An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Planning : Focus on the next 6months East Hall under construction - 1962 E. Harrouch

  2. Linear planning : EDMS 1771976 (03-07-2019) • Gantt : EN-EA Planning SharePoint (Updated weekly) Index • Important info : • Bldg. Envelop : Not critical • Primary Area : Critical path • Secondary area : ~3month of slack available • CLOUD Run = High coactivity • B.352 : • No heavy work after Aug 2020 : ~2mo of slack • No access after Oct. 2020 : No Slack • B.251 : Service installation sequence frozen due to groups availability = Very little slack available in installation phase • B.263 : OK • Warning : Installation phase is more likely to be delayed than the dismantling phase. • -> The installation tasks in the next slides are marked in red Planning East Area PT30

  3. August 2019 • B.157 : • SMB-SE : Suspended scaffolding dismantling, from 29/07 to 20/09 • EN-CV : Destratificationfans installation, from 29/07 to 23/08 • EN-SMM : Network preparation + Laser scan, until the 02/08 • EN-HE : Dismantling of the primary area (Shielding, magnets, …), until the 11/09 • BE-ICS : Primary Area access system dismantling, from 12/08 to 16/08 • B.352 : • EN-EL : Completion of the decabling campaign, until 02/08 • B.251 : • EN-EA :False floor dismantling, until 02/08 • SMB-SE : Demolition works, painting work, from 19/08 to 30/08 Planning East Area PT30

  4. September 2019 • B.157 : • SMB-SE : Suspended scaffolding dismantling, until the 20/09 • CLOUD : CLOUD Run, from 02/09 to 15/11 • EN-EL : Decabling campaign in the primary area, from 23/09 to 29/11 (to be rediscussed) • B.352 : • EN-EL : Decabling from b352 to b157, from 23/09 to 29/11 (to be rediscussed) • EN-SMM : Network consolidation, from 23/09 to 27/09 (Could be anticipated) • B.251 : • SMB-SE : New false floor installation, from 02/09 to 20/09 Planning East Area PT30

  5. October 2019 • B.157 : • CLOUD : CLOUD Run, 02/09 to 15/11 • EN-EL : Decabling campaign in the primary area, from 23/09 to 29/11 (to be rediscussed) • B.352 : • EN-SMM : Ground marking, from 30/09 to 04/10 (Optic file to be provided by EN-EA) • EN-EA : Installation of mechanical supports, from 07/10 to 01/11 • B.251 : • EN-CV : Pipework and ventilation ducts installation, from 04/10 to 28/11 Planning East Area PT30

  6. November 2019 • B.157 : • CLOUD : CLOUD Run, 02/09 to 15/11 followed by cleaning • EN-EL : Decabling campaign in the primary area, from 23/09 to 29/11 (to be rediscussed) • EN-CV : Demin. Circuit (South side) installation (Skid, pipes, …), from 29/10 to 12/12 • B.352 : • EN-CV : Cooling circuit installation, from 04/11 to 15/11 • EN-SMM : Support levelling, from 18/11 to 29/11 • B.251 : • EN-CV : Pipework and ventilation ducts installation, from 04/10 to 28/11 • EN-EL : Transformers installation, from 25/11 to 29/11 Planning East Area PT30

  7. December 2019 • B.157 : • EN-EA : Final cleaning of the primary area, from 02/12 to 06/12(Could be anticipated) • CLOUD : CLOUD decabling, from 10/12 to 06/01 • EN-SMM: Shielding ground marking, from 09/12 to 12/12 • EN-EA : New shielding configuration installation from 13/12 to 16/01 • B.352 : • TE-MSC: Magnets installation, from 02/12 to 10/01 • B.251 : • EN-EL : Cable trays installation, from 29/11 to 09/01 Planning East Area PT30

  8. Summary By area : • B.157 : • Roof/outside : High coactivity in the coming weeks, but the end is soon … • Primary area : Baseline planning has no slack, anticipation of decabling activities may give us some, • Fast access areas : Slack generally available but high coactivity is expected during the whole worksite, • CLOUD : Everything is ready for the CLOUD RUN, cleaning/decabling at the end of the RUN is very important for the other activities • B.352 : Good progress of decabling activities may allow some anticipation, first beamline installation (End of this year) • B.251 : is on its critical path already, • Don’t forget to communicate any delay in your delivery schedules or if you can anticipate any task. Planning East Area PT30

  9. Thanks for your attention ! Planning East Area PT30