An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 6 May 2010

  2. Agenda • Program Status • DAM results • Market Readiness • Follow-Up Discussion Technical Advisory Committee

  3. 208 Days to Go-Live Phase 5: Full Functionality 0 Items Impacting Go-Live Date Technical Advisory Committee

  4. 208 Days to Go-Live Phase 5: Full Functionality Market Quality Testing and Operational Readiness Achievements within Market Trials: • Market Trials has been running for 13 weeks • Phase 2.1: Market Connectivity • Real Time / Day Ahead • Qualifications • 95% of the QSEs have qualified • 99% of network model has been validated • CRR • Two monthly CRR auctions have been run and invoiced • Phase 3.0: Real Time Markets • Six month LMP analysis started on March 1st • The $2,250 cap on prices has only been reached a few times since 03/04/10 • Phase 4.0: DAM / RUC • Nine DAM runs have been completed • Running twice a week • DRUC • DAM / Real Time Settlement • Strong participation from the Market Participants (191 QSEs on Thursday April 29th ) • Upcoming Milestones for Market Trials: • Reporting support for DAM/RUC/SAS • CMM Module • DAM / RUC 3x/wk • DAM / RUC 5x/wk • Closed Loop LFC • Phase 5: Full Functionality • 168 HR Test • System Cut-Over Technical Advisory Committee

  5. Integrated Nodal Timeline – Go-Live December 1st, 2010 Technical Advisory Committee

  6. 2010 Market Trials Timeline – Go-Live December 1st, 2010 Technical Advisory Committee

  7. 208 Days to Go-Live DAM Summary • Issues with DAM: • Intermittent issues with CRR performance and availability since Monday, May 3rd • Correcting Market Bid/Offer IDs with special characters (4/29) • The AS Awards file had an issue with publishing after DAM. (4/27) • Encountered a known issue where MMS cannot handle multiple Load Resources mapped to a single Load point in the model (4/13, 4/15) Technical Advisory Committee

  8. 208 Days to Go-Live Market Trials 5.0: Full Functionality: Day 1 Summary • Tuesday May 4th for Operating Day Wednesday May 5th • 174 QSEs participated • 20,261 - 27,435 MWs Solution Range • $13.69 - $47.34 Solution Price Range • Several Issues involving the first full run • Credit limit data was missing for Op Day 5/5.  Cause was linked to the DSV load yesterday.  DAM submission timeline extended until 11am. • DAM Operators tried to work around the outages defect (Patch 7 fixes the issue). NDP errored out due to missing data in the RDB database.  ERCOT is investigating a possible ABB defect. • Once issue was fixed, DAM was rerun.  DAM then errored out due to the known issue with the decimal combination in a few specific bids. • Implemented manual workaround.  Reran DAM.  Results posted around 2:50 pm. DRUC was delayed until 3:52pm, but completed and was published. Technical Advisory Committee

  9. Communication Channels For Market Participants • Issue Management • Market Participants will report all issues using the markettrials@ercot.com email address • Business oriented issues • Initially reviewed by the ERCOT Wholesale Client Services Account Managers • If required, issues are escalated to the Market Trials Lead responsible for that functional area • More complex or in-depth questions will be ultimately escalated to a Subject Matter Expert (SME) • Technical issues • Initially reviewed by the Market Trials Technical Generalist for initial triage • If required, issues will be escalated to IT Production Support • If determined to be a variance / defect, ERCOT will leverage our existing defect management process to estimate, analyze and prioritize the resolution • Our goal is that all questions will be responded to within 24 hours • Typically responses are that same business day • If you have not received a response within 24 hours, feel free to re-forward • ERCOT will maintain a known issues spreadsheet for each functional area on the Nodal Readiness center • Will be updated every Friday by EOB (note that if no new known issues are discovered or closed, the spreadsheet will remain static) • Known issues will be added as a standing agenda item on the Friday Market calls Technical Advisory Committee

  10. Go-Live BUSINESS PROCESS TEST ICCP Quality SE Quality Solution/ Data Quality HRUC Integrated Credit Management 1 Day Dual Entry Model Load /Validation Processes SASM Business Stability Contingencies UI Performance Improvements DAM RTM ICCP Point Checkout DRUC Phase 5:Full Functionality SCED RARF Integration MARKET TEST CRR INVOICES Phase 5:Full Functionality Solution/ Data Completeness DAM PERFORMANCE & LOAD TEST Model Baseline Testing May Auction System Stability Integration Phase 4: DAM/RUC INTEGRATION TEST Functional Completeness Functional Stability FA/SA TEST Test Activities Business Quality NMMS RTM EMS OS CRR DAM COMS CMM REG REPORTS MT 2.1 SEM MT 4.0 MT 5.0 MT 3.0 Technical Advisory Committee

