Real Time Scheduling Terminologies define Fixed Priority Scheduler Ref: Real Time System Chapter 2 & 3
Jobs and Tasks • A jobis a unit of work that is scheduled and executed by a system • e.g. computation of a control-law, computation of an FFT on sensor data, • transmission of a data packet, retrieval of a file • A taskis a set of related jobs which jointly provide some function • e.g. the set of jobs that constitute the “maintain constant altitude” task, • keeping an airplane flying at a constant altitude . Your system should sample the temperature sensor reading every 1 ms.
Execution Time • A job Ji will execute for time ei • This is the amount of time required to complete the execution of Ji when it executes alone and has all the resources it needs • Value of ei depends upon complexity of the job and speed of the processor on which it is scheduled; may change for a variety of reasons: • Conditional branches • Cache memories and/or pipelines • Compression (e.g. MPEG video frames) • Execution times fall into an interval [ei−, ei +]; assume that we know this interval for every hard real-time job, but not necessarily the actual ei • Terminology: (x, y] is an interval starting immediately after x, continuing up to and including • Often, we can validate a system using ei+ for each job; we assume ei= ei+ and ignore the interval lower bound • Inefficient, but safe bound on execution time
Release and Response Time • Release time – the instant in time when a job becomes available for execution • May not be exact: Release time jitter so riis in the interval [ri−, ri+] • A job can be scheduled and executed at any time at, or after, its release time, provided its data and control dependency conditions are met • Response time – the length of time from the release time of the job to the time instant when it completes • Not the same as execution time, since may not execute continually
Deadline and Timing Constraint • Completion time – the instant at which a job completes execution • Relative deadline – the maximum allowable response time of a job • Absolute deadline – the instant of time by which a job is required to be completed (often called simply the deadline) • absolute deadline = release time + relative deadline • Feasible interval for a job Jiis the interval (ri, di) • Deadlines are examples of timing constraints
Example • A system to monitor and control a heating furnace • The system takes 20ms to initialize when turned on • After initialization, every 100 ms, the system: • Samples and reads the temperature sensor • Computes the control-law for the furnace to process temperature readings, determine the correct flow rates of fuel, air and coolant • Adjusts flow rates to match computed values • The periodic computations can be stated in terms of release times of the jobs computing the control-law: J0, J1, …, Jk, … • The release time of Jkis 20 + (k × 100) ms
Example • Suppose each job must complete before the release of the next job: • Jk’s relative deadline is 100 ms • Jk’s absolute deadline is 20 + ((k + 1) × 100) ms • Alternatively, each control-law computation may be required to finish sooner – i.e. the relative deadline is smaller than the time between jobs, allowing some slack time for other jobs
Hard vs Soft Real Time • Tardiness – how late a job completes relative to its deadline • lateness = completion time – absolute deadline • tardiness = max(0, lateness) • If a job must never miss its deadline, then the system is described as hard real-time • A timing constraint is hard if the failure to meet it is considered a fatal fault; this definition is based upon the functional criticality of a job • A timing constraint is hard if the usefulness of the results falls off abruptly (or may even go negative) at the deadline • A timing constraint is hard if the user requires validation (formal proof or exhaustive simulation) that the system always meets its timing constraint • Examples: Flight control; Railway signalling; Anti-lock brakes • If some deadlines can be missed occasionally, with acceptably low probability, then the system is described as soft real-time • This is a statistical constraint • Examples: Stock trading system ; DVD player ; Mobile phone
Hard vs Soft Real Time • Note: there may be no advantage in completing a job early • It is often better to keep jitter (variation in timing) in the response times of a stream of jobs small • Timing constraints can be expressed in many ways: • Deterministic • e.g. the relative deadline of every control-law computation is 50 ms; the response time of at most 1 out of 5 consecutive control-law computations exceeds 50ms • Probabilistic • e.g. the probability of the response time exceeding 50 ms is less than 0.2 • In terms of some usefulness function • e.g. the usefulness of every control-law computation is at least 0.8 [In practice, usually deterministic constraints, since easy to validate]
