Caltrain Modernization Program UpdatePalo Alto City Council Rail CommitteeAugust 10, 2012
Presentation Topics • State Legislature Update • Next Steps for the Peninsula • Blended System Planning Analysis Update • Discussion
Green Light for HSR & Blended System • Bay Area State Assembly and Senate support • Elaine Alquist, D-San Jose • Tom Ammiano, D- San Francisco • Jim Beall, D-San Jose • Nora Campos, D-San Jose • Paul Fong, D-Mountain View • Rich Gordon, D-Menlo Park • Jerry Hill, D-San Mateo • Mark Leno, D-San Francisco • Fiona Ma, D-San Francisco • Leland Yee, D-San Francisco
SB 1029 • Appropriates $705 million for Caltrain Modernization • $600 million from Prop 1A (HSR) • $105 million from Prop 1A (Connectivity) • Funds available for: • “blended system improvements consistent with the MOU” and • “shall not be used to expand the system to a dedicated four-track system” • Bonds sold and allocated to project by State Controller
Project Delivery Focus • Early Investment (2019) • Define outreach/decision-making structure and process • Advanced Signal System • Advance design from “Critical” to “Final” • Electrification & Electric Vehicles • Update / Recirculate Caltrain EA/EIR • Define project delivery approach/team • Blended System (2029) • Complete current planning studies • Schedule for completing planning process
Capacity Analysis Service Plan / Operations Considerations Grade Crossing & Traffic Analysis Infrastructure Need Fleet Need Revenue / Cost Service Plan Options Decision-Making Matrix Blended System Alternatives Design & Environmental Review Blended System Planning Process
Blended System • Service Plan/Operations Considerations Analysis
Purpose / Goals • Consider service / operations variables not included in capacity analysis • Requested by stakeholders • Inform development of service plan options
Simulation Model Results • 4 Track Options • 3 Track Option • Model: high performance • Practice: further evaluation
Blended System • Grade Crossing & Traffic Analysis
Study Purpose & Goals • 40 at-grade crossings • Identify relationship between: • Train service levels • Gate down time • Local traffic • Analyze future scenarios (2035): • Impacts from Caltrain versus future growth • Difference between service plan options • Improvement recommendations