphy’s Law’ – “What will go wrong, will”) • Country or Political Risk including such risks as inflation, unstable new environmental regulations (Carbon Tax), labor markets • Environmental Risks (whether from site pre-conditions or impacts during construction and operation) • Change-in-Law Risks, affecting the political or environmental risks
Basis For Effective Management Of Total Cost of Risk Quantifying Risks Pro-Active Actions (Comprehensive Avoid Scope) Retain Risks Transfer Prudent Business Decisions Based On Knowledge Of Maximum Exposures
Risk Management - Avoidance • Identify the risks • Quantify the risks • Technical hurdles • Commercial sensitivities • Mitigate the risks • Best industry practices • Safety training of ALL personnel • Hydrogen Safety Specialist professional • On-going Management Commitment
Risk Management - Retention Function of: • Financial Wherewithal • Deductibles • Resources to Manage Exposures • R&D Commitments • Corporate Strategies Mitigate the Risks
Risk Management – Transfer Problems with Traditional Outlets • Lack of Technical Understanding • Requires dedicated internal resources that can not be funded from current premiums earned • Very limited actuarial basis for loss history • “New” Industries Do Not Fit Existing Models • Minimum track record to base claims • High deductibles essentially self-insuring • Coverage exclusions • Excess high premiums • Fear of “blimps & bombs” • Few insurers doing “high risk” business • High rejection rate of applications by insurers
Case Study – Hospital as Site Questions Raised • Hospital’s current power needs? in 5 /10 years? • Hospital’s current need for waste heat? in 5 / 10 years? • Hospital’s current contracts for power & fuel and when do they expire? • Fuels available and pricing thresholds? • Hospital’s “green” position? • Value of land resources? • Internal resources available for project development? • How does the Energy Actions of the Hospital impact the Greater Community? • Hospital’s overall future expansion plans?
Case Study – Hospital as Site Findings • The hospital did not have any technology risk exposures, • The project risk exposures seemed to be financially mitigated • If the hospital wanted a share of the revenue from the sale of power to the local utility, then they would have to participate in the risk sharing currently being borne solely by the developer.
Conclusions • Both new and existing uses of hydrogen and hydrogen related technologies can benefit from an effective Risk Management Strategy. • The Strategy needs to address all the elements associated with the Total Cost of Risk model. • By mitigating risk exposures, the prospects of successful project significantly increase especially if they are identified and incorporated early in the design process.