Framework schedule from YETS 2015 to LS3

Framework schedule from YETS 2015 to LS3. Marzia Bernardini, on behalf of OSS team Joint LIU and HL-LHC meeting, 15 th October 2015. Contents. General information YETS and EYETS - activities related to regular maintenance - length of YETS and EYETS for LHC and Injectors LS2

charity
Download Presentation

Framework schedule from YETS 2015 to LS3

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Framework schedule from YETS 2015 to LS3 Marzia Bernardini, on behalf of OSS team Joint LIU and HL-LHC meeting, 15th October 2015

  2. Contents General information YETS and EYETS - activities related to regular maintenance - length of YETS and EYETS for LHC and Injectors LS2 - Framework for LHC - Framework for Injectors Beyond LS3: overview for LHC and Injectors Methodology & Interfaces with EN-MEF Coordination & Schedule & Safety aspects Conclusion M. Bernardini - 15th October 2015

  3. Overview & Contingencies • Contingency strategy • There are NO contingencies in the global schedule, from the general coordination point of view • For the Injectors, a long recommissioning period is foreseen to mitigate potential issues related to the restart of the machines M. Bernardini - 15th October 2015

  4. YETS regular maintenance & tests LHC - CV maintenance in LHC and its Experiments 10 wks • Safety tests (mainly during Christmas Break) by GS-ASE and EN-EL • Minor regular maintenance on cryogenic equipment and rotating machines • LHC Recommissioning  1 wkcan be considered as baseline if not major interventions occur during the YETS Regular maintenance activities on other equipment are performed in the shadow of the activities listed above • In conclusion the minimum length (beam to beam) of the YETS for LHC is 13 wks(including the Christmas Break) M. Bernardini - 15th October 2015

  5. YETS regular maintenance & tests SPS • Hardware tests (mainly magnet tests) before and after the shutdown 2wk • CV maintenance for SPS (not including North Area)  6wks • Activities related to Recommissioning by BE-OP3 wks can be considered as a baseline, but this duration can evolve • The safety tests by GS-ASE and EN-EL Regular maintenance activities on other equipment are performed in the shadow of the activities listed above • In conclusion the minimum length (beam to beam) of the YETS for the SPS is 13 wks* (including the Christmas Break) * The RP cool down period is not included M. Bernardini - 15th October 2015

  6. YETS regular maintenance & tests PSB & PS • Hardware tests (mainly magnet tests) before and after the shutdown 1wk • CV maintenance for PSB, PS, Linac2 and Linac4 (not including Isolde, AD, East Area, CTF3 and n-TOF)  5wks • Activities related to Recommissioning by BE-OP 3wks can be considered as a baseline, but this duration can evolve • The safety tests by GS-ASE and EN-EL Regular maintenance activities on other equipment are performed in the shadow of the activities listed above • In conclusion the minimum length (beam to beam) of the YETS for the PS and PSB is 11 wks* (including the Christmas Break) * The RP cool down period is not included M. Bernardini - 15th October 2015

  7. YETS: reality vs baseline YETS 2015-2016 and 2017-2018 • LHC & SPS: YETS kept to 13 wks • PSB and PS: duration aligned to LHC and SPS. Due to the following requests: • Decabling project and its implementation strategy; • Anticipation of LIU activities during YETS Duration of YETS 2015-2016 & 2017-2018 M. Bernardini - 15th October 2015

  8. EYETS 2016-2017 LHC In addition to the baseline there was a request from CMS to anticipate works of LS2, to prepare the Experiment to cope with the 2e34 cm-2s-1 luminosities. These works imply the full opening of Endcaps and impact the duration of the YETS INJECTORS The implementation strategy of the decabling project foresees a massive decabling campaign in the PSB during the Year End Technical Stop 2016-2017 Extended Year End Technical Stop 2016-2017 M. Bernardini - 15th October 2015

  9. LS2 Framework for LHC During the LS2 three main categories of activities will be implemented • Maintenance: Cryogenics, Cooling and Ventilation, Vacuum, Electrical Systems, Collimation, Access System, Fire detection, ODH, … • Projects: HL-LHC • Consolidation & Other activities: this concerns all equipment in the LHC machine LS2 Days: https://indico.cern.ch/e/436424 The Baseline as for Chamonix 2014 foresaw a Length of LS2 of 18 Months, but following the requests of the Hi-Lumi LHC project and the outcomes of the cost and schedule review, the Length of LS2 is now extended to 24 Months. M. Bernardini - 15th October 2015

