Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014. Overview of Project Schedule. Existing Site and Traffic Pattern. 575 Herndon Parkway Parcel #225. 593 Herndon Parkway Parcel 227. 198 Van Buren Parcel #226. Pavilion Site.
E N D
Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014
Existing Site and Traffic Pattern 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Site
Existing Underground SWM 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Site
PHASE 1.1 - Target Start: February 2016, Duration: 1 Month • Install Fence 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Site
PHASE 1.1 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226
PHASE 1.1 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Laydown
PHASE 1.1 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Laydown
PHASE 1.1 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall • Build Construction Access 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown
PHASE 1.2 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall • Build Construction Access • Install Fence 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown
PHASE 1.2 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall • Build Construction Access • Install Fence • Demo Median 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown
PHASE 1.3 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall • Build Construction Access • Install Fence • Demo Median • Construct New Aisle 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown
PHASE 1.3 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall • Build Construction Access • Install Fence • Demo Median • Construct New Aisle • Relocate Dumpster • Pave to Existing • Permanent Traffic Shift 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown
PHASE 2 - Target Start: March 2016, Duration: 2 Months • Relocate Existing Utilities • Install New Utilities • Relocate Transformer 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown
PHASE 3 - Target Start: May 2016, Duration: 4 Months • Erect Service Crane • Excavate • Install Footings • Install FDN/SOG • Concrete Columns/Beams • Install Precast Concrete 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Crane Pavilion Laydown
PHASE 4 - Target Start: September 2016, Duration: 5 Months • Install Escalators • Erect Pedestrian Bridge 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Crane Pavilion Laydown
PHASE 4 - Target Start: September 2016, Duration: 5 Months • Install Escalators • Erect Pedestrian Bridge • Install Curb & Gutter • Install Pavers • Install Sidewalks • Install Finishes 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Crane Pavilion Laydown
PHASE 5 - Target Start: February 2017, Duration: 2 Months • Remove Service Crane 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Pavilion Pavilion Site
PHASE 5 - Target Start: February 2017, Duration: 2 Months • Remove Service Crane • Install Sidewalk 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Pavilion Site
PHASE 5 - Target Start: February 2017, Duration: 2 Months • Remove Service Crane • Install Plaza & Sidewalk • Install Landscaping 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Pavilion Site
PHASE 5 - Target Start: February 2017, Duration: 2 Months • Remove Service Crane • Install Plaza & Sidewalk • Install Landscaping • Remove Fencing 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Pavilion Site
Parking Impacts – Parcels 225 and 227 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Pavilion Site