Modeling Periodic task • A set of jobs that are executed repeatedly at regular time intervals can be modelled as a periodic task • Each periodic task Tiis a sequence of jobs Ji,1, Ji,2, …, Ji,n • The phase of a task Tiis the release time ri ,1 of the first job Ji,1 in the task. It is denoted by ϕi (“phi”) • The period pi of a task Tiis the minimum length of all time intervals between release times of consecutive jobs • The execution time eiof a task Tiis the maximum execution time of all jobs in the periodic task • The period and execution time of every periodic task in the system are known with reasonable accuracy at all times • The hyper-period of a set of periodic tasks is the least common multiple of their periods: H = lcm(pi) for i = 1, 2, …, n • The time after which the pattern of job release/execution times starts to repeat
Modeling Periodic Task • The ratio ui= ei/ piis the utilization of task Ti • The fraction of time a periodic task with period pi and execution time ei keeps a processor busy • The total utilization of a system is the sum of the utilizations of all tasks in a system: U = Σui • We will usually assume the relative deadline for the jobs in a task is equal to the period of the task • It can sometimes be shorter than the period, to allow slack time < Many useful, real-world, systems fit this model; and it is easy to reason about such periodic tasks >
Responding to External Event • Many real-time systems are required to respond to external events • The jobs resulting from such events are sporadic or aperiodic jobs • A sporadic job has a hard deadlines • An aperiodic job has either a soft deadline or no deadline • The release time for sporadic or aperiodic jobs can be modelled as a random variable with some probability distribution, A(x) • A(x) gives the probability that the release time of the job is not later than x • Alternatively, if discussing a stream of similar sporadic/aperiodic jobs, A(x) can be viewed as the probability distribution of their inter-release times [Note: sometimes the terms arrival time (or inter-arrival time) are used instead of release time, due to their common use in queuing theory]
Modeling sporadic and areriodic task • A set of jobs that execute at irregular time intervals comprise a sporadic or aperiodic task • Each sporadic/aperiodic task is a stream of sporadic/aperiodic jobs • The inter-arrival times between consecutive jobs in such a task may vary widely according to probability distribution A(x) and can be arbitrarily small • Similarly, the execution times of jobs are identically distributed random variables with some probability distribution B(x) <Sporadic and aperiodic tasks occur in some real-time systems,and greatly complicate modelling and reasoning >
Approaches to Real-Time Scheduling • Different classes of scheduling algorithm used in real-time systems: • Clock-driven • Primarily used for hard real-time systems where all properties of all jobs are known at design time, such that offline scheduling techniques can be used • Weighted round-robin • Primarily used for scheduling real-time traffic in high-speed, switched networks • Priority-driven • Primarily used for more dynamic real-time systems with a mix of • time based and • event-based activities, • where the system must adapt to changing conditions and events .
Clock Driven Scheduling • Decisions about what jobs execute at what times are made at specific time instants • These instants are chosen before the system begins execution • Usually regularly spaced, implemented using a periodic timer interrupt • Scheduler awakes after each interrupt, schedules the job to execute for the next period, then blocks itself until the next interrupt • Typically in clock-driven systems: • All parameters of the real-time jobs are fixed and known • A schedule of the jobs is computed off-line and is stored for use at runtime; as a result, scheduling overhead at run-time can be minimized • Simple and straight-forward, not flexible
Round Robin Scheduling • Regular round-robin scheduling is commonly used for scheduling time-shared applications • Every job joins a FIFO queue when it is ready for execution • When the scheduler runs, it schedules the job at the head of the queue to execute for at most one time slice • Sometimes called a quantum – typically O(tens of ms) • If the job has not completed by the end of its quantum, it is preempted and placed at the end of the queue • When there are n ready jobs in the queue, each job gets one slice every n time slices (n time slices is called a round)
Priority-Driven Scheduling • Assign priorities to jobs, based on some algorithm • Make scheduling decisions based on the priorities, when events such as releases and job completions occur • Priority scheduling algorithms are event-driven • Jobs are placed in one or more queues; at each event, the ready job with the highest priority is executed • The assignment of jobs to priority queues, along with rules such a whether preemption is allowed, completely defines a priority scheduling algorithm • Priority-driven algorithms make locally optimal decisions about which job to run • Locally optimal scheduling decisions are often not globally optimal • Priority-driven algorithms never intentionally leave any resource idle • Leaving a resource idle is not locally optimal
Priority Driven Scheduling • Most scheduling algorithms used in non real-time systems are priority-driven • First-In-First-Out • Last-In-First-Out • Shortest-Execution-Time-First • Longest-Execution-Time-First • Real-time priority scheduling assigns priorities based on deadline or some other timing constraint: • Earliest deadline first • Least slack time first • Etc.
