P14415:P3 Arborloo Plastic Base Development. Week 3 Project Planning Review 9/12/13. Team Members. Agenda. Background and Project Definition Stakeholders Key Deliverables Customer Requirements Engineering Requirements House of Quality
E N D
P14415:P3 Arborloo Plastic Base Development Week 3 Project Planning Review 9/12/13
Agenda Background and Project Definition Stakeholders Key Deliverables Customer Requirements Engineering Requirements House of Quality Project Schedule/Work Breakdown Structure/Gantt Chart Closing Comments: Issues, Corrective Actions, and Q&A
Background Information • Inadequate sanitation is a major cause of preventable illnesses in children around the world. According to UNICEF, diarrhea alone causes over 1.6 million deaths in children under 5. These illnesses can easily be prevented by improving sanitation. However, cost is a major barrier limiting the adoption of sanitation in Haiti. • Peter Morgan’s Arborloois a simple latrine built over a small pit, which when filled is then moved to a new pit location. The old, filled pit then has vegetation planted on top of it, such as a fruit tree.
P14415 Problem Statement • Current State • Difficult to adopt in rural areas due to high cost and transportation difficulties • Desired State • A low cost, portable, easy to assemble, and aesthetically pleasing arborloo base that can be financed in parts • Project Goals • Analyze the current arborloo design to find opportunities to incorporate plastic • Help improve sanitation in Haiti • Constraints • System must be financeable in parts • Design must incorporate plastic • Design must be compliant with the skills and tools available to the intended population
Stakeholders • Haitian citizens • Environmental Protection Agency • Possible Manufacturers • RIT • MSD Team
P14415 Key Deliverables • 3 to 4 Detailed Designs • 2 Functional Prototypes • Bill of Material • Test Plan and Documented Results
Process to Develop Customer Requirements • PRP – Rough cut • Generated list of possible customer needs • Customer Interview – Refinement • Refined list: addition/removal & Importance • Expert Interview • Asked the “Why’s” to resolve final list “Cost is the number 1 factor blocking the adoption of sanitation in Haiti” – Pedro Cruz
References • 1. "Water, Sanitation and Hygiene." UNICEF. Web. 07 Sept. 2013. http://www.unicef.org/wash/index_wes_related.html