100 likes | 207 Views
Modification Proposal 255 – LSP Objection Rates. Simon Trivella –27 th August 2009 Distribution Workstream. ROM Request. 3 Options put forward Option 1 (“Complex”) Option 2 (“Medium”) Option 3 (“Simple”) All present a level of complexity in data extraction & reporting
E N D
Modification Proposal 255 – LSP Objection Rates Simon Trivella –27th August 2009 Distribution Workstream
ROM Request • 3 Options put forward • Option 1 (“Complex”) • Option 2 (“Medium”) • Option 3 (“Simple”) • All present a level of complexity in data extraction & reporting • Offshore development required
ROM Request • Costs & Timescales • Development & Implementation up to £26k • Approximately 4 weeks of analysis • Approximately 12 weeks delivery (includes testing & implementation) • Annual support costs low • Requirements / Solution dependant
Sample Report • Provided to assist with discussion / development • Based on 4 months of data • Manually created • Report compares: • Number of competitive confirmations against a Users portfolio; • Number of those confirmations that have lapsed due to objection from the registered User
Sample Report • User - The existing registered Shipper (that can object) • Incoming Confirmations - The number of opportunities to object • Transfers / Successful Objections - The number of successful transfers / objections (the result of the incoming confirmations) • Successful Objections - Percentage of incoming confirmations that did not transfer due to a successful objection
Sample Report • 10,522 Incoming Confirmations (objection opportunities) • 9,363 Transfers • 1,159 Successful Objections • Successful Objection Rate of 11% • 61 Shippers (SSCs) • 42 Shippers with no objections
Modification Proposal 255 – LSP Objection Rates Simon Trivella –27th August 2009 Distribution Workstream