1 / 31

OPSM 301 Operations Management

Ko ç Un iversity. OPSM 301 Operations Management. Class 8: Project Management: Introduction and CPM. Zeynep Aksin zaksin @ku.edu.tr. New module: outline. Chapter 3 from textbook: will skip parts on AOA networks Two sessions on theory Two sessions applications and Microsoft Project

catori
Download Presentation

OPSM 301 Operations Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Koç University OPSM 301 Operations Management Class 8: Project Management: Introduction and CPM Zeynep Aksin zaksin@ku.edu.tr

  2. New module: outline • Chapter 3 from textbook: will skip parts on AOA networks • Two sessions on theory • Two sessions applications and Microsoft Project • MS Project available in SOS Z15 computer lab

  3. Why project management? • Competition through new product development • Information-intensive products: costly to produce, cheap to reproduce • Flatter organizations • Systems approach • Project approach

  4. Project • A single “product” is obtained from the completion of a project • The differentiating characteristic of projects from processes is the intense uncertainty in projects • Two types of project • With absolute deadline: olympic stadium • With relative deadline : new product development project • Successful project management: To finish on time without going over budget and without sacrificing from the scope of the project

  5. Project Management • Examples • Construction • R & D • Computer system implementation • Product development • Advertising campaign • Business Plan

  6. Project Life Cycle:A Facility Construction Example • Feasibility: project formulation, feasibility studies, strategy design etc. A go/no-go decision is made at the end of this phase • Planning and design: base design, cost and schedule, contract terms, and detailed planning • Production: manufacturing, installation and testing. The facility is substantially completed at the end of this phase • Turnover and start-up: final testing and maintenance. The facility is in full operation at the end of this phase

  7. ProjectManagement Resources Scope Budget Schedule

  8. Some observations • Most projects • Either go over time • or over budget • or the promised content cannot be delivered • Little’s law: more projects in the system (WIP), longer completion times

  9. Modern Project Management • The process of project management has two dimensions: the “science” and the “art” of project management • Technical: defining, planning and controlling • Socio-Cultural: • stimulating teamwork and personal motivation • identifying and resolving problems • shaping customer expectations • sustaining political support of top management • monitoring subcontractors • negotiating with functional managers

  10. Project Planning, Scheduling, and Controlling

  11. Structuring Projects:Pure Project • The project manager has full authority over the project. • Team members report to one boss. • Shortened communication lines. • Team pride, motivation, and commitment are high. Advantages • Duplication of resources. • Organizational goals and policies are ignored. • Lack of technology transfer. • Team members have no functional area "home." Disadvantages

  12. President Research and Development Engineering Manufacturing Project A Project B Project C Project A Project B Project C Project A Project B Project C Structuring Projects Functional Project

  13. Structuring Projects Functional Project • A team member can work on several projects. • Technical expertise is maintained within the functional area. • The functional area is a “home” after the project is completed. • Critical mass of specialized knowledge. Advantages • Aspects of the project that are not directly related to the functional area not done well enough. • Motivation of team members is often weak. • Needs of the client are secondary and are responded to slowly. Disadvantages

  14. President Research and Development Engineering Manufacturing Marketing Manager Project A Manager Project B Manager Project C Structuring Projects Matrix Project: Organization Structure

  15. Structuring Projects Matrix • Enhanced interfunctional communications. • Pinpointed responsibility. • Duplication of resources is minimized. • Functional “home” for team members. • Policies of the parent organization are followed. Advantages • Too many bosses. • Depends on project manager’s negotiating skills. • Potential for suboptimization. Disadvantages

  16. Work Breakdown Structure • 1. Project • 2. Major tasks in the project • 3. Subtasks in the major tasks • 4. Activities (or work packages) to be completed

  17. The Work Breakdown Structure 1. House 1.2 Heating System 1.3 Interior Design 1.1 Building/Structure 1.4 Garden/Parking 1.2.1 Piping 1.2.2 Furnace 1.2.3 Fuel Tank 1.2.4 Solar Panels WP-FT1WP-FT2WP-FT3 WP-SP1 WP-SP4 WP-SP2 WP-SP5WP-SP3 WP-P1WP-P2WP-P3 WP-F1WP-F2