RATE Monotonic Algorithm (RM) • Assumptions • Fixed-priority algorithms • Rate monotonic • Deadline monotonic • Chapter 6 of Liu Book
Assumptions • Focus on well-known priority-driven algorithms for scheduling periodic tasks on a single processor • Assume a restricted periodic task model: • A fixed number of independent periodic tasks exist • Jobs comprising those tasks: • Are ready for execution as soon as they are released • Can be pre-empted at any time • Never suspend themselves • New tasks only admitted after an acceptance test; may be rejected • The period of a task defined as minimum inter-release time of jobs in task • There are no aperiodic or sporadic tasks • Scheduling decisions made immediately upon job release and completion • Algorithms are event driven, never intentionally leave a resource idle • Context switch overhead negligibly small; unlimited priority levels
Fixed- and Dynamic-Priority Algorithms • A priority-driven scheduler is an on-line scheduler • It does not pre-compute a schedule of tasks/jobs: instead assigns priorities to jobs when released, places them on a run queue in priority order • When pre-emption is allowed, a scheduling decision is made whenever a job is released or completed • At each scheduling decision time, the scheduler updates the run queues and executes the job at the head of the queue • Jobs in a task may be assigned the same priority (task level fixed priority) or different priorities (task level dynamic-priority) • The priority of each job is usually fixed (job level fixed-priority); but some systems can vary the priority of a job after it has started (job level dynamic-priority) • Job level dynamic-priority usually very inefficient
Fixed-Priority Scheduling: Rate-Monotonic • Best known fixed-priority algorithm is rate-monotonic scheduling • Assigns priorities to tasks based on their periods • The shorter the period, the higher the priority • The rate (of job releases) is the inverse of the period, so jobs with higher rate have higher priority • Widely studied and used • For example, consider a system of 3 tasks: • T1 = (4, 1) ⇒ rate = 1/4 • T2 = (5, 2) ⇒ rate = 1/5 • T3 = (20, 5) ⇒ rate = 1/20 • Relative priorities: T1 > T2 > T3
Fixed-Priority Scheduling: Deadline-Monotonic • The deadline-monotonic algorithm assigns task priority according to relative deadlines – the shorter the relative deadline, the higher the priority • When relative deadline of every task matches its period, then rate monotonic and deadline-monotonic give identical results • When the relative deadlines are arbitrary: • Deadline-monotonic can sometimes produce a feasible schedule in cases where rate-monotonic cannot • But, rate-monotonic always fails when deadline-monotonic fails =>Deadline-monotonic preferred to rate-monotonic
Schedulability Tests • Simulating schedules is both tedious and error-prone… can we demonstrate correctness without working through the schedule? • Yes, in some cases! This is a schedulability test • A test to demonstrate that all deadlines are met, when scheduled using a particular algorithm • An efficient schedulability test can be used as an on-line acceptance test;clearly exhaustive simulation is too expensive for this!
Exercise your brain muscle • Assume that you have a system of periodic, independent, pre-emptible tasks to be scheduled on a single processor, T = {Ti} for i = 1..n, where Ti = (φi, pi, ei, and Di) for each i.
(a) Assume that pi = Di for each i. What is the schedulability condition of the Rate Monotonic algorithm for this system? Is this a necessary and sufficient condition? (b) Assume that pi ≤ Di for each i. Under what conditions will the schedulability of the Rate Monotonic algorithm for this system be identical to that stated in response to part (a) above?