An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Construction Cost Estimanting 4003Cost Estimating/EngineeringConcrete Structures Prepared by: Ebrahim A Alkooheji Instructor: Proff. Locurcio

  2. Problem 5-1 • How many cubic yards of concrete are required to construct a: • 3000 psi reinforced concrete • 100’ x 30’’ x 12’’ • 8% Waste

  3. COUNTINUE • Convert all units to LFT : • 100 ft • 30’’/12= 2.5 ft • 12’’/12= 1 ft 2. Find Volume: • 100’ x 2.5’ x 1’= 250 CF 3. Convert to cy: • 250/27= 9.25 CF

  4. Countinue 4. Add 8% Waste: • 9.25 CYx 1+ (8/100)= 9.99 CY = 10 CY

  5. Problem 5-3 • Calculate the cost of materials & labor to construct the rebar for the footing in problem 5-1: • Rebar #4 • Overlap is to be 18’’ • Allow 3’’ cover of the rebar at both ends. • Each bar is 20’ long • Include 6% sales tax on all material

  6. Countinue • 5 piece of 20ft + 7ft is required for each span = 6 piece for each span • 6 piece #4 rebar x 4 = 24 pieces are required

  7. Continue • A #4 rebar weight = 0.668lb/LF • Total span = 24 LF each span x 20 LF = 480 LF • Total weight = 0.668 lb/LF x 480 LF = 320.64 lb • Convert lb to Ton for RS-Means: 320.64 lb/2000= 0.16 Ton

  8. Continue

  9. Problem 5-32 • Prepare an estimate for the cost of material & labor to construct the continuous footing from the drawings: • 4000 psi fiber reinforced structural concrete. • Include cost of forms • Fiber reinforcing • Concrete • Placement labor & Equipment • Include 10% waste

  10. Figures

  11. Continuous Footing • Calculate total LF: • 16’ +22’+28’+13’+(28’+12’-16’=24’)+(22’-13’=9’) = 112 LF 2. Find volume: • 112 Lf x 2 x 1= 224 CF 3. Convert cf to cy: 224cf/27 = 8.29 = 8.3 CY 4. Add waste: 8.3 x (1+10/100)= 9.125 = 9.25 CY

  12. Continuous Footing

  13. Form work

  14. Continue

  15. Continue

  16. Bahrain