1 / 8

Project Boring MMMM

Project Boring MMMM. Team Mr. Geoffrey Friason Mr. Michael Braun Mr. Eric Yost. Advisors Dr. Aziz Inan Dr. Peter Osterberg Industry Representatives Mr. Wes Mickanin Mr. Jared A. Hay. Overview. Scorecard Additional Accomplishments Plans, Milestones, etc. Issues/Concerns Conclusions.

chip
Download Presentation

Project Boring MMMM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project BoringMMMM Team Mr. Geoffrey Friason Mr. Michael Braun Mr. Eric Yost • Advisors • Dr. Aziz Inan • Dr. Peter Osterberg • Industry Representatives • Mr. Wes Mickanin • Mr. Jared A. Hay University of Portland School of Engineering

  2. Overview • Scorecard • Additional Accomplishments • Plans, Milestones, etc. • Issues/Concerns • Conclusions University of Portland School of Engineering

  3. Scorecard • Assemble alpha hardware prototype • Hall sensor hardware functional; PIC, LCD not verifiable currently • Theory of Operations completion • Approved • Create test scenarios • Not documented – will be done tomorrow • Get approval of Change Control Board • Absolutely University of Portland School of Engineering

  4. Additional Accomplishments • Ordered extra Hall effect sensors • Ordered Lexan for casing • Verified operation of components • ADC • AMUX • LCD • Adjusted code to new ADC • Currently testing PIC functionality University of Portland School of Engineering

  5. Plans for March • Figure out how to debug firmware ASAP • Complete test case documentation by 3/2 • Have test case success by 3/21 University of Portland School of Engineering

  6. Milestones University of Portland School of Engineering

  7. Concerns/Issues • How to debug firmware • Talk to Dr. Lu about ICD2 debugging University of Portland School of Engineering

  8. Conclusions • Behind on prototype goal • Theory of Operations complete • Hardware ready for firmware debugging *pending approval of CCB University of Portland School of Engineering