1 / 10

STEREO Science Center Status Report

STEREO Science Center Status Report. William Thompson NASA Goddard Space Flight Center. Phase E Kickoff Meeting February 23, 2007. SSC Requirements. Archive Status. Currently working: Telemetry ingest Archiving of MOC data products Level-0 telemetry organized by year and month

Download Presentation

STEREO Science Center Status Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STEREO Science CenterStatus Report William Thompson NASA Goddard Space Flight Center Phase E Kickoff Meeting February 23, 2007

  2. SSC Requirements

  3. Archive Status Currently working: • Telemetry ingest • Archiving of MOC data products • Level-0 telemetry organized by year and month • Generating DSN schedule summary page • Archiving of instrument data • SECCHI, PLASTIC, SWAVES • Virtual Solar Observatory • Serving SECCHI and PLASTIC data • Software distributed through SolarSoft library • Organization of SPICE ephemerides within SolarSoft • SPICE orbit web browser, “Where is STEREO?”

  4. STEREO Orbit Tool • Web-based tool for plotting STEREO’s position in the solar system. • Can also plot Ulysses and Messenger positions, Parker spiral. • Also prints out summary information. • Uses IDL RPC server, with a PHP front-end.

  5. Beacon Status • Ephemerides and viewperiod files being generated for ground stations. • Successful tests of beacon reception Chilbolton, England and Koganei, Japan • Locked onto both spacecraft and recorded telemetry • Sent telemetry through socket connection to SSC server • Automatically processed telemetry into data files and web plots • Additional work needed send telemetry in realtime • Tests from Fairbanks, Alaska expected next week • Also processing realtime telemetry from DSN through MOC interface. • Processing SECCHI, IMPACT, PLASTIC • Realtime SECCHI beacon images are now online. • IMPACT/PLASTIC plots are imminent • SWAVES onboard software change by end of month

  6. Beacon & Daily Summary Plots In-situ plots & data not yet “live”

  7. Science Coordination Status • Science planning web pages: • Current plans • Archived as-run plans • DSN Schedule Summary • Weekly meeting minutes • Early Orbit Summary • STEREO Orbit Tool Planning Calendar & Meeting Minutes DSN Summary

  8. Education & Public Outreach Includes coordination with NASA Portal Galleries, classroom activities, etc.

  9. Future Work • Beacon processing: • Need new software from instrument teams (IMPACT, SWAVES) • Daily summary plots: • Same comments as above • Need to incorporate non-STEREO data • SolarSoft has software to retrieve WIND, ACE, SOHO data • Image/plot search tool • Plan to build on SOHO tool • “Latest events” pages under development