  10. HL-LHC Installation Overview for LS2 Courtesy Paula Alvarez Lopez – LS2 Days High bandwidthpick-ups Prep. works halo diagnostic systems New transp. refrigerator New Q5 In-situ a-C coating TCSPM TAXN Mask for D2 Fast wire scanners TDIS Cryo-bypass+TCLD Mask for D1 BGV Author DPT-GRP

  11. For HL-LHC LS2 willbe the period of D(TH)RILLING! Courtesy Lucio Rossi – LS2 Days L.Rossi

  12. LS2@LHC: Proposal of First Draft skeleton TESTS and WARM UP CRYO Maintenance ELECTRICAL Maintenance & Consolidation Magnets replacement Other activities… HL activities @ P2, P4, P6 and P8 Lift replacement HL activities @ LSS7 Cool Down @ P7 COOL DOWN, TESTS and HWC Depending on the cool down and warm up sequence Windows available for activities  Between 18 and 22 Months

  13. LS2 Framework for Injectors Defined by LIU project L4 7 months PSB 15.5 months PS 11.5 months SPS 18 months Start of LS2 for the injectors: • Surface activities for Linac2, Linac4 and PSB machines will start in November 2018, during tunnel RP cooling. • All other surface activities for PS and SPS will start at the end of the ion run, in December 2018. Please refer to Julie’s talk during this session Courtesy Julie Coupard – LS2 Days M. Bernardini - 15th October 2015

  14. Beyond LS2 YETS 2021-2022 & YETS 2022-2023  13 wks for LHC & Injectors (beam to beam); equivalent to YETS 2015-2016 & 2018-2019 LS3 for LHC 30 months mainly for HL project LS3 for Injectors  12 months M. Bernardini - 15th October 2015

  15. Methodology and interfaces with EN-MEF M. Bernardini - 15th October 2015

  16. Methodology and interfaces with EN-MEF • SCHEDULING & SAFETY COORDINATION • Coordination meetings are held by the different facility’s coordinators to plan the activities during YETS and LS2 • Groups announce their activities, technical and safety aspects, interfaces are discussed • Facility coordinators gradually will refine the schedule and the organization M. Bernardini - 15th October 2015

  17. Methodology and interfaces with EN-MEF From Space Reservation (Project Phase) to ECR (Installation Phase) Space reservation • Existing situation and introduction • Reason for the change • Detailed description • Impact on other items • References ECR • Existing situation and introduction • Reason for the change • Detailed description • Impact on other items • Impact on items/systems • Impact on utilities and services • Impact on cost, schedule and performance • Impact on operational safety • Elément(s) important(s) de sécurité • Other operational safety aspects • Worksite safety • Organization • Regulatory tests • Particular risks • References M. Bernardini - 15th October 2015

  18. Global picture Coutesy K. Foraz – LS2 days HL-LHC Upgrade Consol. R2E LIU Maintenance Schedule & Coordination Worksite Coordination Config. managt Integration Safety M. Bernardini - 15th October 2015

  19. LS2 Project Priorities (by decreasing priorities) Realisation phase • Safety • Quality • Schedule Approval phase • Safety • Activities needed to reach 300 fb-1(Integrated Luminosity) during run3 • HL-LHC and LIU projects • Approved projects • Approved studies • Others M. Bernardini - 15th October 2015

  20. LS2 Project: main dates and milestones LS1PostMortem LS2Day LS2Day LS2Day PLANis madeavailable ConsolidatedList of tasksto DirectorA&T 1st stepfinalvalidation Finalvalidation Coutesy J. Ph. Tock – LS2 days LS2 Days 30th September2015 • LS1 Post Mortem: 1st trimester’15 • Start date: Mid December 2018; • Duration: 24 months (end 2020) • Yearly “LS2 day” as of 2015 • Activities declared in Plan by end’15 both for injectors and LHC; • March’16, definition of activities for EYETS 2016; • Mid’16, definition of activities for YETS 2017 and LS2; • Preliminary “final” validation: mid 2017.

  21. Conclusion • The YETS and EYETS are mainly dedicated to annual maintenance in the LHC and its Injectors. Nevertheless major projects as decabling project, LIU and HL-LHC will profit for these times to anticipate activities related to LS2 • The LS2 duration has been re-adjusted to allow the completion of major activities related to LIU and HL-LHC: • From 18 months to 24 (+4) months for LHC & its Injector chain • The LS2 in Injectors is mainly dedicated to the implementation of LIU project • The LS2 in LHC is mainly dedicated to major maintenances, HL-LHC and civil engineering activities in preparation of LS3 • The LS2 committee set the priorities for the LS2 Project, as well main dates and milestones M. Bernardini - 15th October 2015

  22. M. Bernardini - 15th October 2015