“Work” Word Problems

“Work” Word Problems. Today’s Date: 11/15/11. Notes on Handout. “Work” Equation. Together + Together = 1 Alone Alone Always “together Over alone + together Over alone” Always equals 1 .

cirila
Download Presentation

“Work” Word Problems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. “Work” Word Problems Today’s Date: 11/15/11 Notes on Handout

  2. “Work” Equation Together + Together = 1 Alone Alone Always “together Over alone + together Over alone” Always equals 1

  3. Ex 1) Nora needs 3 hours to chop down the tree in front of her house. Her younger brother needs 6 hours to do the same job. How much time would it take them if they worked together? Bro’s Part of Job 1 Whole Job Completed Nora’s Part of Job + = (2) (1) (6) Multiply every term to get the common denominator

  4. Example 1 cont… • Define variable: • Write the equation: • Solve: x is time together 2 hours (to complete the job together)

  5. T.O.O. SET-UP #3 Do NOT finish the problem. This time they give Sean’s time & time together, but not Ian’s time.

  6. Example 2 (#4 on WS) An inlet pipe can fill a tank in 3 hours. It takes 11 hours for the drainpipe to empty the tank. How long will it take to fill the tank if both the inlet pipe and the drainpipe are open? 1 = Inlet and Drain pipe are working against each other. So, make Drain pipe’s rate alone negative.

  7. Example 2 cont… (11) (3) (33)

  8. Example 3 (#5 on WS) Crane A can unload the container ship in 10 hours, and crane B can unload it in 14 hours. Crane A started to unload the ship at noon and was joined by crane B at 2 pm. At what time was the unloading job of the ship completed? Crane A: Started at noon (12:00) Crane B: Started at 2:00 Let x = Crane B’s time Crane A worked 2 hours more than Crane B : x + 2

  9. Example 3 cont… Once you get x, you need to add that time to 2:00 to get “WHAT TIME” job was finished. Finish for HW. Your answer will be a decimal so round to the nearest tenth and convert to “Time”

  10. T.O.O. Work with a neighbor to set up #6. Do NOT finish the problem. Clue: Larger Pump’s time is x – 7

  11. Homework #8 Finish “Work” Problems side of WS a) Define Variable b) Write equation c) Solve Products & Quotients; Sums & Differences side: do Every Other Odd (1, 5, 9, 13, 17, 21)