Software SYSTEMS DEVELOPMENT. 4: System Design. Simplified view on software product development process. Project Lifecycle. Project Time Management. Activity Definition Activity Sequencing Activity Duration Estimation Schedule Development Schedule Control.
E N D
Software SYSTEMS DEVELOPMENT 4: System Design
Project Time Management • Activity Definition • Activity Sequencing • Activity Duration Estimation • Schedule Development • Schedule Control
Duration Estimation 3 points method • a= the best-case estimate • m = the most likely estimate • b = the worst-case estimate • E = (a + 4m + b) / 6
Schedule Control PV=BCWS - Budgeted Cost of Work Scheduled AC=ACWP - Actual Cost of Work Performed EV=BCWP - Budgeted Cost of Work Performed • In time units: • PV = Planned Work Time for Planned Work • AC = Time Actually Spent • EV = Planned Work Time for Work Done
Some Derived Metrics • SV: Schedule Variance (BCWP-BCWS) • A comparison of amount of work performed during a given period of time to what was scheduled to be performed. • A negative variance means the project is behind schedule • CV: Cost Variance (BCWP-ACWP) • A comparison of the budgeted cost of work performed with actual cost. • A negative variance means the project is over budget.
Some More Derived Metrics • SPI: Schedule Performance Index • SPI=BCWP/BCWS • SPI<1 means project is behind schedule • CPI: Cost Performance Index • CPI= BCWP/ACWP • CPI<1 means project is over budget • CSI: Cost Schedule Index (CSI=CPI x SPI) The further CSI is from 1.0, the less likely project recovery becomes.
SoW: Statement of Work • Deliverables: What will be delivered? • Brief description (source: SRS) • Activities: What should be done? • Brief Description (source: WBS) • Timeline: When it will be done (Milestones)? • Milestones Dates (source Gantt)
Assignment: Project Plan • Project Management Team vs. Development Team • Customer plays PM role • Jointly define the scope with development team • WBS • Stop when work package can be reliably estimated • Don’t forget non-coding activities (testing, bug fixing) • Gantt Chart • Milestones/Deliverables each week • Dependencies, time and resource allocation • SoW • 2 page brief • Project/Milestones scope
Weekly reports by PM team • Each week after the project kickoff • PM team: project status and metrics (10 minutes) • Development team: milestone demo (10 minutes) • Project Start Date: 23/05/2010 • Duration: 4 weeks • Reduce scope if needed.