  18. Time planning: activity list Activity A B C D E F Predecessor -- A B, D -- D E

  19. A, 3 B, 5 C, 3 Start Finish D, 2 E, 2 F, 5 Activity-on-node network diagram (or PERT diagram)

  20. 5 9 3 1 0 8 11 7 2 4 6 10 Developing Project Network • Rules: • Draw networks from left to right • Each activity has a unique identification number • An activity’s identification number should be larger than that of the activities’ preceding it • Loops (cycles) are not allowed • Conditional statement (e.g., if this happens then …) are not allowed • If there are multiple start or finish activities, a common start or finish node is used

  21. A B A, 3 B, 5 C, 3 C Activity Start Finish D E D, 2 E, 2 F, 5 F Time Gantt chart: Early start

  22. A B A, 3 B, 5 C, 3 C Activity Start finish D E D, 2 E, 2 F, 5 F Time Gantt chart: Late start

  23. PERT/CPM Network Diagrams • Advantages • Allows visualization of task relationships • Facilitates calculation of critical path • Clarifies impact of decisions on downstream activities • Disadvantages • Complex, not easy to comprehend at a glance • Charts don’t readily depict durations, dates, and progress

  24. JAN FEB MAR 1 8 15 22 29 5 12 19 26 5 12 19 26 Gantt Charts • Advantages • Easy to understand • Easy to show progress and status • Easy to maintain • Most popular view to communicate project status to client and/or senior management • Disadvantages • Can be superficial • Not always easy to visualize precedence relationships

  25. Terminology • The early start (ES) time for an activity is equal to the maximum early finish (EF) times of all of its predecessor activities • ES=max (EF) of predecessors • The early finish (EF) time for an activity is equal to the early start (ES) time plus the expected activity duration (ET) for the activity EF=ES+ET

  26. Terminology • The late finish (LF) time for an activity is equal to the minimum late start (LS) times of all of its successor activities • LF=min(LS) of successors • The late start (LS) time for an activity is equal to the late finish (LF) time minus the expected activity duration (ET) for the activity • LS=LF-ET • Total slack (TS) time of an activity: • TS = LS-ES=LF-EF

  27. Activity Name Earliest Start Earliest Finish ES EF Latest Start LS LF Activity Duration Latest Start and Finish Steps Latest Finish

  28. A ES EF LS LF Finding the Critical Path B Start at time t=0 4 7 3 6 9 D 0 4 11 9 4 2 0 4 9 11 C 4 9 Activity Slack: S = LS-ES, or S = LF-EF 4 9 5

  29. A Finding the Critical Path Activity Slack: S = LS-ES, or S = LF-EF B S=2 4 7 3 S=0 6 9 S=0 D 0 4 11 9 4 2 0 4 9 11 C 4 9 Critical Path: Path with zero activity slacks 4 S=0 5 9

  30. Finding the Critical Path • Start from the left (start node). For node 0: ES=0,EF=0 • For each activitity find Early Start (ES) by checking all immediate predecessors Early Finish times. ES of activitiy=max(EF) of all predecessors. EF of activity=ES+Activity time • For the late start and late finish, start calculations from the end node. • For each activity find Late Finish(LF) by checking all immediate successors of the activity: LF of activity=min(LS) of all successors LS=LF-Activity time 5. Find Slack times for all activities, S=EF-ES=LF-LS 6. All activities with S=0 are on the critical path (there can be more than one critical paths)

  31. A C F F 0 2 2 4 4 7 H H H A 2 C 4 13 0 2 10 2 2 3 E H Slack=0 Slack=0 Slack=6 4 8 13 15 0 0 H F H H Start 8 4 15 13 0 0 4 2 0 Slack=0 Start B D G B D G 0 3 3 7 8 13 H H H 4 8 13 1 4 8 3 4 5 Slack=1 Slack=1 Slack=0 AON Network for Milwaukee General Hospital Slack=0

More Related