  11. Nodal Defects Trends - High Priority (Must Fix Before Go-Live) • Defect counts decreased due to planned defect migrations into Nodal ITest. • Primary source for Open defect counts are EIP, EMS, MMS, and NMMS. Technical Advisory Committee

  12. Nodal Program Risks & Issues Technical Advisory Committee

  13. Market Readiness Vikki Gates Readiness & Transformation

  14. Participant Readiness Touch Points 2010 May June July August Meetings • NATF 5/4 • NATF 6/1 and 6/29 • TBD • NATF 8/3 and 8/31 • Nodal 101 • Transmission 101 • Generation 101, 201 • CRR – instructor-led • NMMS • Economics of LMP • NOIE QSE Operations • Nodal 101 • LSE 201 • Generation 101, 201 • Economics of LMP • CC Workshop • VC Workshop • AS Workshop • Retail Workshop • Nodal 101 • Transmission 101 • Generation 101, 201 • Basic Training Program • NOIE QSE Operations • Settlements 301 • Nodal 101 • Transmission 101 • Generation 101, 201 • Basic Training Program • NOIE QSE Operations • Settlements 301 Training • Standby site visits • Metrics monitoring • Bi-weekly TSP calls • MRS #4 Cutover • TSP Outage Scheduler Road Show begins • Phase 5 Metrics launch • Qualification assessment (MP17) • Standby site visits • Standby site visits Outreach • Weekly Trials calls • 2 hr system-wide LFC test • Phase 5 Market Trials initiates • Weekly Trials calls • 8 hr system-wide LFC test • Full market trials functionality continues • Weekly Trials calls • 48 hr system-wide LFC test • Verifiable costs in execution • NPRR206 in execution • Weekly Trials calls • Prepare for 168 hr test Market trials Technical Advisory Committee

  15. Next 60-days of Classes and Settlement Workshops Enrollment at: http://nodal.ercot.com/training/courses/index.html Technical Advisory Committee

  16. Next 60-days of Classes and Settlement Workshops (continued) Enrollment at: http://nodal.ercot.com/training/courses/index.html Technical Advisory Committee

  17. Metrics Roadmap Timing and Design Confirmed PURPLE Timing subject to change, design in progress ORANGE New Metric N1 EMO1 MP6 MP15A EMO6 EMO10 EMO7 EMO9(A) EMO9(C) EMO9(D) MO5 MO4 N2 MP3 EMO2 EMO9(B) EMO13 EMO8 MP23 MP15B CRR3 MP20 EMO3 MO3 MO8 MP3 MP16 MO9 MO7 MO10 C10 CO8 CO5 CO3 CO9 E5 R0 CO2 C1-C10 CO4 R1 CO6 CO7 R2 CO1 IMM1 R3 CRR4 E3 E12 MP11 E7 MP14C E9 E10 E1 E11 MP17 Technical Advisory Committee

  18. CRR Metrics Active Phase 3 Metric Notes: 1. Added CRR3 participation threshold (market segment) - >= 80% participation (GREEN), >= 50% and < 80% (AMBER), < 50% (RED) Technical Advisory Committee

  19. Real-Time Metrics Active Phase 3 and 4 Metrics Notes: 1. ERCOT Criteria added to MP3 and MP15(B) – “ERCOT scores in connectivity will mirror the MP scores.” Technical Advisory Committee

  20. Day-Ahead Market Metrics • Notes: • MP16 – 10 DAM runs (as of the 5/4/2010 run) • MP16 – Metric is based on a 2 week rolling average. • MP16 – 96.5% Load participating. Technical Advisory Committee

  21. Outage Scheduler Metrics Active Phase 3 Metric Technical Advisory Committee

  22. Network Modeling Metrics Active 4 Metric • Notes: • MP6 does not include 405 QSE CB and DSC points from TSP outreach. ERCOT is determining whether these rollback into the QSER MP6 measurement Technical Advisory Committee

  23. Network Model Metrics Network Modeling Metrics Notes: 1. SE performance requirements in EMO12 moved to EMO9(A) Technical Advisory Committee

  24. Resource Entity Metrics Technical Advisory Committee

  25. Readiness Metrics Technical Advisory Committee

  26. Questions ?

  27. Appendix

  28. Nodal Program Risks & Issues: Definitions Definitions for Category, Probability and Severity of Risks & Issues: • Category • Scope : Will require a scope change • Schedule: Will require a schedule change • Budget: Will require a budget change • Probability • High : Probability to occur is ≥ 90%; perceived impact would require a Change Request over the next 1-3 months • Medium: Probability to occur is between 31 – 89%; perceived impact would require a Change Request over the next 4 -10 months • Low: Probability to occur is ≤ 30 %; not expected to require a Change Request • Severity • High: Milestone impact, or budget impact >$250,000 • Medium: Milestone impact - but expected to be mitigated, or budget impact between $0 - $250,000 • Low: No milestone impact, or no budget impact Technical Advisory Committee